Question

Job costing, normal and actual costing. Atkinson Construction assembles residential houses

Job costing, normal and actual costing. Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $ 8,800,000 and 2017 direct labor-hours to be 220,000.

At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017 .


Laguna ModelMission Model
Construction periodFeb-June 2017May-0ct 2017
Direct material costs$106,550$127,450
Direct labor costs$36,250$41,130
Direct labor-hours9701,000

Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $ 8,400,000, and the actual direct labor-hours were 200,000.

Required

1. Compute the (a) budgeted indirect-cost rate and (b) actual indirect-cost rate. Why do they differ?

2. What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and (b) actual costing?

3. Why might Atkinson Construction prefer normal costing over actual costing?

2 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

1 . Budgeted indirect cost rate = budgeted indirect cost (assembly support)/budgeted direct labour hours

= $8800000/220000 hours = $40 per direct labour hours.

Actual indirect cost rate = actual indirect cost (assembly support)/actual direct labour hours

= $8400000/200000 hours = $42 per direct labour hour.

Note that both the rates i.e. budgeted I direct cost rate and actual indirect cost rate differs because both the numerators and denominators in the two calculations are different. In case of budgeted indirect cost rate it is based on budgeted numbers whereas in case of actual indirect cost rate it is based upon actual numbers.

2. (a). Job costs of Laguna model and the mission model using normal costing is as follow :-

Particulars Laguna model mission model
Direct cost
- direct material $106550 $127450
- direct labor $36250 $41130
Total of direct cost $142800 $168580
Indirect costs : assembly support $38800 ($40x970) $40000 ($40x100)
Total costs as per normal capacity $181600 $208580

2 . (b) . Job cost of laguna model and the mission model using actual costing is as follows :-

Particulars Laguna model mission model
Direct cost
- direct material $106550 $127450
- direct labor $36250 $41130
total of direct cost $142800 $168580
Indirect cost : assembly support $40740 (42x970) $42000 (42x1000)
Total cost using actual costing $183540 $210580

3 . Normal costing enabled Atkinson to report a job cost as soon as the job is completed, assuming that both the direct material and direct labor cost is known at the time of use. Once the 970 direct labor hours are known for the laguna model, atkinson can compute the $181600 cost figure using normal costing. Atkinson csn use the information to manage the cost of lagun model job as well as to bid on similar jobs later in the year. On the other hand Atkinson has to wait till the end of the year to compute the cost of $183540 of Laguna model using actual costing. That's why Atkinson construction might prefer normal costing per actual costing

Add a comment
Know the answer?
Add Answer to:
Job costing, normal and actual costing. Atkinson Construction assembles residential houses
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of 2017, Andrews is comparing the costs of several jobs that were started and completed in 2017 E (Click the icon to view the...

  • Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Avery budgets 2017 assembly-support costs to be $8,100,000 and 2017 direct labor-hours to be 135,000. At the end of 2017, Avery is comparing the costs of several jobs that were started and completed in 2017. (Click the icon to view the data.)...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $ 8,000,000 and 2017 direct labor-hours to be 160,000 . At the end of 2017 , Andrews is comparing the costs of several jobs that were started and completed in 2017 .Direct materials and direct...

  • Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential...

    Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor hours is the location base for assembly support costs in December 2016. Acre budgets 2017 by support costs to be $8.000.000 and 2017 direct labor hours to be 100,000. At the end of 201 Acre is comparing the costs of several...

  • E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with...

    E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Attleboro budgets 2017 assembly-support costs to be $8,600,000 and 2017 direct labor-hours to be 215,000. At the end of 2017, Attleboro is comparing the costs of several jobs that were started and completed in 2017. (Click the...

  • 1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June...

    1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June 2017 106,440 $ 36,625 $ Mission Model May-Oct 2017 127,250 41,130 1,090 $ 970 Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $7,425,000, and the actual direct labor-hours were 165,000. Print Done X Requirements 1. Compute the...

  • Company names may be different but the structure is the same! Please replace names with new...

    Company names may be different but the structure is the same! Please replace names with new company names if this applies! Thank you! Ashton Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Ashton budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of...

  • materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base...

    materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Anderson budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166.000. At the end of 2017, Anderson is comparing the costs of several jobs that were started and completed in 2017 (Click the icon to view the data) Read the requirements Requirement 1. Compute the (a) budgeted indirect.cost rate and (b) actual indirect.cost...

  • 1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model...

    1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and Why might Atkinson Construction prefer normal costing over actual costing? 4-24 Budgeted manufacturing overhead rate, allocated manufacturing overhead. Taylor Company uses bosting. It allocates manufacturing overhead costs using a budgeted rate per machine-hour. The following data are available for 2017: Budgeted manufacturing overhead costs $3,800,000 Budgeted machine-hours 200,000 Actual manufacturing overhead costs $3,660,000 Actual machine-hours...

  • 4-25 Job cesting, accounting for manufacturing overhead, budgeted rates. The Matthew Company uses a normal job-costing...

    4-25 Job cesting, accounting for manufacturing overhead, budgeted rates. The Matthew Company uses a normal job-costing system at its Minneapolis plant. The plant has a machining department and an assem- bly department. Its job-costing system has two direct-cost categories (direct materials and direct manufac- turing labor) and two manufacturing overhead cost pools (the machining department overhead, allocated to jobs based on actual machine-hours, and the assembly department overhead, allocated to jobs based on actual direct manufacturing labor costs). The 2017...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT