Answer-
The upfront expenditure ( Immediately incurred ) = $ 25
million / year
Cost of capital = 10 %
Project A
Payback period
Year | 0 | 1 | 2 | 3 | 4 | |
Project A | Net Cash Flow (NCF) | - $ 25 | $ 5 | $ 10 | $ 15 | $ 20 |
Cumulative NCF | - $ 25 | - $ 20 | - $ 10 | $ 5 | $ 25 |
Payback period = full years until recovery + (unreovered cost at the beginning of last year / cash flow during the last year)
Payback period = 2 + ( $ 10 / $ 15 ) = 2 + 0.66 = 2.66 years
Project B
Payback period
Year | 0 | 1 | 2 | 3 | 4 | |
Project B | Net Cash Flow (NCF) | - $ 25 | $ 20 | $ 10 | $ 8 | $ 6 |
Cumulative NCF | - $ 25 | - $ 5 | $ 5 | $ 13 | $ 19 |
Payback period = 1 + ( $ 5 / $ 10 ) = 1 + 0.5 = 1.5 years
2)
IRR Project A
IRR will be calculated by setting NPV =0
0 = - $ 25 + $ 5 / ( 1 +IRR) + $ 10 / ( 1+IRR)2 + $ 15 / ( 1+ IRR)3 + $ 20 / ( 1+ IRR)4
IRR = 27.27 %
IRR Project B
0 = - $ 25 + $ 20 / ( 1 +IRR) + $ 10 / ( 1+IRR)2 + $ 8 / ( 1+ IRR)3 + $ 6 / ( 1+ IRR)4
IRR = 36.15 %
3)
If the cost of capital = 5 %
Project A
NPV = - $ 25 + $ 5 / (1 + 0.05) + $ 10 / (1 +0.05)2 + $ 15 / (1+0.05)3 + $ 20 / (1+0.05)4
NPV = - $ 25 + $ 5 / 1.05 + $ 10 / 1.052 + $ 15 / 1.053 + $ 20 / 1.054
NPV = - $ 25 + $ 5 / 1.05 + $ 10 / 1.1025 + $ 15 / 1.158 + $ 20 / 1.2155
NPV = - $ 25 + $ 4.76 + $ 9.07 + $ 12.95 + $ 16.45
NPV = - $ 25 + $ 43.23
NPV = $ 18.23
Project B
NPV = - $ 25 + $ 20 / (1 + 0.05) + $ 10 / (1 +0.05)2 + $ 8 / (1+0.05)3 + $ 6 / (1+0.05)4
NPV = - $ 25 + $ 20 / 1.05 + $ 10 / 1.052 + $ 8 / 1.053 + $ 6 / 1.054
NPV = - $ 25 + $ 20 / 1.05 + $ 10 / 1.1025 + $ 8 / 1.158 + $ 6 / 1.2155
NPV = - $ 25 + $ 19.05 + $ 9.07 + $ 6.91 + $ 4.94
NPV = - $ 25 + $ 39.97
NPV = $ 14.97
Since the projects are mutually exclusive only the project with higher NPV should be selected, therefore Project A ( $ 18.23 ) should be selected over Project B ( $ 14.97).
4)
If the cost of capital = 10 %
Project A
NPV = - $ 25 + $ 5 / (1 + 0.15) + $ 10 / (1 +0.15)2 + $ 15 / (1+0.15)3 + $ 20 / (1+0.15)4
NPV = - $ 25 + $ 5 / 1.15 + $ 10 / 1.152 + $ 15 / 1.153 + $ 20 / 1.154
NPV = - $ 25 + $ 5 / 1.15 + $ 10 / 1.3225 + $ 15 / 1.52 + $ 20 / 1.75
NPV = - $ 25 + $ 4.35 + $ 7.56 + $ 9.87 + $ 11.43
NPV = - $ 25 + $ 33.21
NPV = $ 8.21
Project B
NPV = - $ 25 + $ 20 / (1 + 0.15) + $ 10 / (1 +0.15)2 + $ 8 / (1+0.15)3 + $ 6 / (1+0.15)4
NPV = - $ 25 + $ 20 / 1.15 + $ 10 / 1.152 + $ 8 / 1.153 + $ 6 / 1.154
NPV = - $ 25 + $ 20 / 1.15 + $ 10 / 1.3225 + $ 8 / 1.52 + $ 6 / 1.75
NPV = - $ 25 + $ 17.39 + $ 7.56 + $ 5.26 + $ 3.43
NPV = - $ 25 + $ 33.64
NPV = $ 8.64
Since the projects are mutually exclusive only the project with higher NPV should be selected, therefore Project B ( $ 8.64 ) should be selected over Project A ( $ 8.21).
Your division is considering two investment projects, each of which requires an up-front expenditure of $25...
3. Your division is considering two investment projects, each of which requires an up-front expenditure of $25 million. You estimate that the cost of capital is 10% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 20 10 10 15 20 (1) What are the payback periods for the two projects? (2) What are the IRRs of the two projects? (3) If the two projects are mutually exclusive and...
Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $27 million. You estimate that the cost of capital is 8% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...
Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $22 million. You estimate that the cost of capital is 12% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...
Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 15%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $ Project B: $
Your division is considering two investment projects, each of which requires an up-front expenditure of $20 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $4,500,000 $20,000,000 2 10,000,000 10,000,000 3 20.000.000 6,500,000 What are the two project’s NPVs assuming the cost of capital is 3%, 12%, 17%? What are the two projects’ IRRs at those same costs of capital?
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $19 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are the two projects' net present values,...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $19 million. You estimate that the investments will produce the following net cash flows: Project A Project B Year 1 $ 5,000,000 $20,000,000 Year 2 10,000,000 10,000,000 Year 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $ Project B $ What are...
Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $5,000,000 $20,000,000 2 $10,000,000 $10,000,000 3 $20,000,000 $6,000,000 a. What are the two project’s net present values, assuming the cost of capital is 5%? 10%? 15% · 5%: · 10%: · 15% b. What are the two project’s IRR at these same costs of capital?
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $ Project B: $ What are the...
NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 a. What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $ Project B: $ What...