Question

During 2017, Vaughn Manufacturing expected Job No. 26 to cost $300000 of overhead, $500000 of materials,...

During 2017, Vaughn Manufacturing expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Vaughn applied overhead based on direct labor cost. Actual production required an overhead cost of $360000, $640000 in materials used, and $300000 in labor. All of the goods were completed. What amount was transferred to Finished Goods?

$1300000
$1240000
$1390000
$1000000
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Overhead rate = Estimated overhead/Estimated labor cost

= 300,000/200,000 = 150% of dl cost

Amount transferred to Finished goods

= Direct Materials + Direct Labor + Overhead

= 640,000 + 300,000 + (300,000*150%)

= 1,390,000

Option C

Add a comment
Know the answer?
Add Answer to:
During 2017, Vaughn Manufacturing expected Job No. 26 to cost $300000 of overhead, $500000 of materials,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During 2019, Crane Company expected Job No. 26 to cost $300000 of overhead, $500000 of materials,...

    During 2019, Crane Company expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Crane applied overhead based on direct labor cost. Actual production required an overhead cost of $330000, $580000 in materials used, and $250000 in labor. All of the goods were completed. What amount was transferred to Finished Goods? $1000000 $1130000 $1205000 $1160000

  • Multiple Choice Question 106 During 2017, Waterway Industries expected Job No. 26 to cost $300000 of...

    Multiple Choice Question 106 During 2017, Waterway Industries expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Waterway applied overhead based on direct labor cost. Actual production required an overhead cost of $290000, $470000 in materials used, and $190000 in labor. All of the goods were completed. What amount was transferred to Finished Goods? $950000 $960000 $945000 $1000000 Multiple Choice Question 111 Crane Company developed the following data for the current year: Beginning...

  • During 2019, Concord Corporation expected Job No. 51 to cost $200000 of overhead, $450000 of materials,...

    During 2019, Concord Corporation expected Job No. 51 to cost $200000 of overhead, $450000 of materials, and $100000 in labor. Concord applied overhead based on direct labor cost. Actual production required an overhead cost of $215000, $490000 in materials used, and $140000 in labor. All of the goods were completed. What amount was transferred to Finished Goods? $845000 $910000 $830000 $750000

  • During 2016 Caruba Manufacturing expected Job 25 to cost $75,000 of overhead, $130,000 of material, and...

    During 2016 Caruba Manufacturing expected Job 25 to cost $75,000 of overhead, $130,000 of material, and $25,000 in labour. Caruba applied overhead based on direct labour cost. Actual production required an overhead cost of $80,000, $140,000 in materials used; and $20,000 in labour. All of the goods were completed. What amount was transferred to Finished Goods? a) $240,000 b) $230,000 c) $220,000 d) $210,000 why the answer is C

  • Question 19 O out of 3 points During 2007, Caruba Manufacturing expected Job 51 to cost...

    Question 19 O out of 3 points During 2007, Caruba Manufacturing expected Job 51 to cost $400,000 of overhead, $500,000 of material, and $200,000 in labor. Caruba applies overhead based X on direct labor cost. Actual production required $520,000 in materials and $240,000 in labor. All of the goods were completed. What amount was transferred to Finished Goods? Selected Answer: b. $1,100,000 Answers: a. $1,070,000 1 b. $1,100,000 C. $1,000,000 d. $1,240,000

  • When a job is finished, the company makes an entry to transfer its total cost to...

    When a job is finished, the company makes an entry to transfer its total cost to finished goods inventory. This response is incorrect because it assumes total costs represents the sum of the actual manufacturing overhead costs, expected overhead costs, and expected materials costs. The correct total costs = direct materials ($750,000) + direct labor ($300,000) + overhead applied [($600,000/ $400,000) or 1.50 x $300,000] = $1,500,000 (“Assigning Costs to Finished Goods”). In the current year, Mitchell Manufacturing expected Job...

  • Marcelino's March 31 inventory of raw materials is $80.000 Raw materials purchases in April are $500000...

    Marcelino's March 31 inventory of raw materials is $80.000 Raw materials purchases in April are $500000 and factory payroll cost in April is $363.000. Overhead costs incurred in April are indirect materials. $50,000 indirect labor. $23.000, factory rent. $32,000, factory utilities. S19.000 and factory equipment depreciation, $51,000. The predetermined overhead rate is 50% of direct labor cost. Job 306 is sold for $635,000 cash in April. Costs of the three jobs worked on in April follow Job 386 Job 387...

  • Weinrich Manufacturing uses a job order cost system and applies overhead to production on the basis...

    Weinrich Manufacturing uses a job order cost system and applies overhead to production on the basis of direct labor hours. On January 1, 2019, Job No. 25 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $10,000; direct labor $6,000; and manufacturing overhead $9,000. Job No. 23 had been completed at a cost of $42,000 and was part of finished goods inventory. There was a $8,000 balance in...

  • Weinrich Manufacturing uses a job order cost system and applies overhead to production on the basis...

    Weinrich Manufacturing uses a job order cost system and applies overhead to production on the basis of direct labor hours. On January 1, 2019, Job No. 25 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $10,000; direct labor $6,000; and manufacturing overhead $9,000. Job No. 23 had been completed at a cost of $42,000 and was part of finished goods inventory. There was a $8,000 balance in...

  • Fannin Company completed Job No. A20 during 2017. The job cost sheet listed the following: Direct...

    Fannin Company completed Job No. A20 during 2017. The job cost sheet listed the following: Direct materials $10,300 Direct labor $5,600 Manufacturing overhead applied Units produced $4,600 Units sold 1,000 units 400 units How much is the cost of the finished goods on hand for this job? $30,750 $12,300 $20,500 $8,200

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT