Question

The following information is available for Department C for the month of August: Units Cost Work...

The following information is available for Department C for the month of August:

Units Cost
Work in process, August 1 (70% complete) 10,000
Direct materials $36,000
Direct labor 18,000
Manufacturing overhead 24,000
Total work in process, August 1 $78,000
Started in production during August 40,000
Costs added:
Direct materials $108,000
Direct labor 48,000
Manufacturing overhead     61,040
Total costs added during August $217,040
Work in process, August 31 (80% complete) 4,000
Units completed and transferred out 42,000


Materials are added at the beginning of the process. Inspection takes place at the 50 percent point in the conversion process to determine spoiled units. Round unit costs to two decimal places. The company uses the weighted average cost flow assumption.

Department C's cost per unit for materials using the weighted average method is

a.$3.60.

b.$2.88.

c.$3.43.

d.$2.16.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Equivalent unit of material = 10000+40000 = 50000 Unit

Cost per equivalent unit of material = (36000+108000)/50000 = 2.88

So answer is b) $2.88

Add a comment
Know the answer?
Add Answer to:
The following information is available for Department C for the month of August: Units Cost Work...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 6) The following information is available for Department C for the month of August Units Work...

    6) The following information is available for Department C for the month of August Units Work in process, August 1 (70% complete) 10,000 $36.000 18,000 Direct materials Direct labor Manufacturing overhead Total work in process, August 1 Started in production during August Costs added: 24,000 $78,000 40.000 $108,000 48,000 61.040 Direct materials Direct labor Manufacturing overhead Total costs added during August Work in process, August 31 (80% complete) Units completed and transferred out $217,040 4,000 42,000 Materials are added at...

  • The following information is available for Department C for the month of August: Units Cost Work...

    The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $ 36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...

  • The following information is available for Department Z for the month of July: Units Cost Work...

    The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...

  • The following information is available for Department Z for the month of July: Units Cost Work...

    The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...

  • The following information is available for Department for the month of July Units Cost 5,000 Work...

    The following information is available for Department for the month of July Units Cost 5,000 Work in process, July 1 (60% complete) Direct materials Conversion Total work in process, July 1 $12,000 18.000 $30,000 Started in production during July 20,000 Costs added: Direct materials Conversion Total costs added during July $36,000 52.000 $88.000 Work in process, July 31, (50% complete) 4,000 Materials are added at the beginning of the process. (Round to two decimal places) Department Z's cost of ending...

  • Badgersize Company has the following information for its Forming Department for the month of August. Work in Process In...

    Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials 80,000 24,000 104,000 54,000 58,000 ? 157,000 Conversion costs: Direct labor 112,000 Overhead applied 147,000 259,000...

  • Badgersize Company has the following information for its Forming Department for the month of August. $...

    Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 104,000 53,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied Total conversion $ 136,000...

  • Badgersize Company has the following information for its Forming Department for the month of August. Work...

    Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,900 units Direct materials: 100% complete s 80,eee 24,e00 $104,00e 55,e00 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied $138,000 $117,e00 147,000 $264,006e...

  • 1. Mannassass Company manufactures chairs. The following information was given for the company: units, beginning work...

    1. Mannassass Company manufactures chairs. The following information was given for the company: units, beginning work in process 0 units started 20,000 units completed ? units, ending work in process 5,000 cost of direct materials $440,000 cost of conversion $ 64,000 Materials in the ending inventory were 100 percent complete and conversion in the ending inventory was 20 percent complete. What are the equivalent units for materials and conversion respectively? a.20,000; 20,000 b.15,000; 14,000 c.20,000; 16,000 d.15,000; 15,000 e.None of...

  • 24) The following information is available for Department 2 of Lake Corporation during March Units Work in process...

    24) The following information is available for Department 2 of Lake Corporation during March Units Work in process inventory, March 1 (80% complete as to direct materials, 30% complete as to conversion costs) Transferred in from Dept. 1 in March Completed during March Work in process inventory, March 31 (50%, complete for direct materials, 10%, complete for conversion costs) 42,000 200,000 228,000 14,000 Costs: Work in process inventory, March 1 Direct materials Conversion Transferred-in Transferred in from Dept. 1 in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT