Flexible budget for March,
Particulars | Amount |
Machine Hours | 17,000 (Hours) |
Utilities | 19,900 |
Maintenance | 69,200 |
Supplies | 6,800 |
Indirect Labour | 1,20,200 |
Depreciation | 67,600 |
Total | 2,83,700 |
Working/Calculation for Flexible budget,
1. Machine Hours - Actual Machine hour worked i.e.17,000 hour
2. Utilities - As per cost formula 16,500 is fixed and additional 0.20 for each hour therefore 0.20*17,000= 3,400 hence total revised amount is 19,900 (16500+3400)
3. Maintenance - Fixed 38,600 and additional 1.8 for each hr therefore 1.8*17,000= 30,600 hence total revised amount is 69,200 (38600+30600)
4. Supplies - 0.40 for each hr hence revised amount is 6,800 (0.40*17000)
5. Indirect Labour - Fixed 94,700 and additional 1.5 for each hr therefore 1.5*17,000= 25,500 hence total revised amount is 1,20,200 (94700+25500)
6. Revised Depreciation is 67,600
Stuck on these last few. Problem 9-23 Flexible Budgets and Spending Variances (LO9-1, LO9-2] You have...
Problem 9-23 Flexible Budgets and Spending Variances [LO9-1, LO9-2] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Problem 9-23 Flexible Budgets and Spending Variances [LO9-1, LO9-2] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Check my world Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent...
Problem 9-20 Activity and Spending Variances [LO9-1, LO9-2, LO9-3) You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs."You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead...
Problem 9-19 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Problem 9-23 Flexible Budgets and Spending Variances You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company’s costing system and “do what you can to help us get better control of our manufacturing overhead costs.” You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in overhead planning...
Saved Pre-Built Problems Problem 9-20 Activity and Spending Variances [LO9-1, Lo9-2, Lo9-3] by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has u find that the company has never used a flexible budget, and you suggest that preparing such a budget would be You have just been hired asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs You find...
Problem 9-20 Activity and Spending Varlances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...
Problem 9-19 Activity and Spending Variances [LO9-1, LO9-2, LO9-3] You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never used a flexible budget, and you suggest that preparing such a budget would be an excellent first step in...