Required information
[The following information applies to the questions
displayed below.]
In 2018, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2020. Information related to the contract is
as follows:
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 2,450,000 | $ | 2,695,000 | |||
Estimated costs to complete as of year-end | 4,900,000 | 2,450,000 | 0 | ||||||
Billings during the year | 2,200,000 | 2,350,000 | 5,450,000 | ||||||
Cash collections during the year | 1,900,000 | 2,300,000 | 5,800,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
rev: 09_15_2017_QC_CS-99734
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
2018 | 2019 | 2020 | |||||||
Cost incurred during the year | $ | 2,100,000 | $ | 3,900,000 | $ | 4,200,000 | |||
Estimated costs to complete as of year-end | 4,900,000 | 4,300,000 | 0 |
Part 5 | |||
Year 2018 | |||
Cost incurred during the year | a | $ 2,100,000 | |
Add: Estimated cost to complete as of year end | b | $ 4,900,000 | |
Estimated Total cost | c | $ 7,000,000 | |
% Completion | a/c | 30% | |
Revenue to be recognized | 10m*30% | $ 3,000,000 | |
Less: Cost incurred | $ 2,100,000 | ||
Gross Profit to be recognized | $ 900,000 | ||
Year 2019 | |||
Cost incurred during the year (2100000+3900000) | A | $ 6,000,000 | |
Add: Estimated cost to complete as of year end | $ 4,300,000 | ||
Estimated Total cost | B | $ 10,300,000 | |
% Completion | A/B | 58.25% | |
Revenue to be recognized | 10m*58.25% | $ 5,825,243 | |
Already recognized till 2018 | $ 3,000,000 | ||
To be recognized in 2019 | $ 2,825,243 | ||
Less: Cost incurred | $ 4,200,000 | ||
Gross Profit/Loss to be recognized | $ -1,374,757 | ||
Year 2020 | |||
Cost incurred during the year | A | $ 10,200,000 | |
Add: Estimated cost to complete as of year end | $ - | ||
Estimated Total cost | B | $ 10,200,000 | |
% Completion | A/B | 100.00% | |
Revenue to be recognized | 10m*100% | $ 10,000,000 | |
Already recognized till 2019 | $ 5,825,243 | ||
To be recognized in 2020 | $ 4,174,757 | ||
Less: Cost incurred | $ 3,900,000 | ||
Gross Profit to be recognized | $ 274,757 |
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the...
in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...
The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000...
[The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...
Required information [The following information applies to the questions displayed below.j In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2019 $2,490,000 $3,984,000 $2,008,600 1,826,000 2,030,000 4,444,000 3,526,000 3,900,000 2018 5,810,000 1,815,000 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,285,000...
Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered intoo a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $4,032,000 1,764,000 4,596,000 4,000,000 $2,604,000 5,796,000 2,040,000 1,820,000 $1,940,400 3,364,000 4,180,000...
Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...