Company Belera is a manufacturing firm producing specialized equipments. June 1, 2018 B/S shows below balances:
Item Beg
RM 4,270
MOH Applied 32,740
MOH Incurred 36,650
June 1, 2018 subsidiary ledgers (job cost sheets) show 3 jobs are being performed with following balances :
Assigned Costs DM DL MOH
R 660 320 408
S 800 548 675
L 980 580 765
During June, RM purchases on account were TL4,940, and all wages (inclusive of payroll taxes) were paid in cash. Additional MOH of depreciation on factory equipment of TL900 was incurred together with miscellaneous production costs of TL440 on account. A summary of MRSs and LTTs shows below information.
Assigned Costs DM DL
R 870 850
K 2,000 870
S 560 360
L 1,300 1,260
R 360 390
General Use 1,500 1,208
MOH was charged to jobs at a rate of 1.85 per TL of DL costs. Jobs R, S and L were completed in June and sold for a total of TL19,400 in cash.
a) Compute the balance of WIP as at June 30.
b) Compute the balance of FG as at June 30.
c) Calculate the balance of MOH account as at June 30.
R | K | S | L | Total | |
Beginning Balance | 1388.00 | 2023.00 | 2325.00 | 5736.00 | |
Costs added | |||||
DM | 1230.00 | 2000.00 | 560.00 | 1300.00 | 5090.00 |
DL | 1240.00 | 870.00 | 360.00 | 1260.00 | 3730.00 |
MOH | 2294.00 | 1609.50 | 666.00 | 2331.00 | 6900.50 |
Total Costs added | 4764.00 | 4479.50 | 1586.00 | 4891.00 | 15720.50 |
Total Costs | 6152.00 | 4479.50 | 3609.00 | 7216.00 | 21456.50 |
a) Balance of WIP = 4479.50 i.e. for Job K
b) Balance of FG = 0, since all jobs completed are sold
c) Actual Manufacturing Overhead = 36650+900+440+1500+1208 =
$40698
Overhead applied = 32740+6900.50 = 39640.50
Balance of MOH = 40698-39640.5 = 1057.50 i.e. under applied
overhead
Company Belera is a manufacturing firm producing specialized equipments. June 1, 2018 B/S shows below balances:...
Use below information for Questions 8 to 10: Company X is a manufacturing firm producing specialized equipments. June 1, 2018 B/S shows below balances: Item Beg RM 4,270 MOH Applied 32,740 MOH Incurred 36,650 June 1, 2018 subsidiary ledgers (job cost sheets) show 3 jobs are being performed with following balances[1]: Assigned Costs DM DL MOH R 660 320 403 S 800 543 675 L 930 580 765 During June, RM purchases on account were TL4,970, and all wages (inclusive...
Use below information for Questions 5 to 7: Company X uses a job cost system and applies overhead to production on the basis of direct labor cost. On January 1, 2018, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: DM of TL27,000, DL of TL11,600, and MOH of TL15,003. As of January 1, Job 49 had been completed at a cost of TL85,007 and was part of...
Company X uses a job cost system and applies overhead to production on the basis of direct labor cost. On January 1, 2018, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: DM of TL27,000, DL of TL11,600, and MOH of TL15,008. As of January 1, Job 49 had been completed at a cost of TL85,004 and was part of finished goods inventory. There was a TL13,500 balance...
3. calculate the ending balances of work in process and finished goods as of June 30. A. WIP: B, FG: 4. calculate cost of goods sold for June. 4.5 At the beginning of June, Galway Company had two jobs in process, Job 78 and Job 79, with the following accumulated cost information: Job 79 Direct materials Direct labor Applied overhead Balance, June 1 Job 78 $1,000 600 750 $2,350 $ 800 1,000 1.250 $3,050 During June, two more jobs (80...
I. Journalizing transactions; calculating overhead; adjusting manufacturing overhead; proving ledger account balances a. Follow instructions in numbers 1 & 2. **The job cost sheets are shown below (Last page). For #1 just name each cost sheet and enter beginning balances shown b. For #2, Name the cost sheet c. Journalize numbers 3 and 5 through 12; **Number 4 just requires you to calculate the pre- determined overhead rate 1. At the beginning of the period, May 1, three jobs were...
Exercise #2 $0 Case Inc. is a construction company specializing in custom patios. The patios are constructed of concrete, brick, fiberglass, and lumber, depending upon customer preference. On June 1, 2020, the general ledger for Case Inc. contains the following data: Raw Materials Inventory $4,200 Work in Process Inventory $5,540 Finished Goods Inventory Factory Overhead $990 CR The beginning work in process inventory consists of three jobs: Rodgers $1,320; Stevens $2,015; and Linton $2,205. The following transactions took place during...
COST ACCOUNTING I. Journalizing transactions; calculating overhead; adjusting manufacturing overhead; proving ledger account balances a. Follow instructions in numbers 1 & 2. **The job cost sheets are shown below (Last page). For #1 just name each cost sheet and enter beginning balances shown b. For #2, Name the cost sheet c. Journalize numbers 3 and 5 through 12; **Number 4 just requires you to calculate the pre- determined overhead rate 1. At the beginning of the period, May 1, three...
5 of 7 complete) Score: 0.16 of 1 pt E17-22 (similar to) June production generated the following activity in Barge Chassis Company's Work in Process Inventory count (Click the icon to view the activity) Additionally, Barge has completed Jobs 142 and 143, with total costs of 348,000 and $37.000, respectively Read the requirements Requirement 1. Prepare the journal entry for production completed in June (Prepare a single journal entry for this event. Record debits first, then credits Exclude explanations from...
1:52 s Peralta Inc, has provided the following information for 2018. Prepare the journal entries to record these transactions. a Purchased raw materials on account for $145,000 Issued S115,000 in raw materials to production ($22,000 were not traceable to specific jobs). e Incurred S115,000 in direct labor costs (14,375 hours) and $62,500 in supervision costs (paid in cash) Incurred the following additional manufacturing overhead costs: factory lease $24,000 (paid in cash) depreciation on equipment S20,000; custodial supplies $7,500 (paid in...
Please help. Exam tomorrow, just a review. Blurry #s on info: a.102 b. 96 c. 100 d. 40 e. 27 Everything else seems viisible? Please help me out! Show all work necessary. No excel work please, thank you! system to account for jobs i produces and closes out any Over- or under-applied manufacturing overhead ods Sold at the end of each quarter. Beginning balances from the Balance Sheet on January I are shown in the w. The table uses the...