Question

2) You are given departmental financial information for a hypothetical Satellite Components Corporation in the table...

2) You are given departmental financial information for a hypothetical Satellite Components Corporation in the table below. Using horizontal and vertical analysis, calculate A) Scrap as a percentage of total output from the department for five months. (1 point) B) Productivity for each month. (1 point) C) The percentage of direct labour to total labour cost for each month. (1 point) D) The percentage of direct labour to total units produced in the period. (1 point) E) What additional information would you like to have, if you were the team leader of this department cost improvement team? State any conclusions from the preceding analysis. (2 points) Satellite Components Corp. Thrust Flow Monitor Component department Costs Cost January February March April May Volume – units 10,500 12,000 11,000 14,000 13,000 Direct material ($) 400,000 510,000 476,000 450,000 600,000 Indirect materials ($) 15,000 30,000 25,000 41,000 30,000 Direct labour ($) 800,000 900,000 900,000 1,000,000 940,000 Indirect labour ($) 40,000 45,000 44,000 76,000 63,000 Rework ($) 20,000 15,000 10,000 9,000 12,000 Scrap ($) 5,000 8,000 10,000 15,000 12,000

I need Question E is to be solved

0 0
Add a comment Improve this question Transcribed image text
Answer #1

i would need other variable costs, fixed costs, administrative and selling costs.

Add a comment
Know the answer?
Add Answer to:
2) You are given departmental financial information for a hypothetical Satellite Components Corporation in the table...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 2 You are the cost Accountant of an industrial concern and have been given the...

    Question 2 You are the cost Accountant of an industrial concern and have been given the following budgeted information regarding the four cost centres within your organisation. The following overhead details have been estimated for the next period: Dept 1 RM 60,000 12,000 Dept 2 RM 70,000 16,000 Maintenance RM 25,000 Canteen RM 15,000 10,000 3,000 Inirect labour Consumables Heat/Light (floor area) Rent and rates Depreciation of equipment Supervision Power Total RM 170,000 41,000 12,000 18,000 30,000 24,000 20,000 315,000...

  • Case (3) Data concerning manufacturing overhead for a Saudi Company are presented below. The Mixing Department...

    Case (3) Data concerning manufacturing overhead for a Saudi Company are presented below. The Mixing Department is a cost center. An analysis of the overhead costs reveals that all variable costs are controllable by the manager of the Mixing Department and that 50% of supervisory costs are controllable at the department level. The flexible budget formula and the cost and activity for the months of July and Augustre as follows Flexible Budget Per Actual Costs and Activity Direct Labor Hour...

  • Case (3) Data concerning manufacturing overhead for a Saudi Company are presented below. The Mixing Department...

    Case (3) Data concerning manufacturing overhead for a Saudi Company are presented below. The Mixing Department is a cost center. An analysis of the overhead costs reveals that all variable costs are controllable by the manager of the Mixing Department and that 50% of supervisory costs are controllable at the department level. The flexible budget formula and the cost and activity for the months of July and August are as follows Flexible Budget Per Direct Labor Hour Actual Costs and...

  • Dotsero Technology, Inc., has a job-order costing system. The company uses departmental predetermined overhead rates to...

    Dotsero Technology, Inc., has a job-order costing system. The company uses departmental predetermined overhead rates to apply manufacturing overhead cost to individual jobs. The predetermined overhead rate in Department A is based on machine hours, and the rate in Department B is based on direct labour hours. At the beginning of the most recent year (i.e., January 1, 2012), the company's management made the following estimates for the coming year: Department A B Machine hours 80,000 21,000 Direct labour hours...

  • Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for...

    Cost Information and FIFO Gunnison Company had the following equivalent units schedule and cost information for its Sewing Department for the month of December: Direct Materials Conversion Costs Units started and completed 40,000 40,000 Add: Units in beginning work in process × Percentage complete: 5,000 × 0% direct materials — 5,000 × 50% conversion Costs 2,500 Add: Units in ending work in process × Percentage complete: 12,000 × 100% direct materials 12,000 — 12,000 × 35% conversion Costs — 4,200...

  • 25-15 ACTIVITY-BASED COSTING AND ACTIVITY-BASED MANAGEMENT, AUTOMOTIVE SUPPLIER O'Sullivan Company is an automotive component supplier. O'Sullivan...

    25-15 ACTIVITY-BASED COSTING AND ACTIVITY-BASED MANAGEMENT, AUTOMOTIVE SUPPLIER O'Sullivan Company is an automotive component supplier. O'Sullivan has been approached by Honda Canada's Alliston, Ontario, plant to consider expanding its production of part 24Ž2 to a total annual quantity of 2,000 units. This part is a low-volume, complex product with a high gross margin that is based on a proposed (quoted) unit sales price of $7.50. O'Sullivan uses a traditional costing system that allocates indirect manufacturing costs based on direct labour...

  • a. Which of the following statements about managerial accounting is true? 1) Managerial accounting information is...

    a. Which of the following statements about managerial accounting is true? 1) Managerial accounting information is prepared for external users. 2) Managerial accounting information is a legal requirement. 3) The structure of managerial accounting practice is relatively flexible. 4) There are structured standards of acceptability for managerial accounting. b. Which of the following statements is incorrect with regard to a manufacturing firm? 1) Inventoriable costs include only prime costs. 2) Inventoriable costs include prime costs and manufacturing overhead costs. 3)...

  • Question 4 Tenaga Engineering Sdn Bhd is a medium size engineering company which undertakes contract Jobs...

    Question 4 Tenaga Engineering Sdn Bhd is a medium size engineering company which undertakes contract Jobs for construction companies. All jobs pass through its three production departments: fabrication, assembly and finishing. The Company has two service departments: stores & maintenance. The typical annual cost and other data for the production and service department is shown in the table below: Tenaga Engineering Sdn Bhd - Cost and Other data Production Departments Cost Items (RM) Fabrication Assembly Direct labour 60,000 45,000 Indirect...

  • The requirements are to correctly budget the following (this is all the directions and information given)....

    The requirements are to correctly budget the following (this is all the directions and information given). THIS IS ALL THE INFORMATION I WAS GIVEN. Perky Turkey Jerky, LLC Balance Sheet March 31, 2018 Assets 22,000.00 9,000.00 2,750.00 14,300.00 Current Assets Cash Accounts Receivable Raw Materials Inventory Finished Goods Inventory Total Current Assets Plant and Equipment Equipment Accumulated Depreciation Plant and Equipment, Net Total Assets 48,050.00 960,000.00 (63,000.00) 897,000.00 945,050.00 7,500.00 100,000.00 Liabilities and Stockholders' Equity Liabilities Accounts Payable Bonds Payable...

  • Mountain Manufacturing Company produces custom stamped metal parts for a variety of customers in Western Canada....

    Mountain Manufacturing Company produces custom stamped metal parts for a variety of customers in Western Canada. During January, the company had two jobs in process. Job A was an order for 1,200 stamped parts and was started in December. Job A had $12,000 of manufacturing costs already accumulated on January 1. Job B was an order for 1,000 stamped parts and was started in January. The company used a job-order costing system. Total manufacturing overhead for the year was estimated...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT