11) Pembroke Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine
0 0
Add a comment Improve this question Transcribed image text
Answer #1

11)Answer B $ 630,000 is Correct Answer

EXplanation:
Total variable manufacturing overhead = Estimated total machine hours * Variable manufacturing


Estimated total manufacturing overhead = Total Fixed manufacturing overhead cost + Total variable

Manufacturing overhead = 357,000 + 273,000 = $630,000

Answer is $ 630,000


12)Anwer B 60% is Correct Answer

EXplanation:
Variable expense ratio=Variable expense/Sales

which is equal to

(192000/320,000)

which is equal to

=60%

Add a comment
Know the answer?
Add Answer to:
11) Pembroke Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Laflame Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Laflame Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 70,000 $357,000 $ 3.99 The estimated total manufacturing overhead is closest to: Multiple Choice o $630,000 o $357,000 o $273,000 o $357,004

  • Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 40,000 $344,000 $ 3.90 Recently, Job M759 was completed. It required 60 machine-hours. The amount of overhead applied to Job M759 is closest to (Round your intermediate calculations to 2 decimal places.) Multiple Choice $516 $984...

  • Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine- hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine hour 80,000 $312,000 $ 2.10 Recently, Job T629 was completed with the following characteristics: Number of units in the job Total machine-hours 50 200 The predetermined overhead rate is closest to: Multiple Choice o $8.10...

  • Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 40,000 Total fixed manufacturing overhead cost $ 344,000 Variable manufacturing overhead per machine-hour $ 3.90 Recently, Job M759 was completed. It required 60 machine-hours. The amount of overhead applied to Job M759 is closest to: (Round your intermediate calculations to 2 decimal places.) Garrison 16e Rechecks...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ 4.00 Recently, Job T587 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The total job cost...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 96,000 Total fixed manufacturing overhead cost $499,200 Variable manufacturing overhead per direct labor-hour $ 2.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 100 $ 640 $9,600 The...

  • Lupo Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...

    Lupo Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on machine hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 30,900 $154,500 $ 3.80 Recently, Job T687 was completed with the following characteristics Number of units in the job Total machine-hours Direct materials Direct labor cost 10 30 $ 740 $1,480 The amount of...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 30,000 Total fixed manufacturing overhead cost $ 252,000 Variable manufacturing overhead per machine-hour $ 2.10 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 30 Direct materials $ 675 Direct labor cost $ 1,050 The amount of...

  • Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based...

    Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data Total direct labor-hours 70,000 Total fixed manufacturing overhead cost $273,000 Variable manufacturing overhead per direct labor-hour $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 50 Total direct labor-hours 100 Direct materials Direct labor cost $7,000 The...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310,000 $4.00 Recently, Job T687 was completed with the following characteristics: 10 30 Number of units in the job Total machine-hours Direct materials Direct labor cost $730 $1,460 The amount of overhead applied to Job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT