Question

Badger Company is a job-order costing manufacturer that applies overhead on the basis of direct labor...

Badger Company is a job-order costing manufacturer that applies overhead on the basis of direct labor hours.

At the beginning of the year, to establish a predetermined overhead rate, Badger Company estimated total $4,500 in overhead costs and total 300 direct labor hours.

On March 1, there were two jobs in process: Job 89 with a beginning balance of $2,300 and Job 90 with a beginning balance of $1,824. During March, three new jobs were started: Jobs 91, 92, and 93. The amount of direct labor hours actually worked on each job during March was as follows:  

      Job 89   Job 90   Job 91   Job 92 Job 93

Direct labor hours    30 hrs.   50 hrs.   65 hrs.   25 hrs. 20 hrs.

Data on costs added during March for all jobs are as follows:  

      Job 89 Job 90   Job 91   Job 92   Job 93

Direct materials cost   $1,300 $1,726 $2,230    $1,525   $820

Direct labor cost       800    1,150    1,620        975      480

By March 31, Jobs 89 and 91 were completed and sold. Job 90 was completed but not sold yet. The rest of the jobs remained in process. On March 1, the beginning balance of the Finished Goods inventory account was $2,050. Badger Company prices its jobs at cost plus 40%.

1. What is the manufacturing overhead applied to Job 89?

A) $450

B) $750

C) $7,200

D) $12,000

2. What is the total manufacturing cost incurred by Job 90?

A) $3,626

B) $2,876

C) $5,450

D) $4,700

3. What is the balance in Work-In-Process on March 31?

A) $3,800

B) $2,875

C) $4,475

D) $9,925

4. What is the balance in Finished Goods on March 31?

A) $5,450

B) $7,500

C) $5,676

D) $17,175

5. What is the amount of Cost of Goods Sold for March?

A) $7,375

B) $9,675

C) $4,825

D) $10,300


6. What is the selling price of Job 91?

A) $6,755

B) $4,825

C) $1,930

D) $5,390

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Overhead rate = Estimated overhead/estimated direct labor hours = 4500/300 = 15 per hour

1) Manufacturing overhead applied to Job 89 = 30*15 = $450

So answer is a) $450

2) Total manufacturing cost incurred by Job 90 = (1726+1150+50*15) = 3626

So answer is a) $3626

3) Balance in Work in process march 31 = (1525+820+975+480+45*15) = 4475

So answer is c) $4475

4) Balance in Finished goods march 31 = (3626+1824) = 5450

So answer is a) $5450

5) Amount of cost of goods sold = 1300+2230+800+1620+(95*15)+2300 = 9675

So answer is b) $9675

6) Selling price = 4825*1.4 = $6755

So answer is a) $6755

Add a comment
Know the answer?
Add Answer to:
Badger Company is a job-order costing manufacturer that applies overhead on the basis of direct labor...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Wayne Company uses a job costing system and applies overhead to jobs using a predetermined overhead...

    Wayne Company uses a job costing system and applies overhead to jobs using a predetermined overhead rate based on direct labor-hours. The company had the following inventories at the beginning and end of March:    Wayne Company uses a job costing system and applies overhead to jobs using a predetermined overhead rate based on direct labor-hours. The company had the following inventories at the beginning and end of March: March 1 March 31 $36,000 $30,000 Direct Materials Work in Process...

  • Pedriani Company uses a job order cost system and applies overhead on the basis of direct...

    Pedriani Company uses a job order cost system and applies overhead on the basis of direct labor hours. On Jan01, 2017, Job No. 25 was the only job in process. Costs incurred prior to Jan01 on this job were as follows: direct materials $10,000; direct labor $6,000; and manufacturing overhead $9,000.  Job No. 23 had been completed at a cost of $42,000 and was part of finished goods inventory.  There was a $5,000 balance in the Raw Materials Inventory account. During the...

  • Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...

    Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Direct materials Direct labor Applied overhead Balance, March 1 Job 86 $4,800 1,200 888 $6,888 Job 87 $1,600 3,000 2,220 56,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...

  • Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs

     Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2017, Job No. 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $20,400, direct labor $12,240, and manufacturing overhead $16,320. As of January 1, Job No. 49 had been completed at a cost of $91,800 and was part of finished goods inventory. There was...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started th e month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1 - A $3,250 Job #3-G $2,690 Job #7-L $3,720 beginning work in process COSTS ADDED DURING JUNE: $3,950 4,180 $4,680 3,530 $2,870 2,410 direct materials direct labor...

  • Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours....

    Reed Incorporated uses a job-order costing system and a predetermined overhead rate based on machine hours. At the beginning of the year, the company estimated that the manufacturing overhead for the year would be $240,000 and machine hours would be 8,000. The following information pertains to December of the current year: Job 10 Job 11 Job 12 Total Work in process, Dec. 1 $16,000 $26,000 $38,000 $80,000 December production activity: Materials requisitioned $4,000 $4,800 $7,200 $16,000 Direct labor cost 2,400...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT