Zarek Confections produces fudge in 10-pound batches. Each batch takes 0.28 hours of direct labor, which includes allowances
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Standard labor cost per batch = number of labor hours per batch*rate per batch

= 0.28*20.50

=$5.74 per batch

Add a comment
Know the answer?
Add Answer to:
Zarek Confections produces fudge in 10-pound batches. Each batch takes 0.28 hours of direct labor, which...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Bowser Products operates a small plant in New Mexico that produces dog food in batches of...

    Bowser Products operates a small plant in New Mexico that produces dog food in batches of 1,500 pounds. The product sells for $6 per pound. Standard costs for 2018 are: Standard direct labor cost = $15 per hour Standard direct labor hours per batch = 10 hours Standard price of material A = $0.35 per pound Standard pounds of material A per batch = 800 pounds Standard price of material B = $0.55 per pound Standard pounds of material B...

  • Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a...

    Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $12 per hour. During August, Hassock produced 19,000 units and used 38,140 hours of direct labor at a total cost of $454,680. What is Hassock’s labor rate variance for August?

  • Hassock Corp. produces woven wall hangings. It takes 4 hours of direct labor to produce a...

    Hassock Corp. produces woven wall hangings. It takes 4 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $18 per hour. During August, Hassock produced 8,900 units and used 36,170 hours of direct labor at a total cost of $647,160. What is Hassock’s labor efficiency variance for August?

  • Suppose that each visor takes 0.10 direct labor hours to produce and Shadee pays its workers...

    Suppose that each visor takes 0.10 direct labor hours to produce and Shadee pays its workers $11 per hour. Required: Determine Shadee's budgeted direct labor cost for May and June. (Do not round your intermediate values. Round your answers to 2 decimal places.) June May Budgeted Direct Labor Cost

  • Direct Labor Variances Bellingham Company produces a product that requires 7 standard direct labor hours per...

    Direct Labor Variances Bellingham Company produces a product that requires 7 standard direct labor hours per unit at a standard hourly rate of $13.00 per hour. If 2,800 units used 20,400 hours at an hourly rate of $12.74 per hour, what is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct labor rate variance...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.20 pounds of materials. The average waste under normal conditions is 0.80 pounds Materials cost $ pound but Stefani always takes the 2.00 % cash discount all of its suppliers $0.45 per pound. Direct labor. Each unit requires 1.60 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly pay rate of Stefani's employees is $12.30. Payroll taxes...

  • Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a...

    Hassock Corp. produces woven wall hangings. It takes 2 hours of direct labor to produce a single wall hanging. Hassock’s standard labor cost is $17 per hour. During August, Hassock produced 14,000 units and used 28,160 hours of direct labor at a total cost of $476,020. What is Hassock’s labor rate variance for August? Multiple Choice $2,685 favorable. $2,700 unfavorable. $2,700 favorable. $5,385 favorable. $2,685 unfavorable.

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.90 pounds. Materials cost $2 per pound, but Stefani always takes the 4.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 1.30 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • Sheffield Company has gathered the following information about its product. Direct materials. Each unit of product...

    Sheffield Company has gathered the following information about its product. Direct materials. Each unit of product contains 5.00 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.80 pounds. Materials cost $1 per pound, but Sheffield always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.70 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • amarisk Company has gathered the following information about its product. Direct materials: Each unit of product...

    amarisk Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.90 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.10 pounds. Materials cost $4 per pound, but Tamarisk always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.35 per pound. Direct labor. Each unit requires 1.80 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT