1 | |||||
Projects | A | B | C | D | E |
Contract price (1) | 512,000 | 723,000 | 481,000 | 206,000 | 462,000 |
Contract costs incurred | 436,000 | 213,000 | 362,000 | 135,000 | 332,000 |
Additional Costs to complete | 113,000 | 497,000 | 0 | 109,000 | 83,000 |
Total cost (2) | 549,000 | 710,000 | 362,000 | 244,000 | 415,000 |
Total gross profit or (loss) (1-2) | -37,000 | 13,000 | 119,000 | -38,000 | 47,000 |
a) | |||||
Project A | -37,000 | ||||
Project B | 0 | ||||
Project C | 119,000 | ||||
Project D | -38,000 | ||||
Project E | 0 | ||||
44,000 | |||||
b) | |||||
Project A | -37,000 | ||||
Project B (13000*123000/710000) | 2,252 | ||||
Project C | 119,000 | ||||
Project D | -38,000 | ||||
Project E (47000*332000/415000) | 37,600 | ||||
83,852 | |||||
2 | |||||
Accounts title and Explanation | Debit ($) | Credit ($) | |||
Construction in Process | 2,252 | ||||
Construction Expenses | 213,000 | ||||
Revenue from Long-term Contracts | 215,252 | ||||
3 | |||||
Particulars | Amount ($) | ||||
Billings | 13,000 | ||||
Cash collections | 71,000 | ||||
Accounts receivable | 58,000 | ||||
Billings on Construction in Process | 13,000 | ||||
Costs incurred | 135,000 | ||||
Loss reported | -38,000 | ||||
Construction in process | 97,000 | ||||
4 | |||||
The account balances would be the same. |
Question 17 The board of directors of Splish Construction Company is meeting to choose between the...
Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...
Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date Estimated costs to complete $410,000 $901,180 $1,067,000 590,000 197,820 -O- 297,000 903,000 1,590,000 271,000 805,000 1,434,000 Billings to date Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used....
During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...
1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...
Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...
During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...
Cheyenne Construction Company began work on a $424,000
construction contract in 2020. During 2020, Cheyenne incurred costs
of $279,500, billed its customer for $204,500, and collected
$170,500. At December 31, 2020, the estimated additional costs to
complete the project total $150,500.
Prepare Cheyenne’s journal entry to record profit or loss, if any,
using (a) the percentage-of-completion method and (b) the
completed-contract method.
Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...
During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...