Question

Complete Job-Order Costing EYK 3-1 EYK3-1. Business Decision Case Elizabeth Flanigan and Associates is an engineering...

Complete Job-Order Costing EYK 3-1

EYK3-1. Business Decision Case Elizabeth Flanigan and Associates is an engineering and design firm that specializes in developing plans for recycling plants for municipalities. The firm uses a job costing system to accumulate the cost associated with each design project. Flanigan employs three levels of employee: senior engineers, associate engineers, and clerical staff. The salary cost of the senior engineers and the associate engineers is assigned to each project as direct labor. The salary cost of the clerical staff is included in overhead, along with the cost of engineering supplies, automobile travel, and equipment depreciation. The cost of airline travel, motels, building permits, and fees from other consultants is charged to each project as direct materials. Overhead is applied to projects using a predetermined overhead rate based on total engineering hours. The rate for 20X0 is $5 per hour.

The six different salary levels for 20X1 for the employees of Elizabeth Flanigan and Associates are listed below. The hourly rate is determined by dividing the yearly salary by 2,000 hours per year.

Senior engineer

Level 1: $44,000 per year ($22 per hour)

Level 2: $36,000 per year ($18 per hour)

Associate engineer

Level 3: $30,000 per year ($15 per hour)

Level 4: 24,000 per year ($12 per hour)

Clerical Staff

Level 5: $16,000 per year ($8 per hour)

     Level 6: $14,500 per year ($7.25 per hour)

The billings that are sent to the municipalities for engineering services utilize cost-plus billing. Typically, the total costs accumulated for a project (direct materials, direct labor, and overhead) are multiplied by 140% to determine the amount of the billing. The differences between the billed amount and the accumulated cost is the “plus” in cost plus.

During March 20X1, Flanigan accumulated the following information related to Job 295 for Johnson Creek City:

Senior engineer hours

Level 1……………………………………………………….52

Level 2……………………………………………………..84

Associate engineer hours

Level 3………………………………………………………106

Level 4………………………………………………………..44

Clerical hours

Level 5…………………………………………………………20

Level 6……………………………………………………..…66

Building Permits……………………………………$1,500

Airline travel and motel………………….……….$865

Required

  1. What amount should be billed to Johnson Creek City for March 20X1?
  2. How much profit was earned on Job 295 during March 20X1

PLEASE ANSWER QUESTIONS IN THIS FORM:

A) Direct Materials:    B)

Building Permits

Airline Travel and Motel

Direct Labor:

senior engineers

Overhead

Total Project Cost

Cost Plus Percentage

Total Amount billed

0 0
Add a comment Improve this question Transcribed image text
Answer #1
DIRECT MATERIAL
BUILDING PERMIT $    1,500.00
AIRLINE TRAVEL AND MOTEL $        865.00
DIRECT LABOR
SENIOR ENGINEERS
LEVEL 1 52*22 $    1,144.00
LEVEL 2 84*18 $    1,512.00
ASSOCIATE ENGINEER HOURS
LEVEL 3 106*15 $    1,590.00
LEVEL 4 44*12 $        528.00
OVERHEAD $    1,430.00
286 * $ 5.00
TOTAL COST $    8,569.00
BILLING AMOUNT 140% OF TOTAL COSTS $ 11,996.60
PROFITS $    3,427.60

SHOW FORMULA IN EXCEL:

DIRECT MATERIAL
BUILDING PERMIT 1500
AIRLINE TRAVEL AND MOTEL 865
DIRECT LABOR
SENIOR ENGINEERS
LEVEL 1 52*22 =52*22
LEVEL 2 84*18 =84*18
ASSOCIATE ENGINEER HOURS
LEVEL 3 106*15 =106*15
LEVEL 4 44*12 =44*12
OVERHEAD =286*5
286 * $ 5.00
TOTAL COST =SUM(B2:B15)
BILLING AMOUNT 140% OF TOTAL COSTS =+B17*1.4
PROFITS =+B18-B17
Add a comment
Know the answer?
Add Answer to:
Complete Job-Order Costing EYK 3-1 EYK3-1. Business Decision Case Elizabeth Flanigan and Associates is an engineering...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Complete Job-Order Costing EYK 3-1 EYK3-1. Business Decision Case Elizabeth Flanigan and Associates is an engineering...

    Complete Job-Order Costing EYK 3-1 EYK3-1. Business Decision Case Elizabeth Flanigan and Associates is an engineering and design firm that specializes in developing plans for recycling plants for municipalities. The firm uses a job costing system to accumulate the cost associated with each design project. Flanigan employs three levels of employee: senior engineers, associate engineers, and clerical staff. The salary cost of the senior engineers and the associate engineers is assigned to each project as direct labor. The salary cost...

  • Job Costing #3 Burlington Corporation uses a job-order costing system and a predetermined overhead rate based...

    Job Costing #3 Burlington Corporation uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated manufacturing overhead for the year would be $3,200,000 and 4,000 machine hours would be used. Labor was estimated at $200/hour. The following information pertains to December of the current year: Job No. Job No. Job No. Job No. 206 207 208 209 Work in process, December 1 $28,000 $30,000 $22,000 $10,000 December...

  • Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

    Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $55,000 Number of moves 2,500 Engineering 101,500 Number of change orders 7,000 Other overhead 180,000 Direct labor hours 50,000 Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

  • Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances...

    Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 72,500 Work in process $ 18,200 Finished goods $ 46,500 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $15.50 per direct labor-hour was based on a cost formula that estimated $620,000 of total manufacturing overhead for an estimated activity level of 40,000 direct...

  • Exercise 2-7 Job-Order Costing; Working Backwards [LO2-1, LO2-2, LO2-3] Hahn Company uses a job-order costing system....

    Exercise 2-7 Job-Order Costing; Working Backwards [LO2-1, LO2-2, LO2-3] Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $15.50 per hour. During the year, the company started and completed only two jobs-Job Alpha, which used 64,400 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job...

  • Exercise 2-7 (Algo) Job-Order Costing; Working Backwards (LO2-1, LO2-2, LO2-3] Hahn Company uses a job-order costing...

    Exercise 2-7 (Algo) Job-Order Costing; Working Backwards (LO2-1, LO2-2, LO2-3] Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $20.50 per hour. During the year, the company started and completed only two jobs—Job Alpha, which used 69,900 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total...

  • Exercise 2-7 Job-Order Costing; Working Backwards [LO2-1, LO2-2, LO2-3] Hahn Company uses a job-order costing system....

    Exercise 2-7 Job-Order Costing; Working Backwards [LO2-1, LO2-2, LO2-3] Hahn Company uses a job-order costing system. Its plantwide predetermined overhead rate uses direct labor-hours as the allocation base. The company pays its direct laborers $12.50 per hour. During the year, the company started and completed only two jobs-Job Alpha, which used 68,200 direct labor-hours, and Job Omega. The job cost sheets for the these two jobs are shown below: Job Alpha Direct materials Direct labor Manufacturing overhead applied Total job...

  • Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company's inventory balances...

    Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company's inventory balances were as follows: Raw materials Work in process Finished goods $ 59,500 $ 37,600 $ 61,800 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company's predetermined overhead rate of $14.25 per direct labor hour was based on cost formula that estimated $570,000 of total manufacturing overhead for an estimated activity level of 40.000 direct...

  • urgent thanks! Grant Marwick and Associates, a CPA firm, uses job order costing to capture the...

    urgent thanks! Grant Marwick and Associates, a CPA firm, uses job order costing to capture the costs of its audit jobs. There were no audit jobs in process at the beginning of November. Listed below are data concerning the three audit jobs conducted during November Rondelli Preston Lopez Direct materials: $900 $600 $300 Auditor labor costs: $5,900 $6,600 $3,700 Auditor hours: 72 88 Overhead costs are applied to jobs on the basis of auditor hours, and the predetermined overhead rate...

  • Exercise 2-9 (Algo) Job-Order Costing and Decision Making (LO2-1, LO2-2, LO2-3] Taveras Corporation is currently operating...

    Exercise 2-9 (Algo) Job-Order Costing and Decision Making (LO2-1, LO2-2, LO2-3] Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production Fixed manufacturing overhead cost Variable manufacturing overhead cost per machine-hour 260,000 $ 5,720,000 $ 2.00 Required: 1. Compute the plantwide predetermined overhead rate. 2....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT