Question

JJ Construction Inc. entered into a contract with a customer to build a corporate office on...

JJ Construction Inc. entered into a contract with a customer to build a corporate office on January 1, 2020, for $18,000,000. The customer owns the construction in process during the construction process and the customer is under obligation to pay for any work completed, even if the contract is canceled. The office is expected to be completed in three years for a total cost of $11,400,000. Actual costs incurred through December 31, 2020, are $4,788,000. Determine the amount of revenue to record in 2020 assuming that the cost-to-cost method is used.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Ans:

Revenue to be recognized in the income statement in 2020 = $1800,000*4,788,000/11,400,000= $756,000

Expense amounts to be recognized in the income statement in 2020 = $756,000

Add a comment
Know the answer?
Add Answer to:
JJ Construction Inc. entered into a contract with a customer to build a corporate office on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • JJ Construction Inc. entered into a contract with a customer to build a corporate office on...

    JJ Construction Inc. entered into a contract with a customer to build a corporate office on January 1, 2020, for $18,000,000. The customer owns the construction in process during the construction process and the customer is under obligation to pay for any work completed, even if the contract is canceled. The office is expected to be completed in three years for a total cost of $11,400,000. Actual costs incurred through December 31, 2020, are $4,788,000. Determine the amount of revenue...

  • JJ Construction Inc. entered into a contract with a customer to build a movable storage facility...

    JJ Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $1,800,000. JJ Construction Inc. owns the work in process and constructs this type of storage unit for a number of customers. The customer made a down payment of 10% of the project, with an additional 10% due at the end of year one and the remaining due when it takes control of the facility. The facility is expected to...

  • JJ Construction Inc. entered into a contract with a customer to build a movable storage facility...

    JJ Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $2,100,000. JJ Construction Inc. owns the work in process and constructs this type of storage unit for a number of customers. The customer made a down payment of 10% of the project, with an additional 10% due at the end of year one and the remaining due when it takes control of the facility. The facility is expected to...

  • ABC Construction Inc. entered into a contract with a customer to build a movable storage facility...

    ABC Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $1,200,000. ABC Construction Inc. owns the work in process and constructs this type of storage unit for a number of customers. The customer made a down payment of 10% of the project, with an additional 10% due at the end of year one and the remaining due when it takes control of the facility. The facility is expected to...

  • ABC Construction Inc. entered into a contract with a customer to build a movable storage facility...

    ABC Construction Inc. entered into a contract with a customer to build a movable storage facility on January 1, 2020, for $1,200,000. ABC Construction Inc. owns the work in process and constructs this type of storage unit for a number of customers. The customer made a down payment of 10% of the project, with an additional 10% due at the end of year one and the remaining due when it takes control of the facility. The facility is expected to...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • A construction company entered into a fixed-price contract to build an office building for $20 million....

    A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $44 million....

    A construction company entered into a fixed-price contract to build an office building for $44 million. Construction costs incurred during the first year were $14 million and estimated costs to complete at the end of the year were $21 million. The building was completed during the second year. Construction costs incurred during the second year were $22 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

  • A construction company entered into a fixed-price contract to build an office building for $48 million....

    A construction company entered into a fixed-price contract to build an office building for $48 million. Construction costs incurred during the first year were $18 million and estimated costs to complete at the end of the year were $27 million. The building was completed during the second year. Construction costs incurred during the second year were $28 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes revenue...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT