Allure company manufactures and distributes two products M and
XY. Overhead cost are currently allocated using the number of units
produced as the allocation base. The controller has recommended
changing to an activity-based (ABC) system.
She has collected the following information.
Activity Cost Driver Amount M XY
Production Setup No. of setups $90,000 6 14
Material & handling No. of parts $48,000 56 24
Packaging cost No. of units 333,750 111,000 74,000
What is the total overhead allocated to product M?
Multiple coice,
$333.750
$260,850
$210.900
$283.050
Answer | |||||
The correct option is B : $ 260,850 | |||||
Explanation | |||||
Activity |
Cost Driver | Amount | M | XY | Total |
Production Setup | No of setups | $ 90,000 | $ 6 | $ 14 | $ 20 |
Material handling | No of parts | $ 48,000 | $ 56 | $ 24 | $ 80 |
Packaging costs | No of Units | $333,750 | $111,000 | $ 74,000 | $185,000 |
$471,750 | |||||
Activity | Allocation to Product M | ||||
Production Setup | 90000/20*6 | $ 27,000 | |||
Material handling | 48000/80*56 | $ 33,600 | |||
Packaging costs | 333750/185000*74000 | $200,250 | |||
Total Overhead | $260,850 | ||||
please like |
Allure company manufactures and distributes two products M and XY. Overhead cost are currently allocated using...
Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: Cost Driver Activity Production setups Amount M XY Number of setups $90,000 45,000 12 18 Number of parts Material handling 63 27 Packaging costs Number of units 165,000 90,000 60,000 $300,000 What is the total overhead per unit...
Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: XY Cost Driver Amount Activity 12 8 Production setups Number of setups 77,000 56 14 Number of parts 56,000 Material handling 56,000 Number of units 203,000 84,000 Packaging costs $336,000 What is the total overhead allocated to Product...
Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: Activity Cost Driver Amount M XY Production setups Number of setups $ 69,000 6 14 Material handling Number of parts 52,000 60 15 Packaging costs Number of units 215,000 112,000 48,000 $ 336,000 What is the total overhead...
Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: Activity Cost Driver Amount M XY Production setups Number of setups $ 69,000 6 14 Material handling Number of parts 52,000 60 15 Packaging costs Number of units 215,000 112,000 48,000 $ 336,000 What is the total overhead...
Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: Activity Cost Driver Amount M XY Production setups Number of setups $ 96,000 12 28 Material handling Number of parts 46,000 42 28 Packaging costs Number of units 225,500 90,000 60,000 $ 367,500 What is the total overhead...
Allure Company manufactures and distributes two products, M and XY. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: Activity Cost Driver Amount M XY Production setups Number of setups $ 96,000 12 28 Material handling Number of parts 46,000 42 28 Packaging costs Number of units 225,500 90,000 60,000 $ 367,500 What is the total overhead...
RS Company manufactures and distributes two products, R and S. Overhead costs are currently allocated using the number of units produced as the allocation base. The controller has recommended changing to an activity-based costing (ABC) system. She has collected the following information: 1.What is the total overhead allocated to Product R using the current system? 2.What is the total overhead per unit allocated to Product R using activity-based costing (ABC)? 3.What is the total overhead allocated to Product S using...
Problem D: CBW Corporation manufactures travel clocks and watches. Overhead costs are currently allocated using direct tabor hours, but the controller has recommended using an activity based costing system based on the following data: Cost Driver Watches Activity Cost Travel assigned Clocks Production setup Setups Se s $100.000 20 30 e setups setups Material handling and Parts requisition $30.000 24 parts 36 parts Packaging and shipping Units shipped 80.000 units 120.000 units . Total overhead $190,000 1 Compute the amount...
Problem D:C&W Corporation manufactures travel clocks and watches. Overhead costs are currently allocated using direct labor-hours, but the controller has recommended using an activity-based costing system based on the following data: 11 > UNS Activity Cost Driver Cost assigned Travel Clocks Watches Production setup Setups $100,000 20 setups 30 setups Material handling and requisition Parts $30,000 24 parts 36 parts Packaging and shipping Units shipped $60,000 80,000 units 120,000 units Total overhead $190,000 1. Compute the amount of total overhead...
Paris, Inc, Produces two products, Product A and Product B. If currently allocates overhead costs using direct-labor hours, but the controller has recommended an activity-based costing (ABC) system using the following data: Activity Level Activity Cost-Driver Base Cost Product A Product B Production setup Number of setups 90,000 11 19 Materials handing & requisition Number of parts per unit 15,000 6 18 Packaging & shipping Number of units shipped 45,000 60,000 120,000 Total overhead 150,000 A, Compute the amount of...