Question

Question 17 The board of directors of Splish Construction Company is meeting to choose between the completed-contract method

Prepare the general journal entry to record revenue and gross profit on project B (second project) for 2021, assuming that th

How would the balances in the accounts discussed in part (c) change (if at all) for Project D (fourth project), if the comple

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Projects A B C D E
Contract price (1) 512,000 723,000 481,000 206,000 462,000
Contract costs incurred 436,000 213,000 362,000 135,000 332,000
Additional Costs to complete 113,000 497,000 0 109,000 83,000
Total cost (2) 549,000 710,000 362,000 244,000 415,000
Total gross profit or (loss) (1-2) -37,000 13,000 119,000 -38,000 47,000
a)
Project A -37,000
Project B 0
Project C 119,000
Project D -38,000
Project E 0
44,000
b)
Project A -37,000
Project B (13000*123000/710000) 2,252
Project C 119,000
Project D -38,000
Project E (47000*332000/415000) 37,600
83,852
2
Accounts title and Explanation Debit ($) Credit ($)
Construction in Process 2,252
Construction Expenses 213,000
  Revenue from Long-term Contracts 215,252
3
Particulars Amount ($)
Billings 13,000
Cash collections 71,000
Accounts receivable 58,000
Billings on Construction in Process 13,000
Costs incurred 135,000
Loss reported -38,000
Construction in process 97,000
4
The account balances would be the same.
Add a comment
Know the answer?
Add Answer to:
Question 17 The board of directors of Splish Construction Company is meeting to choose between the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred...

    Splish Construction Company began work on a $402,000 construction contract in 2020. During 2020, Splish incurred costs of $252,000, billed its customer for $210,500, and collected $177,000. At December 31, 2020, the estimated additional costs to complete the project total $162,405. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred...

    Splish Construction Company began work on a $418,500 construction contract in 2020. During 2020, Splish incurred costs of $285,500, billed its customer for $233,000, and collected $172,000. At December 31, 2020, the estimated additional costs to complete the project total $155,765. Prepare Splish’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction...

    Question 12 --/1 View Policies Current Attempt in Progress During 2020, Headland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date Estimated costs to complete $410,000 $901,180 $1,067,000 590,000 197,820 -O- 297,000 903,000 1,590,000 271,000 805,000 1,434,000 Billings to date Collections to date Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used....

  • During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Sunland Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete 2020 2021 2022 $410,000 $901,180 $1,067,000 590,000 197,820 -0- 297,000 903,000 .590,000 271,000 805,000 1,434,000 Billings to date Collections to date ✓ Your answer is correct Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...

  • Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work...

    Exercise 18-36 Coronado Construction Company uses the percentage-of-completion method of accounting. In 2017, Coronado began work under contract #E2-D2, which provided for a contract price of $2,234,000. Other details follow: 2017 2018 Costs incurred during the year $615,980 $1,420,000 Estimated costs to complete, as of December 31 1,005,020 -0- Billings to date 413,000 2,234,000 Collections during the year 351,000 1,530,000 What portion of the total contract price would be recognized as revenue in 2017? In 2018? Revenue recognized in 2017...

  • During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job...

    During 2017, Cullumber Company started a construction job with a contract price of $1,610,000. The job was completed in 2019. The following information is available. 2017 2018 2019 Costs incurred to date $434,300 $859,560 $1,073,000 Estimated costs to complete 575,700 242,440 -0- 1,610,000 Billings to date 301.000 897,000 271,000 1428,000 Collections to date 817,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used $ Gross profit recognized in 2017 $ Gross profit...

  • Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred...

    Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...

  • During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job...

    During 2020, Oriole Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. Costs incurred to date Estimated costs to complete Billings to date Collections to date 2020 $366,300 623,700 297,000 270,000 2021 $831,440 262,560 894,000 816,000 2022 $1,067,000 -0- 1,590,000 1,417,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT