Question

Exercise 15-06 a-b (Video) A job cost sheet of Sunland Company is given below. JOB NO. 2,000 7/2 ITEM FOR 7/31 Manufacturing
LULATOR FULL SCREEN (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs as
0 0
Add a comment Improve this question Transcribed image text
Answer #1
  1. The source documents are:

Direct materials – Material requisition slips

Direct labor- Time tickets

Manufacturing overhead – predetermined overhead rate

  1. The predetermined overhead rate = Manufacturing overhead/direct labor

Computing on various dates i.e. 600/500 or 480/400 or 600/500, predetermined overhead rate as required would be 120% of direct labor hours.

  1. The computation of total cost and unit cost is given below :

Particulars

Amount ($)

Direct materials (700 +900 + 1660+1560)

4,820

Direct labor (500+400+500)

1400

Manufacturing overhead (600+480+600)

1680

Total costs

$ 7,900

Quantity as given

2,000

Unit cost (7900/2000)

3.95

  1. The required journal entry would be:

Date

Particulars

Debit ($)

Credit ($)

31 July

Finished Goods Inventory

7,900

             Work in Process Inventory

7,900

(To record the completion of product)

kindly upvote

Add a comment
Know the answer?
Add Answer to:
Exercise 15-06 a-b (Video) A job cost sheet of Sunland Company is given below. JOB NO....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CES Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given...

    CES Exercise 2-6 (Video) (Part Level Submission) A job cost sheet of Sandoval Company is given below. vel 2.000 JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 7/2 7/31 Manufacturing Overhead on) Date 7/10 700 900 500 300 600 360 udy. 1,640 1,600 700 840 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What...

  • Ajob cost sheet of Sunland Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31...

    Ajob cost sheet of Sunland Company is given below. JOB NO. ITEM FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 12 15 22 24 27 31 Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor $700 900 $400 300 1,700 1,500 500 $500 375 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (a) What are the source documents for direct...

  • Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet...

    Ajob cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead 800 900 Date 7/10 12 15 22 24 27 31 500 400 625 500 1,675 1,550 700 875 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct...

  • A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469...

    A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 White Lion Cages Date Requested ITEM 7/2 Todd Company FOR Date Completed 7/31 Manufacturing Overhead Direct Direct Date Materials Labor 700 7/10 12 900 15 400 500 22 300 375 24 1,700 27 1,550 31 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost *(a) Answer the following questions. (1) What are the source documents...

  • A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost...

    A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 12 15 400 400 500 500 22 24 1,625 1,525 27 31 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (a) Answer the following questions. (1) What are the source documents...

  • A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet...

    A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 400 1,675 1,575 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Your answer is partially correct. Try again. Answer the following questions. (1) What are the source documents for direct materials, direct labor, and...

  • A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 2,500...

    A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 2,500 469 Quantity White Lion CagesDate Requested ITEM 7/2 FOR Todd Company Date Completed 7/31 Direct Materials Direct Labor Manufacturing Overhead Date 700 900 600 750 400 500 1,650 1,525 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs...

  • Question 1 of 3 A job cost sheet of Sandoval Company is given below. JOB NO....

    Question 1 of 3 A job cost sheet of Sandoval Company is given below. JOB NO. ITEM FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 2,500 7/2 7/31 Manufacturing Overhead Date 7/15 700 900 12 500 400 300 375 15 22 24 27 31 1,675 1,575 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are...

  • A job cost sheet of Crane Company is given below. 2.000 JOB NO. ITEM 7/2 FOR...

    A job cost sheet of Crane Company is given below. 2.000 JOB NO. ITEM 7/2 FOR Job Cost Sheet 469 Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor 700 7/31 Manufacturing Overhead Date 7/10 12 900 15 400 480 360 22 300 24 1,620 1,520 27 31 500 600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Your answer is partially correct. Answer the following questions. (1) What...

  • Exercise 2-6 (Part Level Submission) A job cost sheet of Sandoval Company is given below. Job...

    Exercise 2-6 (Part Level Submission) A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 469 Quantity 2,500 ITEM White Lion Cages Date Requested 7/2 FOR Todd Company Date Completed 7/31 Date Direct Materials Direct Labor Manufacturing Overhead 7/10 700 12 900 15 440 550 22 380 475 24 1,600 27 1,500 31 540 675 Cost of completed job:          Direct materials          Direct labor           Manufacturing overhead        Total cost        Unit cost (1)...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT