  1. Job Cost Sheet

    Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons for the variances between the estimated and actual costs are noted on the sheet. The data are then available to management in evaluating the efficiency of operations and in preparing quotes on future jobs. On October 1, Remnant Carpet Company gave Jackson Consulting an estimate of $3,150 to carpet the consulting firm’s newly leased office. The estimate was based on the following data:

    Estimated direct materials:
    30 meters at $33 per meter $ 990
    Estimated direct labor:
    24 hours at $30 per hour 720
    Estimated factory overhead (75% of direct labor cost) 540
    Total estimated costs $2,250
    Markup (40% of production costs) 900
    Total estimate $3,150

    On October 3, Jackson Consulting signed a purchase contract, and the delivery and installation were completed on October 10.

    The related materials requisitions and time tickets are summarized as follows:

    Materials Requisition No. Description     Amount
    112 15 meters at $33 $495
    114 19 meters at $33 627
    Time Ticket No. Description     Amount
    H10 12 hours at $30 $360
    H11 16 hours at $30 480

    Required:

    Enter amounts as positive numbers.

    1. Complete that portion of the job order cost sheet that would be prepared when the estimate is given to the customer.

    2. Record the costs incurred, and complete the job order cost sheet.

    JOB ORDER COST SHEET
    Customer Jackson Consulting Date October 1
    Date wanted October 10
    Date completed October 10
    Job. No.
    ESTIMATE
    Direct Materials Direct Labor Summary
    Amount Amount Amount
    30 Meters at $33 $ 24 Hours at $30 $ Direct Materials $
    Direct Labor
    Factory Overhead
    Total $ Total $ Total cost $
    ACTUAL
    Direct Materials Direct Labor Summary
    Mat. Req. No. Description Amount Time Ticket No. Description Amount Item Amount
    112 15 Meters at $33 $ H10 12 Hours at $30 $ Direct Materials $
    Direct Labor
    114 19 Meters at $33 H11 16 Hours at $30 Factory Overhead
    Total $ Total $ Total Cost $

    What is the best explanation for the variances between actual costs and estimated costs. (For this purpose, assume that the additional meters of material used in the job were spoiled, the factory overhead rate has proven to be satisfactory, and an inexperienced employee performed the work.)

    1. The direct materials cost exceeded the estimate by $132 because 4 meters of materials were spoiled. The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inexperienced employee. The factory overhead cost exceeded the estimate because an additional $90 of factory overhead was allocated because of the increase in direct labor.
    2. Management didn't provide enough direction to complete tasks on budget.
    3. The direct materials cost exceeded the estimate by $75 because 3 meters of materials were spoiled.
    4. The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inexperienced employee.

    Select the correct answer from the above choices.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer is given below

JOB ORDER COST SHEET Customer Jackson consulting Date October 1 Date wanted October 10 Date completed October 10 Job. No. Dir

Add a comment
Know the answer?
Add Answer to:
Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...

    ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...

  • Ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office bui...

    ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...

  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...

    Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...

  • Answer questions 1-4? encing Inc. uses a job order cost system. The following data summarize the...

    Answer questions 1-4? encing Inc. uses a job order cost system. The following data summarize the operations 11,840 related to production for March, the first month of operations: A. Materials purchased on account, $45,000. B. Materials requisitioned and factory labor used: LAL LEDGER Job Materials Factory Labor $2,500 301 $1,850 302 3,150 7,220 303 2,200 5,350 304 1,800 2,400 6,225 2,900 305 4,230 306 1,770 For general factory use 1,200 5,000 C. Factory overhead costs incurred on account, $1,800. D....

  • Job-Order Costing U-Design-It Furniture Company uses a job-order cost system.   The company applies manufacturing overhead to...

    Job-Order Costing U-Design-It Furniture Company uses a job-order cost system.   The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $144,000 for the year and the estimated direct labor hours were 18,000 hours.   In March, Job #175 was completed.   Direct materials totaled $7,000. Total labor costs were $6,000 at $20 per hour. At the end of the year, it was determined that the company worked 17,000 direct labor hours...

  • Laurelton Heating & Cooling installs and services commercial heating and cooling systems. Laurelton uses job costing...

    Laurelton Heating & Cooling installs and services commercial heating and cooling systems. Laurelton uses job costing to calculate the cost of as jobs Overhead is allocated to each job based on the number of direct labor hours spent on that job. At the beginning of the current year, Laurelton estimated that its overhead for the coming year would be $64 800. It also anticipated using 4,050 direct labor hours for the year In October, Laurelton started and completed the following...

  • A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 2,500...

    A job cost sheet of Sandoval Company is given below. Job Cost Sheet JOB NO. 2,500 469 Quantity White Lion CagesDate Requested ITEM 7/2 FOR Todd Company Date Completed 7/31 Direct Materials Direct Labor Manufacturing Overhead Date 700 900 600 750 400 500 1,650 1,525 500 625 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Answer the following questions. (1) What are the source documents for direct materials, direct labor, and manufacturing overhead costs...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT