Cost of the plant in Vancouver is not given. If needed for the calculations, the information...
A 50-mgpd (million gallons per day) water treatment plant was proposed in 2017 for Ureka. A 60- mgpd plant using the same treatment process was built in 2010 in Vancouver for $50,000,000. Given the following additional information and assumptions: Poor site condition in Vancouver required an additional $3,000,000 for foundations, which is not anticipated for Ureka. Assume the power sizing size exponent = 0.67. Assume inflation will persist at an average 5% per annum. Assume the location index for Vancouver...
1/ Using the information presented in Question 1 above,
determine the Historical Cost of the building after taking
into consideration the capitalization of interest.
2/ Using the information presented in Question 1 above,
determine the Interest Expense that Desert would report on
their Income Statement for the year ended December 31,
2019.
3/ Using the information in Question 1 above, assume
instead that Desert's only other outstanding debt during
2019 was a $450,000, 9%, three-year note (i.e. all other
information...
Part a Donahue Ltd purchased a plant on 1 July 2018 for N$300 000. The entity incurred transfer fees of N$90 000. The expected dismantling cost at the end of the useful life of the plant is N$200 000. The applicable discount rate after tax (tax rate 25.75%) 6.3% Useful life 12 years The plant is erected on rented premises and the rental agreement requires dismantling of the plant at the end of its useful life. Assume that Inland Revenue...
Given all the information in the table, use PERT/CPM to help Mr.
Hawthorne address to the following questions.
A. Create the network diagram representing the problem.
B. What is the total time expected to be required to complete
the project if no delays occur?
C. What are the earliest and latest start and finish times for
the individual activities required to meet the expected project
completion time provided in question B (show your method for
determining this)?
D. Which are...
MULTIPLE-CHOICE questions E1-1.ABC Engineering use cost method to cart engineering use cost method to calculate the stage of completion of its construction act. Total estimated contract costs of their contract are $100 million. In the first year of their contract, ABC Engineering has incurred the following costs: Cost of purchase of raw materials worth $10 million ($5 million of which are unused by the year end) 2. Payment of salaries and wages of $5 million ($1 million of accrued salaries...
How can we assess whether a project is a success or a
failure?
This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...