Question
Construction Engineering Financial

Assignment Description: A contractor has signed a contract to pour the footing, foundation, and slab floor for a building. The contractor uses the costs codes and descriptions from RS Means (see below). The original estimate for the labor to complete the footing and foundation was $8,400 and the contractor has subcontractor the work out for $8,560. The subcontractor has billed the contractor for $2,700 for this work. No additional cost commitments are expected to be made for this line item. The original estimate for concrete to complete the footings and foundation is $9,270, no costs have been committed, and the contractor has received a bill for $3,960. The contractor estimates that it will cost an additional S5,310 to purchase the remaining concrete for the footings and foundations. The original estimate for the labor to complete the slab floor is $20,000 and S100 change order has been approved for additional work. This work will be performed by in-house crews. The work has yet to be performed and the contractor, but the contractor has been given a 1% price discount for the slab concrete from the supplier, which reduces the total estimate for this item by 1%, Determine the total estimated cost at completion for this project and the variance for each cost code 03000 CONCRETE 03200 Under-slab Gravel 03300 Footing & Foundation Labor 03400 Footing & Foundation Concrete 03450 Concrete Pump 03500 Slab/Floor-Labor 03600 Slab/Floor-Concrete 03650 Light-Weight Concrete 03700 Pre-cast Concrete 03900 Rebar
No need to use all rows. Just use what you need and have.
media%2Fe02%2Fe028658b-9df1-4a33-91af-c8
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Code Description

Original Estimate

(A)

Changed Orders

(B)

Total Estimate

(C = A+B)

Committed Costs

(D)

Committed Costs Invoiced

(E)

Non Committed Costs Invoiced

(F)

Total Committed and Non Committed Costs Invoiced

(G= E+F)

Estimated Cost to Complete

(H)

Total Estimated Cost at Completion

(I=G+H)

Variance Over/Under

(J=I-C)

03300 Footing and Foundation - Labor $8400 $8400 $8560 $2700 $2700 $2700 -$5700
03400 Footing and Foundation - Concrete $9270 $9270 $3960 $3960 $5310 $9270 $0
03500 Slab/Floor - Labor $20000 $100 $20100

$19899

(Deducting 1% Supplier Discount)

$19899

$19899 -$201
Total $37670 $100 $37770 $28459 $2700 $3960 $6660 $25209 $31869 -$5901
Add a comment
Know the answer?
Add Answer to:
Construction Engineering Financial No need to use all rows. Just use what you need and have....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was...

    can you please answer question 1 and 3 please ABC General Contractors ABC General Contractors was an established construction company handling small-to medium- sized commercial and industrial construction projects. Some recent projects that the company had completed were a 20,000-square-foot factory building, a four-story office building, and a water filtration plant. TELEVISION TOWER BID The company was now in the process of preparing a bid for a television station for the erection of a 225-foot-high television antenna tower and the...

  • Question 1: What is a joint venture and why might two construction firms choose to form...

    Question 1: What is a joint venture and why might two construction firms choose to form one? (4 points) Case Study 1: Please answer the first 4 questions with the following case data for Project 101 and Project 102. A construction company began operations on January 2, 2010. During the year the company was awarded three construction contracts. The company incurred $300,000 operating expenses for the year for which $275,000 has been paid while the balance is owed as of...

  • its all one question just matching, thank you!!! Costs that have already incurred Cost of goods...

    its all one question just matching, thank you!!! Costs that have already incurred Cost of goods available for sale minus ending (finished goods) inventory Selling, general and administrative expenses Triple bottom line 1. Materials used in manufacturing Raw materials inventory 2. Can be traced to a cost object Work in process inventory 3. Total manufacturing costs to account for minus ending work in process inventory Finished goods inventory 4. Value chain 5. Goods that are partway through the manufacturing process,...

  • Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction...

    Orleans Construction Company Case (adapted from Meredith and Mantel) The Orleans Construction Company, a small construction company in North Carolina, has been awarded a contract for the construction of a new 25,000 soccer stadium at Greensboro. The City is hoping to use this facility to attract a new soccer franchise. The construction cannot start earlier than March 2, 2020 (because of the availability of bond funds) and must be completed within 1 year (52 weeks). A penalty clause of $13,000...

  • Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all....

    Dear Sir/Madam, could you answer all the question below. I appreciate if u can answer all. Thank You :) A (Bad?) Day in the Life of a Project Manager Frank Mills is a Site Agent for McMurray Concrete Ltd which specialises in building concrete structures on industrial sites. His present site is a large chemical plant, Agrochem Ltd that manufactures farm fertilisers. The project he is currently working on is part of a large contract being managed by Design Solutions...

  • you dont have to do all 3 but i would appreciate. Clunk, Inc. operates a machine...

    you dont have to do all 3 but i would appreciate. Clunk, Inc. operates a machine shop in which the employees are members of Mechanics and Mattress Handlers Brotherhood, a trade union. The union has negotiated pay rates for each job. Last week a trainee grinder operator spent 42 hours working on a grinder, the full union rate for which was $15 per hour The trainee was paid $8 per hour. The work she performed could have been done by...

  • HEY, ALL I NEED IS THE LAST QUESTION PLEASE, THESE SCREENSHOTS ARE FOR TO HELP YOU...

    HEY, ALL I NEED IS THE LAST QUESTION PLEASE, THESE SCREENSHOTS ARE FOR TO HELP YOU UNDERSTAND WHAT HAS BEEN DONE BEFORE :D P15-3A Prepare entries for a job order cost system and cost of goods manufactured schedule Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data. Raw Materials Inventory Work...

  • Check my work mode: This shows what is correct or incorrect for the work you have...

    Check my work mode: This shows what is correct or incorrect for the work you have completed so far. It does not i Cane Company manufactures two products called Alpha and Beta that sell for $120 and $80, respectively. Each prod. uses only one type of raw material that costs $6 per pound. The company has the capacity to annually produce 100,0 units of each product. Its average cost per unit for each product at this level of activity are...

  • need assistance post to general journal and assist with IS & Sequity, Balance Sheet and Post...

    need assistance post to general journal and assist with IS & Sequity, Balance Sheet and Post Close TB July 2019 Transactions Date Description of the Transaction 1 July 1 Borrow $35,000.00 from 1st Bank by signing a 24 month note. (As an example of how to journalize and post a transaction - this transaction has already been entered into the General Journal and posted to the General Lodger.) July 1 Receive $80,050.00 cash from new investors, and issue $80,050.00 of...

  • Help with the areas that have 0.00! DESCIULUIT VI LTE Transacuum July 1 Borrow $35,000.00 from...

    Help with the areas that have 0.00! DESCIULUIT VI LTE Transacuum July 1 Borrow $35,000.00 from 1st Bank by signing a 24 month note. (As an example of how to journalize and post a transaction -- this transaction has already been entered into the General Journal and posted to the General Ledger.) July 1 Receive $68,700.00 cash from new investors, and issue $68,700.00 of Common Stock to them. July 1 Purchase $44,700.00 of new mowing equipment, paying cash to the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT