Question

At the beginning of 2017, Stellar Construction Company changed from the completed-contract method to recognizing revenue...

At the beginning of 2017, Stellar Construction Company changed from the completed-contract method to recognizing revenue over time (percentage-of-completion) for financial reporting purposes. The company will continue to use the completed-contract method for tax purposes. For years prior to 2017, pretax income under the two methods was as follows: percentage-of-completion $114,200, and completed-contract $79,400. The tax rate is 40%.

Prepare Stellar’s 2017 journal entry to record the change in accounting principle. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

Account Titles and Explanation

Debit

Credit

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Pre tax under % completion method. =. $114,200 Pre tax under completed - method =. $79,400 % completed reported=. $34,800. Hi

Add a comment
Know the answer?
Add Answer to:
At the beginning of 2017, Stellar Construction Company changed from the completed-contract method to recognizing revenue...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • At the beginning of 2017, Culver Construction Company changed from the completed-contract method to recognizing revenue...

    At the beginning of 2017, Culver Construction Company changed from the completed-contract method to recognizing revenue over time (percentage-of-completion) for financial reporting purposes. The company will continue to use the completed-contract method for tax purposes. For years prior to 2017, pretax income under the two methods was as follows: percentage-of-completion $110,500, and completed-contract $72,300. The tax rate is 30%. Prepare Culver’s 2017 journal entry to record the change in accounting principle. (Credit account titles are automatically indented when amount is...

  • Blue Construction Company, which began operations in 2017, changed from the completed-contract to...

    Blue Construction Company, which began operations in 2017, changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2018. For tax purposes, the company employs the completed-contract method and will continue this approach in the future. The appropriate information related to this change is as follows. Pretax Income from Percentage-of-Completion Completed-Contract Difference 2017 $966,000 $600,000 $366,000 2018 906,000 434,000 472,000 (a) Assuming that the tax rate is 35%, what is the amount of net income...

  • Tamarisk Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction...

    Tamarisk Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2018. For tax purposes, the company employs the completed-contract method and will continue this approach in the future. (Hint: Adjust all tax consequences through the Deferred Tax Liability account.) The appropriate information related to this change is as follows. Pretax Income from: Percentage-of-Completion Completed-Contract Difference 2017 $714,000 $647,000 $67,000 2018 642,000 512,000 130,000 (a) Assuming that the tax rate is 30%, what...

  • inment NEX MY INSTRUCTOR FULL SCREEN PRINTER VERSION Exercise 22-1 Whispering Construction Company changed from the...

    inment NEX MY INSTRUCTOR FULL SCREEN PRINTER VERSION Exercise 22-1 Whispering Construction Company changed from the completed-contract to the percentage-of-completion method of accounting for long-term construction contracts during 2018. For tax purposes, the company employs the completed: contract method and will continue this approach in the future. (Hint: Adjust all tax consequences through the Deferred Tax Liability account.) The appropriate information related to this change is as follows. Pretax Income from: Percentage-of- Completed Completion Contract $761,000 $610,000 688,000 462,000 2017...

  • At the beginning of 2015, a construction company changed from the completed-contract method to the percentage-of-completion...

    At the beginning of 2015, a construction company changed from the completed-contract method to the percentage-of-completion method for accounting purposes but not for tax purposes. Income before taxes under both methods for the past three years appears below: 2013 2014 2015 Completed-Contract $ 475,000 625,000 700,000 Percentage-of-Completion $ 900,000 700,000 1,050,000 Assuming an income tax rate of 40% for all years, what amount will be debited to Construction in Process account, to record the change at the beginning of 2015?

  • Headland Construction Company began work on a $419,400 construction contract in 2017. During 2017, Headland incurred...

    Headland Construction Company began work on a $419,400 construction contract in 2017. During 2017, Headland incurred costs of $280,200, billed its customer for $216,300 and collected $174,500. At December 31, 2017, the estimated additional costs to complete the project total $161,600. Prepare Headland's journal entry to record proft or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is...

  • At the beginning of 2018, a construction company that began operations in 2016 changed from the...

    At the beginning of 2018, a construction company that began operations in 2016 changed from the completed-contract method to the percentage-of-completion method for accounting purposes but not for tax purposes. Gross profit figures under both methods for the past three years appear below: Completed-Contract Percentage-of-Completion 2016 $ 950,000 $ 1,800,000 2017 1,250,000 1,900,000 2018 1,400,000 2,100,000 Assuming an income tax rate of 30% for all years, the effect of this accounting change on prior periods should be reported by f...

  • d. none UI ile dov. 23.During 2018, a construction company changed from the completed-contract method to...

    d. none UI ile dov. 23.During 2018, a construction company changed from the completed-contract method to the percentage- of-completion method for accounting purposes but not for tax purposes. Gross profit figures under both methods for the past three years appear below: Completed-Contract Percentage-of-Completion $ 800,000 2016 $ 475,000 950,000 2017 625,000 2018 1.050,000 700.000 S1.800.000 $2.800.000 Assuming an income tax rate of 40% for all years, the effect of this accounting change on prior periods should be reported by a...

  • Exercise 22-1 Monty Construction any changed from the comed-contract to the percent method and will continue...

    Exercise 22-1 Monty Construction any changed from the comed-contract to the percent method and will continue this proach in the future. Ad alta com of completion method of e s through the Deferred to using for long-term construction s account. The programmation 2018 For de change the c ente r s Pretax income from Percentage of Completed Completion Contract 5727.000 $561.000 640.000 490,000 Difference 1.000 190.000 (a) Assuming that the tax is 04. What is the amount of income that...

  • Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred...

    Cheyenne Construction Company began work on a $424,000 construction contract in 2020. During 2020, Cheyenne incurred costs of $279,500, billed its customer for $204,500, and collected $170,500. At December 31, 2020, the estimated additional costs to complete the project total $150,500. Prepare Cheyenne’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. Cheyenne Construction Company began work on a $424.000 construction contract in 2020. During 2020, Cheyenne incurred costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT