a:
Project P | Project Q | |
NPV | 3494.48 | 7080.47 |
IRR | 11.15% | 10.55% |
MIRR | 9.69% | 9.37% |
Payback | 4.21 | 4.29 |
b: If they are independent, select Both since both have positive NPVs
If they are mutually exclusive select Q since it has higher NPV.
Workings
Year | Project P | Cumulative CF | Project Q | Cumulative CF |
0 | -35800 | -35800 | -90000 | -90000 |
1 | 8500 | -27300 | 21000 | -69000 |
2 | 8500 | -18800 | 21000 | -48000 |
3 | 8500 | -10300 | 21000 | -27000 |
4 | 8500 | -1800 | 21000 | -6000 |
5 | 8500 | 6700 | 21000 | 15000 |
6 | 8500 | 15200 | 21000 | 36000 |
2. Project P costs $35,800 and is expected to produce cash flows of $8,500 per year...
Please show all work. Must be completed using financial formulas, NO EXCEL. a. Calculate the NPV, IRR, MIRR, and traditional payback period for each project, assuming a required rate of return of 8%. b. If the projects are independent, which project(s) should be selected? If they are mutually exclusive, which project should be selected? Project P costs $10,400 and is expected to produce cash flows of $3,650 per year for five years. Project Q costs $30,000 and is expected to...
Project S has a cost of $10,000 and is expected to produce benefits (cash flow) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flow of $7,400 per year for 5 years. Calculate the two projects’ NPV, IRR, and MIRR, assuming a cost of capital of 12%. If these are two mutually exclusive projects, which project would be selected? Justify your answer(s). HAND WRITE WORK PLEASE :)
4. Project S has a cost of $10,000 and is expected to produce cash flows of $3000 per year for 5 years. Project L has a cost of $25,000 and is expected to produce cash flows of $7400 for 5 years. Calculate the NPV and IRR of the two projects assuming a cost of capital of 12%. Which project would you select, assuming they are mutually exclusive, using each ranking method?
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected the produce cash flows of $7,400 per year for 5 years. Calculate the two projects' NPVs, IRRs, MIRRs and Pls assuming a cost of capital of 12%? Which project would be selected assuming they are mutually exclusive, using each ranking method? Which project should actually be selected?
2. Project S costs $10,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $10,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Both Projects S and L, since both projects have IRR's > 0....
Project S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,500 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $8,000 per year for 5 years. a. Calculate the two projects' NPVS, assuming a cost of capital of 14%. Round your answers to the nearest cent Project S Project L Which project would be selected, assuming they are mutually exclusive? -Select b. Calculate the two projects'...
Capital Budgeting Methods Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of $2,700 per year for 5 years. Project L costs $26,000 and is expected to produce cash flows of $7,100 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 10%. Do not round intermediate calculations. Round your answers to the nearest cent. Project S: $ Project L: $ Which project would be selected, assuming they...
Project S costs $11,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $27,000 and its expected cash flows would be $7,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Both Projects S and L, since both...
Project S costs $16,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $50,000 and its expected cash flows would be $12,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend?
(Discounted payback period) Gio's Restaurants is considering a project with the following expected cash flows: Year Project Cash Flow (millions) $(210) AWNO If the project's appropriate discount rate is 11 percent, what is the project's discounted payback period? The project's discounted payback period is years. (Round to two decimal places.) (Mutually exclusive projects and NPV) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash flows: Project A Project B Year Cash Flow...