Question

Laflame Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hour
Multiple Choice o $630,000 o $357,000 o $273,000 o $357,004
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total manufacturing overhead = variable overhead + Fixed overhead

= 70000*3.90 + 357000

= $630000

Add a comment
Know the answer?
Add Answer to:
Laflame Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 11) Pembroke Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...

    11) Pembroke Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data (4 pts): Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 70,000 $ 357,000 $ 3.90 The estimated total manufacturing overhead is closest to: A) $273,000 B) $630,000 C) $357,004 D) $357,000 12) Stauffer Corporation has provided the following contribution format income statement. Assume...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 70,000 $273,000 $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 50 100 $ 680 $7,000 The...

  • Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 96,000 Total fixed manufacturing overhead cost $499,200 Variable manufacturing overhead per direct labor-hour $ 2.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 100 $ 640 $9,600 The...

  • Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Harootunian Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine- hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine hour 80,000 $312,000 $ 2.10 Recently, Job T629 was completed with the following characteristics: Number of units in the job Total machine-hours 50 200 The predetermined overhead rate is closest to: Multiple Choice o $8.10...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: 30,300 Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour $575,700 4.00 16 Recently, Job T687 was completed 699 Number of units the job Total machine-hours Direct materials Direct labor cost $1, The amount of overhead applied to Job T687 is closest to NO Choice...

  • Spang Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Spang Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 20,000 $176,000 2.20 Recently, Job P505 was completed with the following characteristics Total machine-hours Direct materials Direct labor cost 200 $ 540 $7,200 The amount of overhead applied to Job P505 is closest to: Multiple...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine- hour 31,000 $310,000 $ Recently, Job T687 was completed with the following characteristics: 10 Number of units in the job Total machine-hours Direct materials Direct labor cost 30 $ 730 $1,460 The unit product cost for...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 32,300 $581,400 $ 2.00 Recently, Job T687 was completed with the following characteristics: 10 40 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 630 $1,260 The unit product cost for...

  • Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310, $ Recently, Job T687 was completed with the following characteristics 10 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 730 $1,460 The totaljob cost for Job T687 is...

  • Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...

    Beat Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours The company based its predetermined overhead rate for the current year on the following data: Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 40,000 $344,000 $ 3.90 Recently, Job M759 was completed. It required 60 machine-hours. The amount of overhead applied to Job M759 is closest to (Round your intermediate calculations to 2 decimal places.) Multiple Choice $516 $984...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT