Question

Integrative Exercise Cost System Choices, Budgeting, and Variance Analyses for Sacred Heart Hospital The Two Cost...

Integrative Exercise
Cost System Choices, Budgeting, and Variance Analyses for Sacred Heart Hospital

The Two Cost Systems

Sacred Heart Hospital (SHH) faces skyrocketing nursing costs, all of which relate to its two biggest nursing service lines—the Emergency Room (ER) and the Operating Room (OR). SHH's current cost system assigns total nursing costs to the ER and OR based on the number of patients serviced by each line. Total hospital annual nursing costs for these two lines are expected to equal $300,000. The table below shows expected patient volume for both lines.

Measure ER OR Total
Number of patients (ER visits or OR surgeries) 1,000 1,000 2,000
Number of vital signs checks 2,000 4,000 6,000
Number of nursing hours 10,000 5,000 15,000

Required:

1. Using the current cost system, calculate the hospital-wide rate based on number of patients.

$ ____________per patient

2. Calculate the amount of nursing costs that the current cost system assigns to the ER and to the OR.

The nursing cost, assigned to the ER $_______
The nursing cost, assigned to the OR $_______

3. Using the results from Requirement 2, calculate the cost per OR nursing hour under the current cost system.
$ _______per OR hour

After discussion with several experienced nurses, Jack Bauer (SHH’s accountant) decided that assigning nursing costs to the two service lines based on the number of times that nurses must check patients’ vital signs might more closely match the underlying use of costly hospital resources. Therefore, for comparative purposes, Jack decided to develop a second cost system that assigns total nursing costs to the ER and OR based on the number of times nurses check patients’ vital signs. This system is referred to as the “vital-signs costing system.” The earlier table also shows data for vital signs checks for lines.

4. Using the vital-signs costing system, calculate the hospital-wide rate based on the number of vital signs checks.
$_______per vital signs check

5. Calculate the amount of nursing costs that the vital-signs costing system assigns to the ER and to the OR.

The vital-signs cost, assigned to the ER $_______
The vital-signs cost, assigned to the OR $_______

6. Using the results from Requirement 5, calculate the cost per OR nursing hour under the vital-signs costing system.
$________ per OR hour

Budgeting and Variance Analysis

In an effort to better plan for and control OR costs, SHH management asked Jack to calculate the flexible budget variance (i.e., flexible budget costs - actual costs) for OR nursing costs, including the price variance and efficiency variance. Given that Jack is interested in comparing the reported costs of both systems, he decided to prepare the requested OR variance analysis for both the current cost system and the vital-signs costing system. In addition, Jack chose to use each cost system’s estimate of the cost per OR nursing hour as the standard cost per OR nursing hour. Jack collected the following additional information for use in preparing the flexible budget variance for both systems:

Actual number of surgeries performed = 950
Standard number of nursing hours allowed for each OR surgery = 5
Actual number of OR nursing hours used = 5,000
Actual OR nursing costs = $190,000

Enter a favorable variance as a negative amount, and an unfavorable variance as a positive amount. If there is no variance, enter "0" and select "No variance" from the dropdown.

7. For the OR service line, use the information above and the cost per OR nursing hour under the current cost system to calculate the

a. flexible budget variance. (Hint: Use your answer to Requirement 3 as the standard cost per OR nursing hour for the current cost system.)
$________Unfavorable

b. price variance.
$__________ Unfavorable

c. efficiency variance.
$_________ Unfavorable

8. For the OR service line, use the information above and the cost per OR nursing hour under the vital-signs costing system to calculate the

a. flexible budget variance. (Hint: Use your answer to Requirement 6 as the standard cost per OR nursing hour for the vital signs cost system.)
$ __________No variance

b. price variance.
$ __________Favorable

c. efficiency variance.
$ ___________Unfavorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER

$ Hospital wide cost per patient:- Total Cost Total Patients Cost per Patient (200000/2000) = 300,000 2000 150 $ Nursing cost

_____________________________________________

If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.

*****************THANK YOU**************

Add a comment
Know the answer?
Add Answer to:
Integrative Exercise Cost System Choices, Budgeting, and Variance Analyses for Sacred Heart Hospital The Two Cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Two Cost Systems Sacred Heart Hospital (SHH) faces skyrocketing nursing costs, all of which relate to its two bigge...

    The Two Cost Systems Sacred Heart Hospital (SHH) faces skyrocketing nursing costs, all of which relate to its two biggest nursing service lines-the Emergency Room (ER) and the Operating Room (OR). SHH's current cost system assigns total nursing costs to the ER and OR based on the number of patients serviced by each line. Total hospital annual nursing costs for these two lines are expected to equal $300,000. The table below shows expected patient volume for both lines. Total Measure...

  • Budgeting and Variance Analysis In an effort to better plan for and control OR costs, SHH management asked Jack to calculate the flexible budget variance (i.e., flexible budget costs - actual costs) f...

    Budgeting and Variance Analysis In an effort to better plan for and control OR costs, SHH management asked Jack to calculate the flexible budget variance (i.e., flexible budget costs - actual costs) for OR nursing costs, including the price variance and efficiency variance. Given that Jack is interested in comparing the reported costs of both systems, he decided to prepare the requested OR variance analysis for both the current cost system and the vital-signs costing system. In addition, Jack chose...

  • A variance analysis question for cost accounting that I am struggling with. I have parts of...

    A variance analysis question for cost accounting that I am struggling with. I have parts of it completed, but there are some parts that I did not really understand. Could you please take a look and help me? I really appreciate it! Thank you very much! You may need to zoom in to see the numbers and information for this question Part 1: Calculate direct materials price and efficiency variances. Actual Costs Incurred Flexible Budget Budgeted Input Qt. Alloved for...

  • Preston’s Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Preston allocates...

    Preston’s Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Preston allocates overhead based on yards of direct materials. Please prepare a flexible budget based on the actual number of recliners sold & then (2) Compute the cost variance and the efficiency variance for direct materials and for direct labor. For manufacturing​ overhead, compute the variable overhead​ cost, variable overhead​ efficiency, fixed overhead​ cost, and fixed overhead volume variances. Round to the nearest dollar. Have Preston​'s...

  • Smith Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Smith allocates...

    Smith Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Smith allocates overhead based on yards of direct materials. The company's performance report includes the following selected data: (Click the icon to view the selected data.) Read the requirements Requirement 1. Prepare a flexible budget based on the actual number of recliners sold. (Round budget amounts per unit to the nearest cent.) 980 Smith Recliners Flexible Budget Budget Amounts per Unit Actual Units (Recliners) Sales Revenue...

  • Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come...

    Mastery Problem: Manufacturing Cost Variance (Actual Costs Compared to Standard Costs) Manufacturing cost variances may come from material costs that are higher or lower than expected, material usage that is not what was expected, higher or lower labor costs than expected, or more or less time spent to produce an item than expected. Overhead cost and volume variances are another cause for costs to be higher or lower than what was expected. The total manufacturing variance can be broken down...

  • Question 2: Cole Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system....

    Question 2: Cole Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Cole allocates overhead based on yards of direct ma The company's performance report includes the following selected data Static Budget Actual Results (975 recliners) (955 recliners) S 482,625 $ 453,625 Sales (975 recliners x S 495 each) (955 recliners x $ 475 each) Variable Manufacturing Costs: Direct Materials 52,065 52,087 Direct Labor 91,650 (5,850 yds @ $ 8.90 / yd.) (5.987 yds @ $...

  • Houston Company produces two products. Standard and Jumbo, and currently uses a costing system that accumulates...

    Houston Company produces two products. Standard and Jumbo, and currently uses a costing system that accumulates all overhead costs in a single cost pool and assigns it to products based on direct labor dollars. After completing a study that showed overhead costs were driven by factors other than volume, Houston's management has decided to implement an activity based costing (ABC) system. The study showed that manufacturing overhead costs could be associated with three activities: (1) purchasing. (2) receiving, and (3)...

  • Urban Elite Cosmetics has used a traditional cost accounting system to apply quality-control costs uniformly to...

    Urban Elite Cosmetics has used a traditional cost accounting system to apply quality-control costs uniformly to all products at a rate of 16 percent of direct-labor cost. Monthly direct-labor cost for Satin Sheen makeup is $97,000. In an attempt to more equitably distribute quality-control costs, management is considering activity-based costing. The monthly data shown in the following chart have been gathered for Satin Sheen makeup.    Activity Cost Pool Cost Driver Pool Rates Quantity of Driver for Satin Sheen Incoming...

  • Problem One: Variance Analysis The Graves Manufacturing Company's costing system has two direct-cost categories: direct materials...

    Problem One: Variance Analysis The Graves Manufacturing Company's costing system has two direct-cost categories: direct materials and direct manufacturing labor. Manufacturing overhead (both variable and fixed) is allocated to products on the basis of standard direct manufacturing labor-hours (DLH). At the beginning of 2017, the controller adopted the following standards for its manufacturing costs: 5 lb. at $5 per lb. 3 hrs. at $15 per hr. Direct materials Direct manufacturing labor Manufacturing overhead: Variable Fixed $7 per DLH $8 per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT