Direct Material Cost Variance = Actual Cost - Standard Cost
= (146000 x $1.10) - (20000 x 7 x $1.15) = $400 (F)

Direct Labor Cost variance = Actual Cost - Standard Cost
= (450 x $12.50) - (20000 x 0.027 x $11.50) = $585 (F)

Add a comment
Know the answer?
Add Answer to:
E23-19 (similar to) Question Help Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • All-Star Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 146,000...

    All-Star Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 146,000 square feet of extruded vinyl purchased at $1.10 per square foot. Production required 440 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.15 per square foot. The labor standard was 0.027 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement...

  • Pro Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000...

    Pro Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000 square feet of extruded vinyl purchased at $1.55 per square foot. Production required 440 direct labor hours that cost $12.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.60 per square foot. The labor standard was 0.024 direct labor hour per fender, at a standard cost of $11.50 per hour. boat fenders during...

  • Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000...

    Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....

  • Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000...

    Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....

  • Deluxe Fender, which uses a standard costs system, manufactured 20,000 boat fenders during 2018, using 144,000...

    Deluxe Fender, which uses a standard costs system, manufactured 20,000 boat fenders during 2018, using 144,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 440 direct labor hours that cost $14.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $13.50 per hour. Please compute the...

  • Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000...

    Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....

  • Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000...

    Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000 square feet of extruded vinyl purchased at $1.55 per square foot. Production required 440 direct labor hours that cost $16.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.60 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $15.50 per hour. Read the requirement....

  • Superior Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2016, using 143,000...

    Superior Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2016, using 143,000 square feet of extruded vinyl purchased at $1.30 per square foot. Production required 460 direct labor hours that cost $14.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.35 per square foot. The labor standard was 0.028 direct labor hour per fender, at a standard cost of $13.50 per hour. Compute the cost...

  • Grand Guard, which used a standard cost accounting system, manufactured 130.000 boat fenders during the year...

    Grand Guard, which used a standard cost accounting system, manufactured 130.000 boat fenders during the year using 1.130 000 eet of extruded vinyl purchased at $1.50 per foot. Production required 4,000 direct labor hours that cost $15.50 per hour. The materials standard was 6 feet of vinyl per fender at a standard cost of $150 per foot. The labor standard was 0.025 direct labor hour per fender at a standard cost of $14.50 per hour Read More Requirement 1. Compute...

  • Please help! i asked this question earlier & got wrong answers and wrong formulas. i included...

    Please help! i asked this question earlier & got wrong answers and wrong formulas. i included a pic of what the formulas are supposed to look like! also there are three parts to this question but only one is shown... please help with all 3 parts Homework: Topic 4 Homework (Chapter 23) Save Score: 0 of 10 pts 20, 4 (4 complete) ▼ Hw Score: 29.52%, 17.71 of 60 pts E23-19 (similar to) Question Help * 0) Quality Fender, which...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT