Calculation of Ending work in process by Weighted Average method
EQUIVALENT UNITS OF PRODUCTION UNDER WEIGHTED AVERAGE
Direct material % | Conversion costs % | |
Completed units | 20000 *100%=20000 | 20000*100%=20000 |
Ending WIP | 4000*50%=2000 | 4000*50%=2000 |
EUP | 22000 | 22000 |
Weighted average cost per unit
Direct material | Conversion costs | |
Opening WIP | 12000 | 8000 |
Costs added | 36000 | 52000 |
Total costs A | 48000 | 60000 |
EUP B | 22000 | 22000 |
Weighted avg cost per unit A÷B | 2.18 | 2.73 |
ENDING WORK IN PROCESS COST
Direct material | 2000*2.18=4360 |
Conversion costs | 2000*2.73=5460 |
Total ending WIP | 9820 |
The following information is available for Department for the month of July Units Cost 5,000 Work...
The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...
The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...
The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...
The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $ 36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...
6) The following information is available for Department C for the month of August Units Work in process, August 1 (70% complete) 10,000 $36.000 18,000 Direct materials Direct labor Manufacturing overhead Total work in process, August 1 Started in production during August Costs added: 24,000 $78,000 40.000 $108,000 48,000 61.040 Direct materials Direct labor Manufacturing overhead Total costs added during August Work in process, August 31 (80% complete) Units completed and transferred out $217,040 4,000 42,000 Materials are added at...
1. Mannassass Company manufactures chairs. The following information was given for the company: units, beginning work in process 0 units started 20,000 units completed ? units, ending work in process 5,000 cost of direct materials $440,000 cost of conversion $ 64,000 Materials in the ending inventory were 100 percent complete and conversion in the ending inventory was 20 percent complete. What are the equivalent units for materials and conversion respectively? a.20,000; 20,000 b.15,000; 14,000 c.20,000; 16,000 d.15,000; 15,000 e.None of...
24) The following information is available for Department 2 of Lake Corporation during March Units Work in process inventory, March 1 (80% complete as to direct materials, 30% complete as to conversion costs) Transferred in from Dept. 1 in March Completed during March Work in process inventory, March 31 (50%, complete for direct materials, 10%, complete for conversion costs) 42,000 200,000 228,000 14,000 Costs: Work in process inventory, March 1 Direct materials Conversion Transferred-in Transferred in from Dept. 1 in...
The following partially completed process cost summary describes the July production activities of the Molding department at Ashad Company. Its production output is sent to the next department. All direct materials are added to products when processing begins. Beginning work in process inventory is 20% complete with respect to conversion. Equivalent Units of Production Units transferred out Units of ending work in process Equivalent units of production Direct Materials 39,500 EUP 4,000 EUP 43,500 EUP Conversion com 39,500 EUP 2,400...
Required: Prepare a production cost worksheet, using Weighted
Average for the finishing department. Please show work.
13) Lexington Company produces baseball bats and cricket paddles. It has two departments that process all products. During July, the beginning work in process in the cutting department was half completed as to conversion, and complete as to direct materials. The beginning inventory included $40,000 for materials and $60,000 for conversion costs. Ending work-in-process inventory in the cutting department was 40% complete. Direct materials...
Question 37 (Mandatory) (2.5 points) Department G had 3,600 units, 40% completed at the beginning of the period, 12,000 units were completed during the period, 2,000 units were one-fifth completed at the end of the period, and the following manufacturing costs were debited to the departmental work in process account during the period: $60,000 Work in process, beginning of period Costs added during period: Direct materials (10,400 at $9.8365) Direct labor Factory overhead 102,300 79,800 25,200 Assuming that all direct...