ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet CompaRequired Enter amounts as positive numbers 1. Complete that portion of the job order cost sheet that would be prepared when tWhat is the best explanation for the variances between actual costs and estimated costs. (For this purpose, assume that the a

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Estimate
Direct Materials Direct Labor Summary
Amount Amount Amount
30 meters at $ 34 $ 1,020.00 20 hours at $ 30 $ 600.00 Direct Materials $ 1,020.00
Direct Labor $     600.00
Factory OH $     450.00
Total $ 1,020.00 Total $ 600.00 Total cost $ 2,070.00
Actual
Mat. Req. Direct Materials Time Tickt Direct Labor Summary
No. Amount No. Amount Amount
112 15 meters at $ 34 $     510.00 M10 10 hours at $ 30 $ 300.00 Direct Materials $ 1,156.00
114 19 meters at $ 34 $     646.00 M11 14 hours at $ 30 $ 420.00 Direct Labor $     720.00
Factory OH $     540.00
Total $ 1,156.00 Total $ 720.00 Total cost $ 2,416.00

Option (a) explains in the best way the reasons for variances

Add a comment
Know the answer?
Add Answer to:
ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office bui...

    ob Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...

  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet...

    Job Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons...

  • Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant...

    Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed,...

  • eBook Calculator Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office...

    eBook Calculator Job Order Cost Sheet Remnant Carpet Company sells and installs commercial carpeting for office buildings. Remnant Carpet Company uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job...

  • Answer questions 1-4? encing Inc. uses a job order cost system. The following data summarize the...

    Answer questions 1-4? encing Inc. uses a job order cost system. The following data summarize the operations 11,840 related to production for March, the first month of operations: A. Materials purchased on account, $45,000. B. Materials requisitioned and factory labor used: LAL LEDGER Job Materials Factory Labor $2,500 301 $1,850 302 3,150 7,220 303 2,200 5,350 304 1,800 2,400 6,225 2,900 305 4,230 306 1,770 For general factory use 1,200 5,000 C. Factory overhead costs incurred on account, $1,800. D....

  • Job-Order Costing U-Design-It Furniture Company uses a job-order cost system.   The company applies manufacturing overhead to...

    Job-Order Costing U-Design-It Furniture Company uses a job-order cost system.   The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $144,000 for the year and the estimated direct labor hours were 18,000 hours.   In March, Job #175 was completed.   Direct materials totaled $7,000. Total labor costs were $6,000 at $20 per hour. At the end of the year, it was determined that the company worked 17,000 direct labor hours...

  • Jackson Company applies overhead to products using direct labor hours as the activity level. During 2019,...

    Jackson Company applies overhead to products using direct labor hours as the activity level. During 2019, Jackson Company had the following estimated costs: Direct materials .................... $258,000 Direct labor ........................ 255,000 Advertising ......................... 35,000 Rent on factory building ............ 36,000 Depreciation .................... ... 60,000 Indirect materials .................. 32,000 Sales commissions ................... 50,000 Production supervisor's salary ...... 40,000 Insurance on factory equipment ...... 18,000 CEO's salary ........................ 95,000 The following additional information is available: 1. 30% of the depreciation relates to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT