The following information is available for Department Z for the
month of July:
Units | Cost | |
Work in process, July 1 (70% complete) | 2,000 | |
Direct materials | $ 6,000 | |
Direct labor | 3,000 | |
Manufacturing overhead | 4,000 | |
Total work in process, July 1 | $13,000 | |
Started in July | 20,000 | |
Costs added: | ||
Direct materials | $18,000 | |
Direct labor | 8,000 | |
Manufacturing overhead | 10,000 | |
Total costs added during July | $36,000 | |
Work in process, July 31 (7.5% complete) | 2,000 |
Materials are added at the beginning of the process. Using the FIFO
method, Department Z's cost per equivalent unit of production with
respect to conversion costs would be:
a.$0.96.
b.$1.18.
c.$0.73.
d.$1.02.
Correct answer--------------a.$0.96.
Working
STEP 1 (FIFO) | |||||
Reconciliation of Units | |||||
Units | % already completed | % completed this period | |||
Material | Conversion cost | Material | Conversion cost | ||
Beginning WIP | 2,000 | 100% | 70% | 0% | 30% |
Units introduced | 20,000 | ||||
Total units to be accounted for | 22,000 | ||||
Completed and Transferred unit | 20,000 | 0% | 0% | 100% | 100% |
Ending WIP | 2,000 | 0% | 0% | 100% | 7.5% |
.
STEP 2 (FIFO) | |||||
Equivalent Units | |||||
Total Units | Material | Conversion cost | |||
Units Transferred: | % completed this period | Equivalent Units | % completed this period | Equivalent Units | |
From WIP | 2,000 | 0% | - | 30% | 600 |
From units started/Introduced | 18,000 | 100% | 18,000 | 100% | 18,000 |
Total | 20,000 | 18,000 | 18,600 | ||
Total Units | Material | Conversion cost | |||
Ending WIP | % completed this period | Equivalent Units | % completed this period | Equivalent Units | |
Total | 2,000 | 100% | 2,000 | 7.5% | 150 |
Total EUP | 22,000 | 20,000 | 18,750 |
.
Cost incurred in Current Period | $ 18,000 | |||
Total Equivalent Units | 18,750 | |||
Cost per Equivalent Units | $ 0.96 |
The following information is available for Department Z for the month of July: Units Cost Work...
The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...
The following information is available for Department for the month of July Units Cost 5,000 Work in process, July 1 (60% complete) Direct materials Conversion Total work in process, July 1 $12,000 18.000 $30,000 Started in production during July 20,000 Costs added: Direct materials Conversion Total costs added during July $36,000 52.000 $88.000 Work in process, July 31, (50% complete) 4,000 Materials are added at the beginning of the process. (Round to two decimal places) Department Z's cost of ending...
The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...
The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $ 36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...
6) The following information is available for Department C for the month of August Units Work in process, August 1 (70% complete) 10,000 $36.000 18,000 Direct materials Direct labor Manufacturing overhead Total work in process, August 1 Started in production during August Costs added: 24,000 $78,000 40.000 $108,000 48,000 61.040 Direct materials Direct labor Manufacturing overhead Total costs added during August Work in process, August 31 (80% complete) Units completed and transferred out $217,040 4,000 42,000 Materials are added at...
(E16-6 The Cutting Department of Cassel Company has the following production and cost data for July Determine costs, and (LO 3,4), AF Production 1. Transferred out 12,000 units. 2. Started 3,000 units that are 60% complete as to conversion costs and 100% complete as to materials at July 31. Costs Beginning work in process Materials Labor Manufacturing overhead $ -0- 45,000 16,200 18,300 Materials are entered at the beginning of the process. Conversion costs are incurred uni- formly during the...
Data Table Requirements UNITS 1. Prepare the July production cost report for Casey's Dyeing Department. The company uses the weighted average method. 2. Journalize all transactions affecting Casey's Dyeing Department during July, including the entries that have already been posted. Assume labor costs are accrued and not yet paid. 75 rolls 590 rolls 550 rolls 115 rolls Print Print Done Done Beginning Work-in-Process Inventory Transferred in from Spinning Department during July Completed during July Ending Work-in-Process (80% complete for conversion...
Department A had no Work-in-Process at the beginning of the period, 2,000 units were completed during the period, 300 units were 50% completed at the end of the period, and the following manufacturing costs were debited to the departmental Work-in-Process account during the period: Direct materials (1,300 at $10) $13,000 11,945 9,555 Direct labor Factory overhead added at the beginning of Assuming that all direct materials weighted-average process costing, what is the total cost of the departmental Work-in-Process Inventory at...
Hana Coffee Company Cost of Production Report-Roasting Department For the Month Ended July 31 Unit Information Units charged to production: Inventory in process, July 1 Received from materials storeroom Total units accounted for by the Roasting Department Units to be assigned costs: Whole Units Equivalent Units Direct Materials Conversion Inventory in process, July 1 Started and completed in July Transferred to Packing Department in July Inventory in process, July 31 Total units to be assigned costs Cost Information Cost per...
E16-6 The Cutting Department of Cassel Company has the following production and cost data for July Det cos Production 1. Transferred out 12,000 units. 2. Started 3,000 units that are 60% complete as to conversion costs and 100% complete as to materials at July 31. Costs Beginning work in process Materials Labor Manufacturing overhead $ -0- 45,000 16,200 18,300 Materials are entered at the beginning of the process. Conversion costs are incurred uni- formly during the process Instructions (a) Determine...