Question

Your division is considering two investment projects, each of which requires an up-front expenditure of $25 million. You esti
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer-

The upfront expenditure ( Immediately incurred ) = $ 25 million / year
Cost of capital = 10 %

Project A

Payback period

Year 0 1 2 3 4
Project A Net Cash Flow (NCF) - $ 25 $ 5 $ 10 $ 15 $ 20
Cumulative NCF - $ 25 - $ 20 - $ 10 $ 5 $ 25

Payback period = full years until recovery + (unreovered cost at the beginning of last year / cash flow during the last year)

Payback period = 2 + ( $ 10 / $ 15 ) = 2 + 0.66 = 2.66 years

Project B

Payback period

Year 0 1 2 3 4
Project B Net Cash Flow (NCF) - $ 25 $ 20 $ 10 $ 8 $ 6
Cumulative NCF - $ 25 - $ 5 $ 5 $ 13 $ 19

Payback period = 1 + ( $ 5 / $ 10 ) = 1 + 0.5 = 1.5 years

2)

IRR Project A

IRR will be calculated by setting NPV =0

0 = - $ 25 + $ 5 / ( 1 +IRR) + $ 10 / ( 1+IRR)2 + $ 15 / ( 1+ IRR)3 + $ 20 / ( 1+ IRR)4

IRR = 27.27 %

IRR Project B

0 = - $ 25 + $ 20 / ( 1 +IRR) + $ 10 / ( 1+IRR)2 + $ 8 / ( 1+ IRR)3 + $ 6 / ( 1+ IRR)4

IRR = 36.15 %

3)

If the cost of capital = 5 %

Project A

NPV = - $ 25 + $ 5 / (1 + 0.05) + $ 10 / (1 +0.05)2 + $ 15 / (1+0.05)3 + $ 20 / (1+0.05)4

NPV = - $ 25 + $ 5 / 1.05 + $ 10 / 1.052 + $ 15 / 1.053 + $ 20 / 1.054

NPV = - $ 25 + $ 5 / 1.05 + $ 10 / 1.1025 + $ 15 / 1.158 + $ 20 / 1.2155

NPV = - $ 25 + $ 4.76 + $ 9.07 + $ 12.95 + $ 16.45

NPV = - $ 25 + $ 43.23

NPV = $ 18.23

Project B

NPV = - $ 25 + $ 20 / (1 + 0.05) + $ 10 / (1 +0.05)2 + $ 8 / (1+0.05)3 + $ 6 / (1+0.05)4

NPV = - $ 25 + $ 20 / 1.05 + $ 10 / 1.052 + $ 8 / 1.053 + $ 6 / 1.054

NPV = - $ 25 + $ 20 / 1.05 + $ 10 / 1.1025 + $ 8 / 1.158 + $ 6 / 1.2155

NPV = - $ 25 + $ 19.05 + $ 9.07 + $ 6.91 + $ 4.94

NPV = - $ 25 + $ 39.97

NPV = $ 14.97

Since the projects are mutually exclusive only the project with higher NPV should be selected, therefore Project A ( $ 18.23 ) should be selected over Project B ( $ 14.97).

4)

If the cost of capital = 10 %

Project A

NPV = - $ 25 + $ 5 / (1 + 0.15) + $ 10 / (1 +0.15)2 + $ 15 / (1+0.15)3 + $ 20 / (1+0.15)4

NPV = - $ 25 + $ 5 / 1.15 + $ 10 / 1.152 + $ 15 / 1.153 + $ 20 / 1.154

NPV = - $ 25 + $ 5 / 1.15 + $ 10 / 1.3225 + $ 15 / 1.52 + $ 20 / 1.75

NPV = - $ 25 + $ 4.35 + $ 7.56 + $ 9.87 + $ 11.43

NPV = - $ 25 + $ 33.21

NPV = $ 8.21

Project B

NPV = - $ 25 + $ 20 / (1 + 0.15) + $ 10 / (1 +0.15)2 + $ 8 / (1+0.15)3 + $ 6 / (1+0.15)4

NPV = - $ 25 + $ 20 / 1.15 + $ 10 / 1.152 + $ 8 / 1.153 + $ 6 / 1.154

NPV = - $ 25 + $ 20 / 1.15 + $ 10 / 1.3225 + $ 8 / 1.52 + $ 6 / 1.75

NPV = - $ 25 + $ 17.39 + $ 7.56 + $ 5.26 + $ 3.43

NPV = - $ 25 + $ 33.64

NPV = $ 8.64

Since the projects are mutually exclusive only the project with higher NPV should be selected, therefore Project B ( $ 8.64 ) should be selected over Project A ( $ 8.21).

Add a comment
Know the answer?
Add Answer to:
Your division is considering two investment projects, each of which requires an up-front expenditure of $25...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3. Your division is considering two investment projects, each of which requires an up-front expenditure of...

    3. Your division is considering two investment projects, each of which requires an up-front expenditure of $25 million. You estimate that the cost of capital is 10% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 20 10 10 15 20 (1) What are the payback periods for the two projects? (2) What are the IRRs of the two projects? (3) If the two projects are mutually exclusive and...

  • Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which...

    Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $27 million. You estimate that the cost of capital is 8% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...

  • Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which...

    Problem 10-21 Payback, NPV, and MIRR Your division is considering two investment projects, each of which requires an up-front expenditure of $22 million. You estimate that the cost of capital is 12% and that the investments will produce the following after-tax cash flows (in millions of dollars): Year Project A Project B 1 5 20 2 10 10 3 15 8 4 20 6 What is the regular payback period for each of the projects? Round your answers to two...

  • Your division is considering two investment projects, each of which requires an up-front expenditure of $15...

    Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 15%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $    Project B: $   

  • Your division is considering two investment projects, each of which requires an up-front expenditure of $20...

    Your division is considering two investment projects, each of which requires an up-front expenditure of $20 million. You estimate that the investments will produce the following net cash flows: Year                       Project A              Project B 1                              $4,500,000           $20,000,000 2                              10,000,000           10,000,000 3                              20.000.000           6,500,000 What are the two project’s NPVs assuming the cost of capital is 3%, 12%, 17%? What are the two projects’ IRRs at those same costs of capital?

  • NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...

    NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $19 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  5,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $    Project B $    What are the two projects' net present values,...

  • NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...

    NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $19 million. You estimate that the investments will produce the following net cash flows:    Project A Project B Year 1 $ 5,000,000 $20,000,000 Year 2 10,000,000 10,000,000 Year 3 20,000,000 7,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Round your answers to the nearest dollar. Project A $    Project B $    What are...

  • Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. Y...

    Your division is considering two investment projects, each of which requires an up-front expenditure of $15 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $5,000,000 $20,000,000 2 $10,000,000 $10,000,000 3 $20,000,000 $6,000,000 a. What are the two project’s net present values, assuming the cost of capital is 5%? 10%? 15% · 5%: · 10%: · 15% b. What are the two project’s IRR at these same costs of capital?

  • NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...

    NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $  4,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 6,000,000 What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $   Project B: $   What are the...

  • NPV Your division is considering two investment projects, each of which requires an up-front expenditure of...

    NPV Your division is considering two investment projects, each of which requires an up-front expenditure of $17 million. You estimate that the investments will produce the following net cash flows: Year Project A Project B 1 $ 6,000,000 $20,000,000 2 10,000,000 10,000,000 3 20,000,000 7,000,000 a. What are the two projects' net present values, assuming the cost of capital is 5%? Do not round intermediate calculations. Round your answers to the nearest dollar. Project A: $ Project B: $ What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT