Question

Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

Required information

[The following information applies to the questions displayed below.]

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018 2019 2020
Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000
Estimated costs to complete as of year-end 4,900,000 2,450,000 0
Billings during the year 2,200,000 2,350,000 5,450,000
Cash collections during the year 1,900,000 2,300,000 5,800,000


Westgate recognizes revenue over time according to percentage of completion.


rev: 09_15_2017_QC_CS-99734

5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2018 2019 2020
Cost incurred during the year $ 2,100,000 $ 3,900,000 $ 4,200,000
Estimated costs to complete as of year-end 4,900,000 4,300,000 0
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Part 5
Year 2018
Cost incurred during the year a $       2,100,000
Add: Estimated cost to complete as of year end b $       4,900,000
Estimated Total cost c $       7,000,000
% Completion a/c 30%
Revenue to be recognized 10m*30% $       3,000,000
Less: Cost incurred $       2,100,000
Gross Profit to be recognized $           900,000
Year 2019
Cost incurred during the year (2100000+3900000) A $       6,000,000
Add: Estimated cost to complete as of year end $       4,300,000
Estimated Total cost B $     10,300,000
% Completion A/B 58.25%
Revenue to be recognized 10m*58.25% $       5,825,243
Already recognized till 2018 $       3,000,000
To be recognized in 2019 $       2,825,243
Less: Cost incurred $       4,200,000
Gross Profit/Loss to be recognized $      -1,374,757
Year 2020
Cost incurred during the year A $     10,200,000
Add: Estimated cost to complete as of year end $                       -  
Estimated Total cost B $     10,200,000
% Completion A/B 100.00%
Revenue to be recognized 10m*100% $     10,000,000
Already recognized till 2019 $       5,825,243
To be recognized in 2020 $       4,174,757
Less: Cost incurred $       3,900,000
Gross Profit to be recognized $           274,757
Add a comment
Know the answer?
Add Answer to:
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the...

  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered...

    The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000...

  • [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered...

    [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....

  • Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...

    Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,204,000 $ 3,192,000 $ 2,424,400 Estimated costs to complete as of year-end 5,396,000 2,204,000 0 Billings during the year 2,140,000 3,256,000 4,604,000 Cash collections during...

  • Required information [The following information applies to the questions displayed below.j In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.j In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows 2019 $2,490,000 $3,984,000 $2,008,600 1,826,000 2,030,000 4,444,000 3,526,000 3,900,000 2018 5,810,000 1,815,000 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,285,000...

  • Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000...

  • Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered intoo a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $4,032,000 1,764,000 4,596,000 4,000,000 $2,604,000 5,796,000 2,040,000 1,820,000 $1,940,400 3,364,000 4,180,000...

  • Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction...

    Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT