Sheridan Company acquires land for $81000 cash. Additional costs are as follows. Removal of shed $500 Filling and grading 1900 Salvage value of lumber of shed 110 Broker commission 1250 Paving of parking lot 10000 Closing costs 460
Cost of land = Cash 81,000 + removal 500 + filling 1900 - Salvage 110 + broker commission 1250 + closing cost 460 = 85,000 |
|
Comment if you face any issues |
Sheridan Company acquires land for $81000 cash. Additional costs are as follows. Removal of shed $500...
Sheridan Company acquires land for $81000 cash. Additional costs are as follows. Removal of shed $500 Filling and grading 1900 Salvage value of lumber of shed 110 Broker commission 1250 Paving of parking lot 10000 Closing costs 460
Sheridan Company acquires land for $71000 cash. Additional costs
are as follows.
Removal of shed
$400
Filling and grading
1800
Salvage value of lumber of shed
170
Broker commission
1330
Paving of parking lot
12000
Closing costs
580
Sheridan will record the acquisition cost of the land as
$75280.
$74940.
$71000.
$72910.
Bonita Company acquires land for $86900 cash. Additional costs
are as follows:
Removal of shed
$ 300
Filling and grading
1500
Salvage value of lumber of
shed
120
Broker commission
1100
Paving of parking lot
10000
Closing costs
510
Bonita will record the acquisition cost of the land as
$90190.
$90430.
$96900.
$88510.
nment Multiple Choice Question 60 Crane Company acquires land for $72000 cash. Additional costs are as follows. Removal of shed $700 1700 110 Filling and grading Salvage value of lumber of shed Broker commission Paving of parking lot Closing costs 1060 8000 640 Crane will record the acquisition cost of the la $72000. $76210. O $73700. $75990 LINK TO TEXT
please help with these accouting questions!
IV ab X X APA 1 Styles Styles Pane Sensiti 7. Burke Company purchases land for $180,000 cash. Burke assumes $5,000 in property taxes due on the land. The title and attorney fees totaled $2,000. Burke has the land graded for $4,400. They paid $20,000 for paving of a parking lot. What amount does Burke record as the cost for the land? A) $186,400. B) $211,400 C) $191,400 D) $180,000. 8. Ramirez Company acquires...
1) A company incurred the following costs: Purchase price of land Survey fees Payment for demolition of old building on land Back property taxes on land Paving costs for parking lot Fence around perimeter of land Lights in parking lot Signs for new business $270,000 4,000 20,000 2,000 60,000 15,000 90,000 5,000 What is the cost of the land? A) $270,000. B) $296,000. C) $356,000. D) $294,000. E) None of the above. 2) Equipment costing $40,000with a book value of...
1) A company incurred the following costs: Purchase price of land Survey fees Payment for demolition of old building on land Back property taxes on land Paving costs for parking lot Fence around perimeter of land Lights in parking lot Signs for new business $270,000 4,000 20,000 2,000 60,000 15,000 90,000 5,000 What is the cost of the land? A) $270,000. B) $296,000. C) $356,000. D) $294,000. E) None of the above. 2) Equipment costing $40,000with a book value of...
On February 1, 2016, Jekel & Hyde Inc. purchased land and incurred other costs relative to the construction of a new warehouse. The costs related to the purchase of the land and the construction of the building are listed below: Purchase price of the land $231,250 Title insurance for the land $1,500 Legal fees to purchase land $1,000 Cost of razing an old building on the land to be used $8,500 for the construction of the warehouse Delinquent property taxes...
The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk next to the item letter. a. Fee paid to attorney for title search $ 2,500 b. Cost of real estate acquired as a plant site: Land 285,000 Cost of real estate acquired as a plant site: Building (to be demolished) 55,000 c. Delinquent real estate taxes on property, assumed by purchaser 15,500...
Allocating payment xed asset accounts The following payents and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asteris a. Fee paid to attorney for title seardch $2,500 b. Cost of real estate acquired as a plant site: Land 285,000 Building (to be demolished) 55,000 c. Delinquent real estate taxes on property, assumed by purchaser 15,500 d. Cost of razing and removing building acquired in (b)...