Question

Constructing and Assessing Income Statements Using Cost to Cost Method On March 15, 2012. Frankel Construction contracted to
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Cost to cost method
Year Cost incurred Percent of total expected cost Revenue recognized Income
2012 $30.00 35% $42.00 $12.00
2013 $35.00 41% $49.00 $14.00
2014 $20.00 24% $29.00 $9.00
$85.00 $120.00 $35.00
Add a comment
Know the answer?
Add Answer to:
Constructing and Assessing Income Statements Using Cost to Cost Method On March 15, 2012. Frankel Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Constructing and Assessing Income Statements Using Cost-to-Cost Method On March 15, 2012, Frankel Construction contracted to...

    Constructing and Assessing Income Statements Using Cost-to-Cost Method On March 15, 2012, Frankel Construction contracted to build a shopping center at a contract price of $120 million. The schedule of expected (which equals actual) cash collections and contract costs follow ($ millions): Year Cash Collections Cost Incurred 2012 $ 30 $ 10 2013 50 25 2014 40 50 Total $ 120 $ 85 (a) Calculate the amount of revenue, expense, and net income for each of the three years 2012...

  • Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is...

    Constructing and Assessing Income Statements Using Percentage of Completion On March 15, 2017, Frankel Construction is contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals actual) cash collections and contract costs follows Year Cash Collections Cost Incurred 2017 2018 2019 $30 million 15 million 50 million40 mlion 40 million 30 million Total $120 million 85 million Calculate the amount of revenue, expense, and income for each of the three years 2017...

  • Constructing and Assessing Income Statements Using Cost-to-Cost Method Assume General Electric Company agreed in May 2016...

    Constructing and Assessing Income Statements Using Cost-to-Cost Method Assume General Electric Company agreed in May 2016 to construct a nuclear generator for NSTAR, a utility company serving the Boston area. General Electric Company estimated that its construction costs would be $840 million. The contract price of $1,050 million is to be paid as follows: $350 million at the time of signing; $350 million on December 31, 2016; and $350 million at completion in May 2017. General Electric incurred the following...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $390 million. The expected completion date is April 1, 2020. lust in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2018 2019 2020 $ 60 $130 $70...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2021 $ 70 130 Costs incurred during the year Estimated costs to complete as of December 31 2022 $60 30...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $400 million. The expected completion date is April 1, 2023. just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 60 $130 $55...

  • Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction...

    Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction is scheduled to commence 1 July 2018 and the estimated date of completion is 30 June 2021. The cost of the building is estimated to be $155m and the total contract price is fixed at $180m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $’000 $’000 $’000 Costs to date 46,500 108,500 155,000 Estimated Costs...

  • Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15,...

    Exercise 5-18 Long-term contract; revenue recognition over time vs. upon project completion [LO5-9] On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington D.С., for $270 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 $ 50 $100 60...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT