Direct Material Cost Variance = Actual Cost - Standard
Cost
= (146000 x $1.10) - (20000 x 7 x $1.15) = $400 (F)
Direct Labor Cost variance = Actual Cost - Standard Cost
= (450 x $12.50) - (20000 x 0.027 x $11.50) = $585 (F)
E23-19 (similar to) Question Help Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat...
All-Star Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 146,000 square feet of extruded vinyl purchased at $1.10 per square foot. Production required 440 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.15 per square foot. The labor standard was 0.027 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement...
Pro Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000 square feet of extruded vinyl purchased at $1.55 per square foot. Production required 440 direct labor hours that cost $12.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.60 per square foot. The labor standard was 0.024 direct labor hour per fender, at a standard cost of $11.50 per hour. boat fenders during...
Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....
Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....
Deluxe Fender, which uses a standard costs system, manufactured 20,000 boat fenders during 2018, using 144,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 440 direct labor hours that cost $14.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $13.50 per hour. Please compute the...
Best Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 145,000 square feet of extruded vinyl purchased at $1.15 per square foot. Production required 460 direct labor hours that cost $13.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.20 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $12.50 per hour. Read the requirement....
Deluxe Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2018, using 142,000 square feet of extruded vinyl purchased at $1.55 per square foot. Production required 440 direct labor hours that cost $16.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.60 per square foot. The labor standard was 0.025 direct labor hour per fender, at a standard cost of $15.50 per hour. Read the requirement....
Superior Fender, which uses a standard cost system, manufactured 20,000 boat fenders during 2016, using 143,000 square feet of extruded vinyl purchased at $1.30 per square foot. Production required 460 direct labor hours that cost $14.50 per hour. The direct materials standard was seven square feet of vinyl per fender, at a standard cost of $1.35 per square foot. The labor standard was 0.028 direct labor hour per fender, at a standard cost of $13.50 per hour. Compute the cost...
Grand Guard, which used a standard cost accounting system, manufactured 130.000 boat fenders during the year using 1.130 000 eet of extruded vinyl purchased at $1.50 per foot. Production required 4,000 direct labor hours that cost $15.50 per hour. The materials standard was 6 feet of vinyl per fender at a standard cost of $150 per foot. The labor standard was 0.025 direct labor hour per fender at a standard cost of $14.50 per hour Read More Requirement 1. Compute...
Please help! i asked this question earlier & got wrong answers and wrong formulas. i included a pic of what the formulas are supposed to look like! also there are three parts to this question but only one is shown... please help with all 3 parts Homework: Topic 4 Homework (Chapter 23) Save Score: 0 of 10 pts 20, 4 (4 complete) ▼ Hw Score: 29.52%, 17.71 of 60 pts E23-19 (similar to) Question Help * 0) Quality Fender, which...