Use the table to find the value of each asset today
ASSET |
Year |
Amount |
Appropriate required return |
A |
1 |
3,000 |
8% |
2 |
3,000 |
||
3 |
3,000 |
||
B |
1 through infinity |
500 |
5% |
C |
1 |
0 |
6% |
2 |
0 |
||
3 |
0 |
||
4 |
0 |
||
5 |
45,000 |
||
D |
1 through 5 |
1,500 |
4% |
6 |
8,500 |
||
E |
1 |
2,000 |
7% |
2 |
3,000 |
||
3 |
5,000 |
||
4 |
7,000 |
||
5 |
4,000 |
||
6 |
1,000 |
||
Use the table to find the value of each asset today ASSET Year Amount Appropriate required...
Valuation of assets Using the information provided in the following table, find the value of each asset today. P6-13 Cash flow Year Amount $ 3,000 3,000 3,000 $ 500 Asset Appropriate required return 8% 1 through oo 5% 6% 4 45,000 $ 1,500 8,500 $ 2,000 3,000 5,000 7,000 4,000 1,000 1 through5 4% 790 4
(Present value of an uneven stream of payments) You are given three investment alternatives to analyze. The cash flows from these three investments are as follows:InvestmentEnd of YearABC1$1,000$2,000$5,00022,0002,0005,00033,0002,000(5,000)4(4,000)2,000(5,000)54,0005,00015,000 What is the present value of each of these three investments if the appropriate discount rate is 11 percent?
14. The following table shows the cash flow for the costs of the Self Performing Contractor and estimates for revenues from a residential project. (in x1000 TL) a) Calculate the Net Cash Flow and the Cumulative Cash Flow for the project (2 points) b) What is the payback period for the project? (2 points) c) What is the Net Present Value (NPV) of the project to the Self Performing Contractor, if the discount rate is i=7% (3 points). d) Would...
6. You’ve been tasked to evaluate an existing piece of
machinery.You collected the following data:
Today
One Year Two Years Three Years Four Years Five Years Six Years
Seven Years Eight Years Nine Years Ten Years
Salvage Value
$20,000 $10,000 $5,000 $2,500 $1,000 $500 $250 $0.00 $0.00 $0.00
$0.00
Annual MX Cost
$1,000 $2,000 $3,000 $4,000 $5,000 $6,000 $7,000 $8,000
$9,000
$10,000
What is the useful life of the existing piece of machinery? Cost
of capital is 4%. Hint calculate...
Table of Crashing DecisionACTIVITYIMMEDIATE PREDECESSOR(S)NORMALCRASHNORMALCRASHA...323,0003,300B...648,0009,000CA114,0004,000 DA543,5004,000EB434,7505,500FC222,0002,000 GD114,0004,000HD,F323,5003,750IE,G323,0004,250JE215,0007,000Since no indirect cost nor penalty cost information is offered, please consider the schedule and crash cost issues only.1. Using Table of Crashing Decision, what is the earliest completion time of this project if normal times are used for all activities?A. fewer than 13 weeks; B. 13 weeks; C. 14 weeks; D. more than 14 weeks2. Using Table of Crashing Decision, what is the minimum time schedule for this project?A. fewer than 8 weeks; B. 8...
Calculate the payback period for a project that has the following cash flows? The required return is 12.0%. Year Cash Flow 0 $ (12,000) 1 $ 1,000 2 $ 2,000 3 $ 3,000 4 $ 4,000 5 $ 5,000 6 $ 6,000 2.25 years 3.25 years 3.85 years 4.40 years None of these are correct.
Assume that a radiologist group practice has the following cost structure: Fixed costs $500,000 Variable cost per procedure $25 Charge (price) per procedure $100 Furthermore, assume that the group expects to perform 7,500 procedures in the coming year. a. Construct the group’s base case projected P&L statement. (See exhibit 5-5). b. What is the group’s contribution margin? c. What is the group’s breakeven point in volume? d. What volume is required to provide a pretax profit of $100,000? e. Complete...
Calculate the payback period for a project that has the following cash flows? The required return is 12.0%. Year Cash Flow 0 $ (12,000) 1 $ 1,000 2 $ 2,000 3 $ 3,000 4 $ 4,000 5 $ 5,000 6 $ 6,000 Group of answer choices 2.25 years 3.85 years 3.25 years 4.40 years None of these are correct.
Calculate the payback period for a project that has the following cash flows? The required return is 12.0%. Year Cash Flow 0 $ (12,000) 1 $ 6,000 2 $ 5,000 3 $ 4,000 4 $ 3,000 5 $ 2,000 6 $ 1,000 Group of answer choices 2.25 years None of these are correct. 3.25 years 4.40 years 3.85 years
Examine the depreciation table shown below. The depreciation method most likely being used is the: Year Beginning of Year Book Value Depreciation Expense Net Book Value 1 $10,000 $1,000 $9,000 2 9,000 2,000 7,000 3 7,000 1,000 6,000 4 6,000 3,000 3,000 5 3,000 500 2,500 Select one: a. Double-declining balance method b. Periodic method c. Straight-line method d. Units-of-production method