Question

1. Suppose the firm estimates its WACC to be 10%. (A) Should the WACC be used...

1. Suppose the firm estimates its WACC to be 10%.

(A) Should the WACC be used to evaluate all of its potential projects, even if they vary in risk? Explain.

(B) Would the NPVs change if the WACC changed? Explain.

1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #2

ANSWER :


(A) 


WACC estimated by the company should not be applied to evaluate all projects irrespective of risks involved. For average risk projects, estimated WACC can be applied. For high risk and low risk projects risk-adjusted WACC should be applied.


Risk-adjusted WACC can be calculate based on beta of similar projects and then required return rate can be calculated using CAPM model. This rate will be risk-adjusted WACC for use in evaluating the projects in accordance of their risks.


For high risk projects, beta will be higher and correspondingly adjusted WACC will be higher than the normal one. Similarly low risk project will have lower beta and lower adjusted WACC. 


This approach would be more realistic and avoid over or under valuation of the projects.


(B)


NPV will change if WACC is changed, since all the future expected earnings will be discounted at the changed WACC. A higher WACC will lower the NPV and a lower WACC will raise the NPV. 



answered by: Tulsiram Garg
Add a comment
Answer #1

A) WACC is Cost of capital
So If NPV is Positive & IRR is greater than WACC, the project is acceptable.
If NPV Is negative, Project is risky & should not be taken even if IRR is high.

Would the NPVs change if the WACC changed? Explain.

The NPV always depends on the WACC. If the cost of capital changes, NPV would also change. There is a direct relation betweenthe NPV and WACC. Increased cost of capital leads to higher NPV and decrease cost of capital obviously leads to lower NPV.

Add a comment
Know the answer?
Add Answer to:
1. Suppose the firm estimates its WACC to be 10%. (A) Should the WACC be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Suppose a firms estimates its WACC to be 15%. Should the WACC be used to evaluate...

    Suppose a firms estimates its WACC to be 15%. Should the WACC be used to evaluate all of its potential projects, even it they vary in risk? If not, what might be "reasonable" costs of capital for average-, high-, and low-risk projects? Scanlon Inc.'s CFO hired you as a consultant to help her estimate the cost of capital. You have been provided with the following data: risk-free rate = 3.20%; required return on the market = 15.75%; and beta=0.86. Based...

  • Why do we use the overall cost of capital for investment decisions even when only one...

    Why do we use the overall cost of capital for investment decisions even when only one source of capital will be used (e.g., debt)? Suppose a firm estimates its weighted average cost of capital (WACC) to be 10%. Should the WACC be used to evaluate all of its potential projects, even if they vary in risk? If not, what might be “reasonable” costs of capital for average, high and low-risk projects?

  • Suppose Acme Industries correctly estimates its WACC at a given point in time and then uses that same cost of capital to...

    Suppose Acme Industries correctly estimates its WACC at a given point in time and then uses that same cost of capital to evaluate all projects of various risks for the next 10 years. ACME will most likely a)become less risky over time, because it will tend to accept more low risk projects that high risk projects. b)become more risky over time, because it will tend to accept more high risk projects that low risk projects. c)continue at the same risk,...

  • LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%, which of the following projects (A, B, and C) should the company accept? O A. Project B, which is of below-average risk and has a return of 8.5%. O B. None of the projects listed in the choices should be accepted. C. Project C, which is of above-average risk...

  • LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    LaPango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk projects have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 9%. B) Accept Project b, if Project b is...

  • Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk proje...

    Suppose a company uses a WACC of 8% for below-risk projects, 10% for average-risk projects, and 12% for above-risk projects. Which of the following independent projects should the company accept? Assume the company uses NPV as its primary accept/reject criteria and that all projects have conventional cash flows. a. Without information about the projects' NPVs, we cannot determine which projects should be accepted. b. Project A, which has average risk and an IRR = 9%. c. All of the projects...

  • Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects...

    Lapango Inc. estimates that its average-risk projects have a WACC of 10%, its below-average risk projects have a WACC of 8%, and its above-average risk project: have a WACC of 12%. Which of the following project(s) should the company accept with the features of each project being described as follows? (Hint: No calculation is needed) A) Accept Project a, if Project a is of average risk and has a return of 11%. B) Accept Project b, if Project b is...

  • Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for av...continues

    Suppose Tapley Inc. uses a WACC of 8% for below-average risk projects, 10% for average-risk projects, and 12% for above-average risk projects. Which of the followingindependent projects should Tapley accept, assuming that the company uses the NPV method when choosing projects?a.Project A, which has average risk and an IRR = 9%.b.Project B, which has below-average risk and an IRR = 8.5%.c.Project C, which has above-average risk and an IRR = 11%.d.Without information about the projects' NPVs we cannot determine which...

  • Апаlysis OPTIMAL CAPITAL BUDGET Marble Construction estimates that its WACC is 10 % if equity comes...

    Апаlysis OPTIMAL CAPITAL BUDGET Marble Construction estimates that its WACC is 10 % if equity comes from retained earnings. However, if the company issues new stock to raise new equity, it estimates that its WACC will rise to 10.8%. The company believes that it will exhaust its retained earnings at $2,500,000 of capital due to the number of highly profitable projects available to the firm and its limited earmings. The company is considering the following seven investment projects: Project Size...

  • Marble Construction estimates that its WACC is 10% if equity comes from retained earnings. However, if...

    Marble Construction estimates that its WACC is 10% if equity comes from retained earnings. However, if the company issues new stock to raise new equity, it estimates that its WACC will rise to 10.8%. The company believes that it will exhaust its retained earnings at $2,500,000 of capital due to the number of highly profitable projects available to the firm and its limited earnings. The company is considering the following seven investment projects: Project Size IRR A $650,000 14.0% B...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT