Question

Project S has a cost of $10,000 and is expected to produce benefits (cash flow) of...

Project S has a cost of $10,000 and is expected to produce benefits (cash flow) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flow of $7,400 per year for 5 years. Calculate the two projects’ NPV, IRR, and MIRR, assuming a cost of capital of 12%. If these are two mutually exclusive projects, which project would be selected? Justify your answer(s).   

HAND WRITE WORK PLEASE :)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

NPV of Project S =PMT*((1-(1+r)^-n)/r)-Cost=3000*((1-(1+12%)^-5)/12%)-10000 =814.13
NPV of Project L =PMT*((1-(1+r)^-n)/r) -Cost=7400*((1-(1+12%)^-5)/12%)-25000 =1675.34

IRR of Project S using Financial Calculator
N=5;PMT =3000;PV=-10000;CPT I/Y =15.24%

IRR of Project L using Financial Calculator
N=5;PMT =7400;PV=-25000;CPT I/Y =14.67%

FV of Cash Flows of S =PMT*((1+r)^n-1)/r) =3000*(((1+12%)^5-1)/12%)=19058.5421
MIRR =(FV/PV)^(1/n)-1 =(19058.5421/10000)^(1/5)-1 =13.77%

FV of Cash Flows of L =PMT*((1+r)^n-1)/r) =7400*(((1+12%)^5-1)/12%)=47011.07
MIRR =(FV/PV)^(1/n)-1 =(47011.07/25000)^(1/5)-1 =13.46%
​​​​​​​
Project L should be selected as it has higher NPV


​​​​​​​

Add a comment
Know the answer?
Add Answer to:
Project S has a cost of $10,000 and is expected to produce benefits (cash flow) of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...

    Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected the produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, IRRs, MIRRs and Pls assuming a cost of capital of 12%? Which project would be selected assuming they are mutually exclusive, using each ranking method? Which project should actually be selected?

  • 4. Project S has a cost of $10,000 and is expected to produce cash flows of...

    4. Project S has a cost of $10,000 and is expected to produce cash flows of $3000 per year for 5 years. Project L has a cost of $25,000 and is expected to produce cash flows of $7400 for 5 years. Calculate the NPV and IRR of the two projects assuming a cost of capital of 12%. Which project would you select, assuming they are mutually exclusive, using each ranking method?

  • Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of...

    Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,500 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $8,000 per year for 5 years. a. Calculate the two projects' NPVS, assuming a cost of capital of 14%. Round your answers to the nearest cent Project S Project L Which project would be selected, assuming they are mutually exclusive? -Select b. Calculate the two projects'...

  • Capital Budgeting Methods Project S has a cost of $9,000 and is expected to produce benefits...

    Capital Budgeting Methods Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of $2,700 per year for 5 years. Project L costs $26,000 and is expected to produce cash flows of $7,100 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 10%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $   Project L: $   Which project would be selected, assuming they...

  • 2. Project P costs $35,800 and is expected to produce cash flows of $8,500 per year...

    2. Project P costs $35,800 and is expected to produce cash flows of $8,500 per year for six years. Project Q costs $90,000 and is expected to produce cash flows of $21,000 per year for six years. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8 percent. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected?

  • Project S has a cost of $15,000 and is expected to produce benefits (cash flows) of...

    Project S has a cost of $15,000 and is expected to produce benefits (cash flows) of $3,000 per year for 6 years. Calculate the project's Net Present Value (NPV) assuming a cost of capital of 15%. -$5,734 -$1,675 -$3,647 -$814 $3,000

  • 2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for...

    2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $10,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0....

  • eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected...

    eBook Project S requires an initial outlay at t - 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years, Mutually exclusive Project L requires an initial outlay at t = 0 of $48,000, and its expected cash flows would be $9,550 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer a. Project L, since the NPV > NPV- b. Both...

  • 10. Consider the following two mutually exclusive projects: Year Cash Flow (A) - $175,000 10,000 25,000...

    10. Consider the following two mutually exclusive projects: Year Cash Flow (A) - $175,000 10,000 25,000 25,000 375,000 Cash Flow (B) - $20,000 10,000 5,000 3,000 1,000 Whichever project you choose, if any, you require a 15 percent return on your investment. a. If you apply the payback criterion, which investment will you choose? b. If you apply the NPV criterion, which investment will you choose? c. If you apply the IRR criterion, which investment will you choose? d. Based...

  • Projects A and B are mutually exclusive. Project A costs $10,000 and is expected to generate...

    Projects A and B are mutually exclusive. Project A costs $10,000 and is expected to generate cash inflows of $4,000 for 4 years. Project B costs $10,000 and is expected to generate a single cash flow in year 4 of $20,000. The cost of capital is 17.5%. What is the NPV of the project you should accept? Group of answer choices $865.73 $492.49 $3,911.49 $354.94

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT