Question

Question 1: What is a joint venture and why might two construction firms choose to form one? (4 points) Case Study 1: PleaseExcavating and backfill was let to another contractor under separate contract. The estimator determined that the wall would cCase Study 2: What are the proper entries for the following three transactions listed in the following three questions? Ameri

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Project 101 Project 102
Original contract linear size 1000
construction cost $800,000 Height 8
Overhead mark-up $150,000
Profit mark up $50,000 Cost of concrete $40,000
cost of reinforcing $10,000
Change order Cost of labor $50,000
Construction cost $50,000 Total cost $100,000
Overhead mark-up $37,500
Profit mark up $12,500 No. of labor hours per liner foot 2.5
Total labor hours 2500
Total construction cost $850,000 Pending cost to be incurred $30,000
Total overhead markup $187,500 Length constructed 700
Total profit mark up $62,500 Hours used 2150
Total project revenue $1,100,000
Question 4 % of completion
Question 2 estimated Construction cost yet to be incurred $200,000 Cost to cost 70%
%age of work pending 23.5% Work quantity 70%
Therefore, percentage of work complated 76.5% labor hours 86%
Revenue $841,176.47
Profit $47,794.12
Cost to cost and work quantity produce same result. Work quantity should be used as reference as this gives the actual amount of work completed wrt the total scsope of work
Question 3 Billing done $1,000,000
Based on billing method the entire amount billed is considered as revenue. So the revenue is $1,000,000 which is higher than the revenue recognized as per percentage of completion method. Contractor has been doing advance billing to the client.
Add a comment
Know the answer?
Add Answer to:
Question 1: What is a joint venture and why might two construction firms choose to form...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Case Study 2: What are the proper entries for the following three transactions listed in the...

    Case Study 2: What are the proper entries for the following three transactions listed in the following three questions? American Construction Company, Inc. started operations on January 2, 2010. American was awarded the contract for Project 101 during January. Bid price was $200,000. Estimated project cost was $180,000. Review the demonstration problem within the text for a complete explanation for entering January’s transactions into the general journal, posting to account ledgers, closing out and finding ending balances for accounts as...

  • American Construction Company, Inc. started operations on January 2, 2010. American was awarded the contract for Project...

    American Construction Company, Inc. started operations on January 2, 2010. American was awarded the contract for Project 101 during January. Bid price was $200,000. Estimated project cost was $180,000. Review the demonstration problem within the text for a complete explanation for entering January’s transactions into the general journal, posting to account ledgers, closing out and finding ending balances for accounts as appropriate, and preparing January’s income statement, and balance sheet. During February, the second month of operations, American completed Project...

  • Question 17 The board of directors of Splish Construction Company is meeting to choose between the...

    Question 17 The board of directors of Splish Construction Company is meeting to choose between the completed-contract method and the percentage of completion method of accounting for long- term contracts in the company's financial statements. You have been engaged to assist Splish's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Splish commenced doing business on January 1, 2021. 2. Construction activities for the year ended...

  • alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project...

    alls Corners Construction Limited (BCCL) specializes in the construction of commercial buildings. A typical construction project lasts between fifteen and twenty-four months. The company uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. BCCL follows ASPE and has a December 31 year-end. On January 1, 2016, the company began work on a contract and, at the beginning of the...

  • Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January...

    Exercise 18-37 Your answer is partially correct. Try again. Yanmei Construction Company began operations on January 1, 2017. During the year, Yanmei Construction entered into a contract with Lundquist Corp. to construct a manufacturing facility. At that time, Yanmei estimated that it would take 5 years to complete the facility at a total cost of $4,500,000. The total contract price for construction of the facility is $6,000,000. During the year, Yanmei incurred $1,185,800 in construction costs related to the construction...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started...

    Question 3: Percentage of Completion Method (12 marks) On January 1, 2017, Eagle Construction Ltd. started a construction project for $4,500,000. Relevant data for 2017 and 2018 are as follows:                                             2017                                    2018 Current year construction costs                                       $3,300,000                             $ 620,000 Estimated remaining costs to complete                              600,000                                   -0- Current year billings                                                            3,100,000                              1,400,000 Current year collections                                                    3,000,000                                1,500,000 Required: Calculate the following amounts for each method:               Completed Percentage-of Contract Completion                                   2017      2018    2017    2018 a) Gross Profit                                                                                              $             $           $          ...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT