rate positively .. let me know if you need any clarification..
ans a | |||||
i | ii | iii=i*ii | |||
Year | Cash flow | PVIF @ 11% | present value | ||
0 | -146000 | 1.0000 | (146,000.00) | ||
1 | 70000 | 0.9009 | 63,063.06 | ||
2 | 69000 | 0.8116 | 56,001.95 | ||
3 | 53000 | 0.7312 | 38,753.14 | ||
11,818.15 | |||||
NPV = | 11,818.15 | ||||
ans b | |||||
i | ii | iii=i*ii | |||
Year | Cash flow | PVIF @ 22% | present value | ||
0 | -146000 | 1.0000 | (146,000.00) | ||
1 | 70000 | 0.8197 | 57,377.05 | ||
2 | 69000 | 0.6719 | 46,358.51 | ||
3 | 53000 | 0.5507 | 29,187.47 | ||
(13,076.98) | |||||
NPV = | (13,076.98) |
newconnect.mheducation.com Chapter - Discounted Cash Flow - Part 2 Chapter 5 - DCF & Interest Rates...
newconnect.mheducation.com Cash Flow - Part 2 Chapter 5 - DCF & Interest Rates - Part 3 Chapter 8 PV & Investment Criteria i Saved A project that will provde annual cash flows of $2,350 for nine years costs $9,700 today, a. At a required return of 12 percent, what is the NPV of the project? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g. 32.16.) b. At a required return of 28 percent, what is...
newconnect. mheducation.com hapter 5. Discounted Cash Flow - Part 2 Chapter 5 - DCF & Interest Rates - Part 3 Chapter 8 Chapter 8 - NPV & Investment Criteria 6 Stenson, Inc., imposes a payback cutoff of three years for its international Investment projects. Assume the company has the following two projects available. 14.28 Year Cash Flow A Cash Flow B 0 -$62,000 -$ 107,000 1 25,500 27,500 2 33,200 32,500 27,500 26,500 13,500 233,000 What is the payback period...
Saved CHAPTER 8 GRADED HOMEWORK A A project has the following cash flows: Cash Flow $112,000 - 67,000 - 57,000 points 8 00:24:33 eBook a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g. 32.16.) b. What is the NPV of this project if the required return is 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,...
A project has the following cash flows: Year Cash Flow $74,000 -56.000 -26,800 2 . a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places,...
Consider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 –$ 340,000 –$ 51,500 1 55,000 25,000 2 75,000 23,000 3 75,000 20,500 4 450,000 15,600 Whichever project you choose, if any, you require a 16 percent return on your investment. a-1 What is the payback period for each project? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback period Project A years Project...
A project has the following cash flows: Year Cash Flow 0 $ 66,500 1 –41,000 2 –32,800 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return % What is the NPV of this project if the required return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
A project has the following cash flows: Year Cash Flow $ 68,000 -44,000 - 31,600 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places,...
A project has the following cash flows: Year Cash Flow $ 71,000 -50,000 -29,200 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,...
A project has the following cash flows: Year Cash Flow $73,000 -54,000 - 27,600 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,...
A project has the following cash flows: Year Cash Flow $112,000 - 67,000 - 57,000 N- a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the NPV of the...