Question

Sheridan Company acquires land for $71000 cash. Additional costs are as follows. Removal of shed $400...

Sheridan Company acquires land for $71000 cash. Additional costs are as follows.

Removal of shed

$400

Filling and grading

1800

Salvage value of lumber of shed

170

Broker commission

1330

Paving of parking lot

12000

Closing costs

580


Sheridan will record the acquisition cost of the land as

$75280.

$74940.

$71000.

$72910.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Acquisition cost of the land

= 71,000+400+1800-170+1330+580

= 74,940.

Option B is the answer

Comment if you face any issues
Add a comment
Know the answer?
Add Answer to:
Sheridan Company acquires land for $71000 cash. Additional costs are as follows. Removal of shed $400...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT