Question

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.

Month
1 2 3 4
Throughput time (days) ? ? ? ?
Delivery cycle time (days) ? ? ? ?
Manufacturing cycle efficiency (MCE) ? ? ? ?
Percentage of on-time deliveries 78 % 73 % 70 % 67 %
Total sales (units) 2330 2230 2116 2036

Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:

Average per Month (in days)
1 2 3 4
Move time per unit 0.8 0.4 0.5 0.5
Process time per unit 3.4 3.2 3.0 2.8
Wait time per order before start of production 23.0 25.2 30.0 32.3
Queue time per unit 4.3 5.1 6.0 7.0
Inspection time per unit 0.6 0.9 0.9 0.6


Required:

1-a. Compute the throughput time for each month.

1-b. Compute the delivery cycle time for each month.

1-c. Compute the manufacturing cycle efficiency (MCE) for each month.

2. Evaluate the company’s performance over the last four months.

3-a. Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as in month 4, except that through the use of Lean Production the company is able to completely eliminate the queue time during production. Compute the new throughput time and MCE.

3-b. Refer to the move time, process time, and so forth, given for month 4. Assume in month 6 that the move time, process time, and so forth, are again the same as in month 4, except that the company is able to completely eliminate both the queue time during production and the inspection time. Compute the new throughput time and MCE.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Ans. Throughput Time Delivery Cycle Manufacturing Cycle
Months Time Efficiency
1 9.1 days 32.1 days 37.36%
2 9.6 days 34.8 days 33.33%
3 10.4 days 40.4 days 28.85%
4 10.9 days 43.2 days 25.69%
*Calculations for 1 a, b, c are shown below:
Ans. 1 a Throughput time = Move time + Process time + Queue time + Inspection time
Months
Particulars 1 2 3 4
Move time per unit 0.8 0.4 0.5 0.5
Process time per unit 3.4 3.2 3 2.8
Inspection time per unit 0.6 0.9 0.9 0.6
Queue time 4.3 5.1 6 7
Total (Throughput Time) 9.1 days 9.6 days 10.4 days 10.9 days
Ans. 1 b Manufacturing cycle efficiency = Process time or value added time / Throughput time * 100
Months
1 3.4 / 9.1 * 100 37.36%
2 3.2 / 9.6 * 100 33.33%
3 3 / 10.4 * 100 28.85%
4 2.8 / 10.9 * 100 25.69%
Ans. 1 c Delivery cycle time = Throughput time + Wait time per order before start of production
Months
1 9.1 + 23 32.1 days
2 9.6 + 25.2 34.8 days
3 10.4 + 30 40.4 days
4 10.9 + 32.3 43.2 days
Ans. 2 The Throughput time measure displays Favorable trends
Delivery cycle time - days measure displays Favorable trends
Manufacturing cycle efficiency - days measure displays Unfavorable trends
*Throughput time and delivery cylce time are increasing every month, so these are favorable trends and
Manufacturing cycle efficiency is an unfavorable trend as it is decreasing every month.
Ans. 3 Month 5 Month 6
Throughput time 3.9 days 3.3 days
Manufacturing cycle efficiency (MCE) 71.79% 84.85%
*Calculations:
Ans. 3 a Month 5 :
Throughput time:
Move time per unit 0.5
Process time per unit 2.8
Inspection time per unit 0.6
Total 3.9 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
2.8 / 3.9 * 100
71.79%
Ans. 3 b Month 6 :
Throughput time:
Move time per unit 0.5
Process time per unit 2.8
Total 3.3 days
MCE (manufacturing cycle efficiency) = Process time / Throughput time * 100
2.8 / 3.3 * 100
84.85%
Add a comment
Know the answer?
Add Answer to:
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 1 Throughput time (days) Delivery cycle time...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month ? Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations, Month 34 Throughput time (days) Delivery cycle time (days)...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month Throughput time (days) Delivery cycle time (days) Manufacturing...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 ? Throughput time (days) Delivery...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations Throughput time (days) Delivery cycle time (days) Manufacturing cycle...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Problem 10-14 Measures of Internal Business Process Performance (LO10-3]...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

  • DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...

    DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT