Question

Brady Construction Company contracted to build an apartment complex for a price of $6,700,000. Construction began...

Brady Construction Company contracted to build an apartment complex for a price of $6,700,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars.

Estimated Costs to Complete
Costs Incurred During Year (As of the End of the Year)
Situation 2021 2022 2023 2021 2022 2023
1 1,670 2,640 1,410 4,050 1,410
2 1,670 1,410 3,080 4,050 3,080
3 1,670 2,640 2,960 4,050 2,860
4 670 3,170 1,340 4,690 960
5 670 3,170 2,490 4,690 2,860
6 670 3,170 3,500 6,255 3,230


Required:
Complete the following table. (Do not round intermediate calculations. Enter answers in dollars. Round your final answers to the nearest whole dollar. Negative amounts should be indicated by a minus sign.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Working notes

Situation

Cost incurred during
the year (A)

Estimated costs
to complete (B)

Total costs
( C) = (A +B)

% of completion
D = A/C

Contract revenue
E

Gross margin
= (E ) - ( C)

Gross profit
recognized
(G ) = F X D

1

                          1,670,000

            4,050,000

         5,720,000

29.20%

               6,700,000

                  980,000

         286,119

2

                          1,670,000

            4,050,000

         5,720,000

29.20%

               6,700,000

                  980,000

         286,119

3

                          1,670,000

            4,050,000

         5,720,000

29.20%

               6,700,000

                  980,000

         286,119

4

                              670,000

            4,690,000

         5,360,000

12.50%

               6,700,000

              1,340,000

         167,500

5

                              670,000

            4,690,000

         5,360,000

12.50%

               6,700,000

              1,340,000

         167,500

6

                              670,000

            6,255,000

         6,925,000

9.68%

               6,700,000

                (225,000)

         (21,769)

For year 2022

Situation

Cost incurred during
the year (A)

Estimated costs
to complete (B)

Total costs
( C) = (A +B)

% of completion
D = A/C

Contract revenue
E

Gross margin
= (E ) - ( C)

Gross profit
recognized
(G ) = F X D

Gross profit
already
recognized (H)

Gross profit
recognized
I = G- H

1

                          4,310,000

            1,410,000

         5,720,000

75.35%

               6,700,000

                  980,000

         738,427

               286,119

             452,308

2

                          3,080,000

            3,080,000

         6,160,000

50.00%

               6,700,000

                  540,000

         270,000

               286,119

             (16,119)

3

                          4,310,000

            2,860,000

         7,170,000

60.11%

               6,700,000

                (470,000)

      (282,524)

               286,119

           (568,643)

4

                          3,840,000

                960,000

         4,800,000

80.00%

               6,700,000

              1,900,000

     1,520,000

               167,500

         1,352,500

5

                          3,840,000

            2,860,000

         6,700,000

57.31%

               6,700,000

                              -  

                    -  

               167,500

           (167,500)

6

                          3,840,000

            3,230,000

         7,070,000

54.31%

               6,700,000

                (370,000)

      (200,962)

               (21,769)

           (179,193)

*1670+2640

For last year

Situation

Cost incurred during
the year (A)

Contract revenue
( B)

Gross margin to be recognized
( C) = B - A

Gross profit
recognized in 2021
D

Gross profit
recognized in 2022
E

Total Gross
profit
recognized till date F = D + E

Gross profit
recognized in 2023
G = C - F

1

                          5,720,000

            6,700,000

             980,000

                      286,119

                   452,308

                  738,427

         241,573

2

                          6,160,000

            6,700,000

             540,000

                      286,119

                   (16,119)

                  270,000

         270,000

3

                          7,270,000

            6,700,000

          (570,000)

                      286,119

                 (568,643)

                (282,524)

      (287,476)

4

                          5,180,000

            6,700,000

         1,520,000

                      167,500

               1,352,500

              1,520,000

                    -  

5

                          6,330,000

            6,700,000

             370,000

                      167,500

                 (167,500)

                              -  

         370,000

6

                          7,340,000

            6,700,000

          (640,000)

                      (21,769)

                 (179,193)

                (200,962)

      (439,038)

The requirement

Revenue recognized over time

Revenue recognized upon completion

Situation

                                  2,021

                   2,022

                 2,023

2021

                        2,022

                       2,023

1

                              286,119

                452,308

             241,573

0

                               -  

                  980,000

2

                              286,119

                (16,119)

             270,000

0

                               -  

                  540,000

3

                              286,119

             (568,643)

          (287,476)

0

                 (179,193)

                (390,807)

4

                              167,500

            1,352,500

                        -  

0

              1,520,000

5

                              167,500

             (167,500)

             370,000

0

                  370,000

6

                              (21,769)

             (179,193)

          (439,038)

                      (21,769)

                 (179,193)

                (439,038)

Add a comment
Know the answer?
Add Answer to:
Brady Construction Company contracted to build an apartment complex for a price of $6,700,000. Construction began...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Brady Construction Company contracted to build an apartment complex for a price of $5,600,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,600,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,560 2,310 1,080 3,390 1,080 — 2 1,560...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,500 2,100 900 3,000 900 — 2 1,500...

  • brady construction company contracted to build an apartment for a price of $6,000,000. Brady Construction Company...

    brady construction company contracted to build an apartment for a price of $6,000,000. Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred (As of the End During Year of the Year) Situation 2021 2022...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,400,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,400,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation Costs Incurred During Year 2021 2022 2023 1,540 2,250 1,020 1,540 1,020 2,560 1,540 2,250 1,920 540 3,040 1,080 540 3,040 1,580 540 3,040 2,200 Estimated costs to Complete (As...

  • Previous questions have wrong answers on here. Brady Construction Company contracted to build an apartment complex...

    Previous questions have wrong answers on here. Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2021 2022 2023 1 1,520 2,190 960 2 1,520 960 2,480 3 1,520 2,190 1,760 4 520 3,020 1,040...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2016 and was completed in 2018. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Required: Copy and complete the following table.

  • 2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction...

    2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,300,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,300,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete (As of the End of the Year) Costs Incurred During Year Situation 2018 2019 2020 2018 2019 2020 11,530 2,220 990 3,210 990 2 1,530 990 2,520...

  • Brady Construction Company contracted to build an apartment complex for a price of $6,100,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $6,100,000. Construction began in 2018 and was completed in 2020. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2018 2019 2020 1,610 2,460 1,230 1,610 1,230 2,840 3 1,610 2,460 2,480 4 6103,110 1,220 610 3,110 2,070 6 610 3,110 2,900 Estimated Costs to...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2013 and was completed in 2015. The following are a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars Costs Incurred During Year Situation 2013 2014 2015 1 1,500 2,100 900 3,000 900 %u2014 2 1,500 900 2,400 3,000 2,400 %u2014 3 1,500 2,100 1,600 3,000 1,500 %u2014 4 500...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT