Question

6) The following information is available for Department C for the month of August Units Work in process, August 1 (70% compl
Materials are added at the beginning of the process. Inspection takes place at the 50 percent point in the conversion process
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1. Calculate equivalent units for materials
Weighted Average Method
UNITS Equivalent Units
Physical Units % complete Materials
Units to be accounted for:
Work in process, beginning 10000
Started into production   40000
Total units 50000
Units accounted for:
Good units Completed and Transferred out   42000 100% 42000
Abnormal Spoilage (50000-42000-4000) 4000 100% 4000
Work in process, Ending 4000 100% 4000
  Total Units accounted for 50000 50000
2.. costs per equivalent unit.
COSTS Costs
Direct Materials
Unit Costs
Work in process, beginning $             36,000
Costs added during Aug $          108,000
Total Cost to be accounted for $          144,000
÷  
Equivalent units 50000
Cost per equivalent unit $2.88
$2.88 is answer.

Feel free to ask any clarification, if required. Kindly provide feedback by thumbs up, if satisfied. It will be highly appreciated.
Thank you.

Add a comment
Know the answer?
Add Answer to:
6) The following information is available for Department C for the month of August Units Work...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following information is available for Department C for the month of August: Units Cost Work...

    The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead     61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...

  • The following information is available for Department C for the month of August: Units Cost Work...

    The following information is available for Department C for the month of August: Units Cost Work in process, August 1 (70% complete) 10,000 Direct materials $ 36,000 Direct labor 18,000 Manufacturing overhead 24,000 Total work in process, August 1 $78,000 Started in production during August 40,000 Costs added: Direct materials $108,000 Direct labor 48,000 Manufacturing overhead 61,040 Total costs added during August $217,040 Work in process, August 31 (80% complete) 4,000 Units completed and transferred out 42,000 Materials are added...

  • The following information is available for Department Z for the month of July: Units Cost Work...

    The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...

  • The following information is available for Department Z for the month of July: Units Cost Work...

    The following information is available for Department Z for the month of July: Units Cost Work in process, July 1 (70% complete) 2,000 Direct materials $ 6,000 Direct labor 3,000 Manufacturing overhead 4,000 Total work in process, July 1 $13,000 Started in July 20,000 Costs added: Direct materials $18,000 Direct labor 8,000 Manufacturing overhead 10,000 Total costs added during July $36,000 Work in process, July 31 (7.5% complete) 2,000 Materials are added at the beginning of the process. Using the...

  • The following information is available for Department for the month of July Units Cost 5,000 Work...

    The following information is available for Department for the month of July Units Cost 5,000 Work in process, July 1 (60% complete) Direct materials Conversion Total work in process, July 1 $12,000 18.000 $30,000 Started in production during July 20,000 Costs added: Direct materials Conversion Total costs added during July $36,000 52.000 $88.000 Work in process, July 31, (50% complete) 4,000 Materials are added at the beginning of the process. (Round to two decimal places) Department Z's cost of ending...

  • Badgersize Company has the following information for its Forming Department for the month of August. Work in Process In...

    Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials 80,000 24,000 104,000 54,000 58,000 ? 157,000 Conversion costs: Direct labor 112,000 Overhead applied 147,000 259,000...

  • Badgersize Company has the following information for its Forming Department for the month of August. $...

    Badgersize Company has the following information for its Forming Department for the month of August. $ 80,000 24,000 104,000 53,000 58,000 Work in Process Inventory, August 1: 20,000 units Direct materials: 100% complete Conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied Total conversion $ 136,000...

  • Badgersize Company has the following information for its Forming Department for the month of August. Work...

    Badgersize Company has the following information for its Forming Department for the month of August. Work in Process Inventory, August 1: 20,900 units Direct materials: 100% complete s 80,eee 24,e00 $104,00e 55,e00 56,000 conversion: 20% complete Balance in work in process, August 1 Units started during August Units completed and transferred in August Work in process (70% complete), August 31 Costs charged to Work in Process in August Direct materials Conversion costs: Direct labor Overhead applied $138,000 $117,e00 147,000 $264,006e...

  • 24) The following information is available for Department 2 of Lake Corporation during March Units Work in process...

    24) The following information is available for Department 2 of Lake Corporation during March Units Work in process inventory, March 1 (80% complete as to direct materials, 30% complete as to conversion costs) Transferred in from Dept. 1 in March Completed during March Work in process inventory, March 31 (50%, complete for direct materials, 10%, complete for conversion costs) 42,000 200,000 228,000 14,000 Costs: Work in process inventory, March 1 Direct materials Conversion Transferred-in Transferred in from Dept. 1 in...

  • Calculate Equivalent Units, Unit Costs, and Transferred Costs - Weighted Average Method Monroe Company processes a...

    Calculate Equivalent Units, Unit Costs, and Transferred Costs - Weighted Average Method Monroe Company processes a food seasoning powder through its Compounding and Packaging departments. In yhe Compounding Department, direct materials are added at the beginning of the process, and direct labor and manufacturing overhead are incurred evenly throughout the process. Monroe uses the weighted average method. Costs in the Compounding Department can be summarized as follows: At August 31, 2019, 3,00 units were in process, 30% complete with respect...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT