Question

Question 3 5 pts With a 85% learning curve, if item 25 took 48 minutes to produce, how long would item 50 take to produce (in
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Here a 85% learning curve means that the learning rate is 85%.The production has been doubled just once i.e.from 25 to 50.Also,we know that the time taken for the item 25 is 48.

So the required time taken for item 50 =85% of 48=0.85×48=40.80 minutes.

Hence only the 'second option' is correct which has been shown using the calculation.

A 85% learning curve means that the cumulative average time and cost of production would decrease by 15%,each time the production is doubled.Here the production is doubled once.And 15% of 48 is 7.2.So the cumulative average time would decrease by 7.2 minutes and hence next item would take 48-7.2=40.80 minutes.

A learning curve graphically shows the improvement in efficiency of production as more is produced.As per the learning theory,the cost or time taken to produce reduces with the increase in production.A producer learns from the previous production experiences and patterns.The magnitude of improvement in efficiency is determined by the learning rate.

Add a comment
Know the answer?
Add Answer to:
Question 3 5 pts With a 85% learning curve, if item 25 took 48 minutes to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CHAPTER 6: LEARNING CURVE (MONDAY) 1. The unit improvement factor for a 60 percent learning curve at 25 units...

    CHAPTER 6: LEARNING CURVE (MONDAY) 1. The unit improvement factor for a 60 percent learning curve at 25 units is 0.0933. The first and second timings of a person doing a job are 5 minutes and 3 minutes respectively. What is the learning-adjusted time estimate for unit number 25? 2. You have just timed a person doing a job a few times. The first time it took the person 25 minutes, the second time it took 20 minutes, and the...

  • Question 3 2 pts The first unit of a product took 80 days for production. The...

    Question 3 2 pts The first unit of a product took 80 days for production. The learning rate for the production process is 85%. How long will it take to make the units 10th through 13th? (Use Table E.3 in Module E (Learning Curves) of the textbook.) from 115 to 135 days from 175 to 195 days from 135 to 155 days from 155 to 175 days from 195 to 215 days

  • (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate...

    (1) Let us suppose it costs $70 to produce the 80th unit, assuming a learning rate of 95%, determine the cost of the 160th unit. (2) If the 4th unit took 24 hours to produce, and the 20th unit took 19 hours to produce, what would the learning rate be? Note: Express your answer in decimal places, i.e., if your answer is 40.56%, enter in 0.4056. (3) Let us suppose it costs $500 to produce the 120th unit, assuming a...

  • Question4 1 pts A furniture maker has an order for 85 identical tables. If the furniture...

    Question4 1 pts A furniture maker has an order for 85 identical tables. If the furniture maker estimates his learning curve at 92% and can reach steady production of 5 hours per table on the 6th table, how long should it take to make all the tables? Express your answer in hours to the nearest whole hour

  • This Question: 4 pts 5 of 5 (0 complete) This Quiz: 25 pts possible The data...

    This Question: 4 pts 5 of 5 (0 complete) This Quiz: 25 pts possible The data below are the average one-way commute times (in minutes) for selected students and the number of absences for those students during the term. Find the equation of the regression line for the given data. What would be the predicted number of absences if the commute time was 40 minutes? Is this a reasonable question? Round the predicted number of absences to the nearest whole...

  • pt took 3 minutes. Question 1 0/1 pts According the the Arrhenius equation, how you can...

    pt took 3 minutes. Question 1 0/1 pts According the the Arrhenius equation, how you can increase the reaction rate? In other words, how can you make k (the rate constant) larger, which leads to a faster reaction? increase the temperature increase the fraction of collisions that result in a successful reaction (the frequency actor

  • 6:21pm mitted Jan 17 at s attempt took 3 minutes ncret Question 1 /2 pts The...

    6:21pm mitted Jan 17 at s attempt took 3 minutes ncret Question 1 /2 pts The citation of a case does not include: The names of the parties The names) of the judge(s) who decided the case The year in which it was decided The volume and page number of the applicable reporter where the opinion may be found The names of the parties

  • mitted Jan 17 at 6:21pm s attempt took 3 minutes Incorect Question 1 /2 pts The...

    mitted Jan 17 at 6:21pm s attempt took 3 minutes Incorect Question 1 /2 pts The citation of a case does not include: The names of the parties The names) of the judge(s) who decided the case The year in which it was decided The volume and page number of the applicable reporter where the opinion may be found The names of the parties

  • Question 3 5p A spark is generated in an automobile spark plug when there is an...

    Question 3 5p A spark is generated in an automobile spark plug when there is an electric potential of 3000 V across the electrode gap. If 60 W of power is generated in a single spark that delivers a total charge of 3 nC, how long does it take for the spark to travel across the gap? 50 ns 75 ns 125 ns 150 ns 225 ns 5 pts > Question 4 aco nattern is

  • It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for...

    It took MegaTech, Inc. 200,000 labor-hours to produce the first of several oil drilling rigs for Antarctic exploration. Your company, Natural Resources, Inc. has agreed to purchase the fifth oil drilling rig from their manufacturing yard. Assume that MegaTech experiences a learning rate of 75%. At a labor rate of $38 per hour, what should you, as the purchasing agent expect to pay for the fifth unit? TN = T1C, Where TN = Time needed to produce the Nth unit...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT