CET 470 Infrastructure, Heavy Highway and Equipment Spring 2019 m 2.9 on p. 58) A track...
Spring 2019 ck dozer cost $235,000 to purchase. FOG and minor $235 nhr A major engine repair costing CET 470 infrastructure, Heavy Highway aan n. 58) A track 2. Infrastructure, Heavy Highway and Equipment Homework 1 Equipment Economics the Interest Table to calculate values. Show your calculations and procedures Instruction: Use a cash flow diagram. Otherwise, the deduction will be applied. new truck for $125,000 and plans to use the truck for 6 years. tractor has purchased a After 6...
please solve problem 1
i
dont need help with the next question i need it with this one
Name. Problem 1: A track dozer cost $185,500 to purchase. Fuel, oil, grease, and minor maintenance are estimated to cost $37.00 per operating hour. A major engine repair costing $26,000 will probably be required after 7,200 hr of use. The expected resale price (salvage value) is 21% of the original purchase price. The machine is expected to have a useful life of...