Help me calculate the total costs using normal costing for each model!
Acre Construction assemblies residential houses. It uses a job-costing system with two direct-cost categories (direct materia
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Normal costing Laguna Model Mission Model
Direct cost 106430+36475= 142905 127325+41320= 168645
Indirect cost 46000 50000
Total cost 188905 218645

**Direct cost =Direct material +Direct labor

Add a comment
Know the answer?
Add Answer to:
Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June...

    1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June 2017 106,440 $ 36,625 $ Mission Model May-Oct 2017 127,250 41,130 1,090 $ 970 Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $7,425,000, and the actual direct labor-hours were 165,000. Print Done X Requirements 1. Compute the...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of 2017, Andrews is comparing the costs of several jobs that were started and completed in 2017 E (Click the icon to view the...

  • Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Avery budgets 2017 assembly-support costs to be $8,100,000 and 2017 direct labor-hours to be 135,000. At the end of 2017, Avery is comparing the costs of several jobs that were started and completed in 2017. (Click the icon to view the data.)...

  • Job costing, normal and actual costing. Atkinson Construction assembles residential houses

    Job costing, normal and actual costing. Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $ 8,800,000 and 2017 direct labor-hours to be 220,000.At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017 .Laguna...

  • Company names may be different but the structure is the same! Please replace names with new...

    Company names may be different but the structure is the same! Please replace names with new company names if this applies! Thank you! Ashton Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Ashton budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of...

  • E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with...

    E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Attleboro budgets 2017 assembly-support costs to be $8,600,000 and 2017 direct labor-hours to be 215,000. At the end of 2017, Attleboro is comparing the costs of several jobs that were started and completed in 2017. (Click the...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $ 8,000,000 and 2017 direct labor-hours to be 160,000 . At the end of 2017 , Andrews is comparing the costs of several jobs that were started and completed in 2017 .Direct materials and direct...

  • materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base...

    materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Anderson budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166.000. At the end of 2017, Anderson is comparing the costs of several jobs that were started and completed in 2017 (Click the icon to view the data) Read the requirements Requirement 1. Compute the (a) budgeted indirect.cost rate and (b) actual indirect.cost...

  • 1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model...

    1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and Why might Atkinson Construction prefer normal costing over actual costing? 4-24 Budgeted manufacturing overhead rate, allocated manufacturing overhead. Taylor Company uses bosting. It allocates manufacturing overhead costs using a budgeted rate per machine-hour. The following data are available for 2017: Budgeted manufacturing overhead costs $3,800,000 Budgeted machine-hours 200,000 Actual manufacturing overhead costs $3,660,000 Actual machine-hours...

  • Kirac & Partners, a Quebec-based public accounting partnership, specializes in audit services. Its job-costing system has...

    Kirac & Partners, a Quebec-based public accounting partnership, specializes in audit services. Its job-costing system has a single direct-cost category (professional labor) and a single indirect-cost pool (audit support, which contains all costs of the Audit Support Department). Audit support costs are allocated to individual jobs using actual professional labor-hours. Kirac & Partners employs 10 professionals to perform audit services. Budgeted and actual amounts for 2017 are as follows: E: (Click the icon to view the data.) Read the requirements....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT