Question

materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for asse
Mission Actual Coating Laguna Model (13) Total costs Requirement 3. Why might Anderson Construction prefer normal costing ove
(5) O both the cost and hour amounts in the two calculations are different O the cost amounts in the two calculations are dif
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. Budgeted indirect costs/Budgeted direct labor hours = Budgeted indirect cost rate

$8300000/166000 = $50 per DLH

Actual indirect costs/Actual direct labor hours = Actual indirect cost rate

$7425000/165000 = $45 per DLH

These rates differ because both the cost and hour amounts in the two calculations are different.

2(a) Normal costing:

Budgeted indirect cost rate x Actual direct labor hours = Indirect costs

Laguna: $50 per DLH x 980 = $49000

Mission: $50 per DLH x 1070 = $53500

Laguna model Mission model
Direct costs 143225 169235
Indirect costs 49000 53500
Total costs 192225 222735

Direct costs:

Laguna: $106350 + $36875 = $143225

Mission: $127825 + $41410 = $169235

2(b) Actual costing:

Actual indirect cost rate x Actual direct labor hours = Indirect costs

Laguna: $45 per DLH x 980 = $44100

Mission: $45 per DLH x 1070 = $48150

Laguna model Mission model
Direct costs 143225 169235
Indirect costs 44100 48150
Total costs 187325 217385

3. (14) enables Anderson to report a job cost as soon as the job is completed.

(15) manage the cost of their current jobs and bid on similar jobs later in the year.

Add a comment
Know the answer?
Add Answer to:
materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June...

    1 Data Table Laguna Model Construction period Direct materials costs Direct labor costs Direct labor-hours Feb-June 2017 106,440 $ 36,625 $ Mission Model May-Oct 2017 127,250 41,130 1,090 $ 970 Direct materials and direct labor are paid for on a contract basis. The costs of each are known when direct materials are used or when direct labor-hours are worked. The 2017 actual assembly-support costs were $7,425,000, and the actual direct labor-hours were 165,000. Print Done X Requirements 1. Compute the...

  • Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Avery Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Avery budgets 2017 assembly-support costs to be $8,100,000 and 2017 direct labor-hours to be 135,000. At the end of 2017, Avery is comparing the costs of several jobs that were started and completed in 2017. (Click the icon to view the data.)...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of 2017, Andrews is comparing the costs of several jobs that were started and completed in 2017 E (Click the icon to view the...

  • Company names may be different but the structure is the same! Please replace names with new...

    Company names may be different but the structure is the same! Please replace names with new company names if this applies! Thank you! Ashton Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Ashton budgets 2017 assembly-support costs to be $8,300,000 and 2017 direct labor-hours to be 166,000. At the end of...

  • Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials...

    Andrews Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Andrews budgets 2017 assembly-support costs to be $ 8,000,000 and 2017 direct labor-hours to be 160,000 . At the end of 2017 , Andrews is comparing the costs of several jobs that were started and completed in 2017 .Direct materials and direct...

  • Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential...

    Help me calculate the total costs using normal costing for each model! Acre Construction assemblies residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor hours is the location base for assembly support costs in December 2016. Acre budgets 2017 by support costs to be $8.000.000 and 2017 direct labor hours to be 100,000. At the end of 201 Acre is comparing the costs of several...

  • Job costing, normal and actual costing. Atkinson Construction assembles residential houses

    Job costing, normal and actual costing. Atkinson Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Atkinson budgets 2017 assembly-support costs to be $ 8,800,000 and 2017 direct labor-hours to be 220,000.At the end of 2017, Atkinson is comparing the costs of several jobs that were started and completed in 2017 .Laguna...

  • E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with...

    E4-23 (similar to) Question Help Attleboro Construction assembles residential houses. It uses a job-costing system with two direct-cost categories (direct materials and direct labor) and one indirect-cost pool (assembly support). Direct labor-hours is the allocation base for assembly support costs. In December 2016, Attleboro budgets 2017 assembly-support costs to be $8,600,000 and 2017 direct labor-hours to be 215,000. At the end of 2017, Attleboro is comparing the costs of several jobs that were started and completed in 2017. (Click the...

  • 1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model...

    1. Compute the (a) budgeted Y UNI What are the job costs of the Laguna Model and the Mission Model using (a) normal costing and Why might Atkinson Construction prefer normal costing over actual costing? 4-24 Budgeted manufacturing overhead rate, allocated manufacturing overhead. Taylor Company uses bosting. It allocates manufacturing overhead costs using a budgeted rate per machine-hour. The following data are available for 2017: Budgeted manufacturing overhead costs $3,800,000 Budgeted machine-hours 200,000 Actual manufacturing overhead costs $3,660,000 Actual machine-hours...

  • direct materials and direct manufacturing Donna Corporation manufactures custom cabinets for kitchens. It uses a normal...

    direct materials and direct manufacturing Donna Corporation manufactures custom cabinets for kitchens. It uses a normal costing system with two direct cost categories labor--and one indirect cost pool, manufacturing overhead costs It provides the following information for 2017 Click the icon to view the information for 2017) Read the requirement Begin by calculating the budgeted Indirect cost rate. Select the formula and then calculate the rate (Assume the cost allocation base is direct labor hours) Budgeted manufacturing overhead costs Budgeted...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT