Answer -
Total cost = $13200 + $33/unit
Calculation:
Total cost of product or Product cost consist both variable and fixed cost. The high-low method is used to determined or identified variable cost and fixed cost from the product cost or mixed cost.
Under high-low method:
Total cost = Fixed cost + Variable cost per unit
So,
As per given information,
High activity cost = $66000
Low activity cost = $49500
Highest activity units = 1600 units
Low activity units = 1100 units
Therefore,
Variable cost per unit and fixed cost can be determine by using high-low method,
Variable cost per unit:
= (High activity cost - Low activity cost) / (Highest activity units - Low activity units)
= ($66000 - $49500) / (1600 units - 1100 units)
= $33 per unit or $33/unit
And
Fixed cost:
= High activity cost - (Variable cost per unit * Highest activity units)
= $66000 - ($33/unit * 1600 units)
= $13200
Now,
The monthly total cost equation,
Total cost = Fixed cost + Variable cost per unit
Total cost = $13200 + $33/unit
Multiple Choice Question 64 Frazier Manufacturing Company collected the following production data for the past month:...
QUES TION 6 Allison Manufacturing Company collected the following production data for the month of November Units Produced 1,600 1,300 1,500 1,100 Total Cost $66,000 57,000 67,500 49,500 If the high-low method is used, what is the monthly total cost equation? Total cost $9,900+$36/unit Total cost $16.500 $30/unit Total cost S0+ $45/unit Total cost $13.200 $33/unit
Wildhorse Corp. has collected the following data concerning its maintenance costs for the past 6 months. Total Cost July August September October November December Units Produced 18,920 33,632 37.836 23,122 42,040 39,938 $40,151 50,448 57,805 41 356 78,299 65.162 Compute the variable cost per unit using the high-low method. (Round answer to 2 decimal places.... 2.25.) Variable cost per unit Compute the fixed cost elements using the high-low method. Fixed costs Click if you would like to Show Work for...
The Welding Department of Healthy Company has the following production and manufacturing cost data for February 2020. All materials are added at the beginning of the process. Manufacturing Costs Beginning work in process Materials $18,400 Conversion costs 14,460 Materials Labor Overhead Production Data Beginning work in process 14,700 units, 1/10 complete Units transferred out 55,300 Units started 50,600 Ending work in process 10,000 units, 1/5 complete $32,860 229,740 67,500 52,695 Prepare a production cost report for the Welding Department for...
Multiple Choice Question 98 The following information is available for Sheridan Company: Sales Cost of goods sold $500000 320000 Total fixed expenses Total variable expenses $150000 260000 A CVP income statement would report contribution margin of $350000. gross profit of $240000. contribution margin of $240000. gross profit of $180000. Click if you would like to Show Work for this question: Open Show Work Multiple Choice Question 142 The following monthly data are available for Waterway Industries which produces only one...
Question 2 The controller of Hall Industries has collected the following monthly expense data for use in analyzing the cost behavior of maintenance costs. Total Maintenance Costs Month January February March April May June $2,643 3,003 3,604 4,505 3,203 4,625 Total Machine Hours 3,504 4,004 6,006 7,908 5,005 8,008 (al) Determine the variable-cost components using the high-low method. (Round variable cost to 2 decimal places e.g. 12.25.) Variable cost per machine hour & Click if you would like to Show...
Question 3 The controller of Sheridan Production has collected the following monthly expense data for analyzing the cost behavior of electricity costs. January February March April 470 May June July August September October November December Total Total Electricity Costs Machine Hours $2,370 210 2,920 390 3,580 4,530 3,210 4,980 4,150 3,850 5,160 665 4,240 3,240 7,770 (a) Determine the fixed- and variable-cost components using the high-low method. Fixed-costs Variable-costs (b) What electricity cost does the cost equation estimate for a...
The Polishing Department of Major Company has the following production and manufacturing cost data for September. Materials are entered at the beginning of the process. Production: Beginning inventory 1,600 units that are 100% complete as to materials and 30% complete as to conversion costs; units started during the period are 45,600; ending inventory of 5,400 units 10% complete as to conversion costs. Manufacturing costs: Beginning inventory costs, comprised of $20,500 of materials and $61,330 of conversion costs; materials costs added...
The controller of Swifty Industries has collected the following
monthly expense data for use in analyzing the cost behavior of
maintenance costs.
Month
Total
Maintenance Costs
Total
Machine Hours
January
$2,550
300
February
2,880
360
March
3,480
510
April
4,380
680
May
3,080
510
June
5,150
700
(a1)
Your answer is correct.
Determine the variable cost components using the high-low method.
(Round variable cost to 2 decimal places e.g.
12.25.)
Variable cost per machine hour
$
Click if you would...
The controller of Hall Industries has collected the following
monthly expense data for use in analyzing the cost behavior of
maintenance costs.
Month
Total
Maintenance Costs
Total
Machine Hours
January
$6,770
6,300
February
7,720
7,200
March
10,680
10,800
April
13,822
14,220
May
9,100
9,000
June
14,060
14,400
(a1)
Your answer is correct.
Determine the variable-cost components using the high-low method.
(Round variable cost to 2 decimal places e.g.
12.25.)
Variable cost per machine hour
$
Click if you would like...
Question The following direct material data pm to the operations of Wright Cn. for the month of December Sted material price $5.00 pound Actual quantity of materials purchased and 16,500 pounds The standard cost card shows that a finished product on pounds of materia The 16.500 pounds were purchased in December at a discount of from the land. In Dec 4,000 fed product were manufactured. Calculate the matenak arance Identify whether the variance fuble or unfavorable Materials per $ Materal...