Question

A 50-mgpd (million gallons per day) water treatment plant was proposed in 2017 for Ureka. A...

A 50-mgpd (million gallons per day) water treatment plant was proposed in 2017 for Ureka. A 60- mgpd plant using the same treatment process was built in 2010 in Vancouver for $50,000,000. Given the following additional information and assumptions:

  • Poor site condition in Vancouver required an additional $3,000,000 for foundations, which is not anticipated for Ureka.

  • Assume the power sizing size exponent = 0.67.

  • Assume inflation will persist at an average 5% per annum.

  • Assume the location index for Vancouver is 1.17 and 1.20 for Ureka.

  • A new high-pressure filter process will be added at Ureka at an additional cost of $4,000,000.

  • The construction period for the new plant will include winter construction. The Vancouver plant was not constructed through a winter season. Assume an increase in construction costs for Ureka of 15%.

To make an order of magnitude estimate of the water treatment plant in Ureka, various multiplication factors need to be calculated.

(a) Calculate the multiplication factor based on the different capacities.

(b) Calculate the multiplication factor based on the different location indexes.

(c) Calculate the order of magnitude estimate of the water treatment plant in Ureka.

(d) Calculate the multiplication factor based on effect of inflation.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Multiplication factor based on different capacities 6 multiplication location different - 0.885 factor based on Indexes = 1.Adding filter cost = 56,856, 103.7 +40000.co = $60,856, 103.7. winter construction cost = 15% of 60,656, 163 = 9,128, 415.56.

Add a comment
Know the answer?
Add Answer to:
A 50-mgpd (million gallons per day) water treatment plant was proposed in 2017 for Ureka. A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cost of the plant in Vancouver is not given. If needed for the calculations, the information...

    Cost of the plant in Vancouver is not given. If needed for the calculations, the information will assist in calculating it. 3- A 50-mgpd (US) water treatment plant is proposed in 2020 for Washington. A 60-mgpd plant using the same treatment process was built in 2013 in Vancouver. Make a conceptual cost estimate based on the following information: - Poor site condition in Vancouver required an additional $3,000,000 for foundation which is not anticipated for Washington. - Assume the size...

  • A water treatment plant will deliver 15.0 million gallons per day 8 PUR(mgd). If the daily...

    A water treatment plant will deliver 15.0 million gallons per day 8 PUR(mgd). If the daily peaking factor is 1.5, how many customers carn it serve with an annual average of 150 gped? A 36-inch pipe carries 25 cfs of water for 20 miles. At the starting point, the chlorine concentration is C,4mgl. Compute the 19 Qexpected concentration at the 20-mile point. The time variable is in days and the rate coefficient is k-1.5 day-1. The decay equation is: C-Ce

  • A water treatment plant operator treats 5 million gallons per day (MGD) of a raw surface...

    A water treatment plant operator treats 5 million gallons per day (MGD) of a raw surface water with 25 mg/L of Aluminum Sulfate (Al2(SO4)3•16H2O) to remove suspended solids in the water. The untreated water contains 20mg/L total suspended solids (TSS). Assuming that the alum removes all but 2 mg/L TSS, determine the weight of sludge which must be removed each day. Assume: - All of the added aluminum sulfate is converted to its solid hydroxide form (Al(OH)3) and captured in...

  • Example 8: A 10 MGD (million gallons per day) surface water treatment plant proposes to use...

    Example 8: A 10 MGD (million gallons per day) surface water treatment plant proposes to use alum coagulation for turbidity reduction using 45 mg/L alum! dosage. The raw water has an alkalinity of 20 mg/L as CaCo,. Commercial alum has the formula Al(SO2)2.144,0 (MW = 594). Determine the daily alum dosage required in kg/d. Z.6 -> EW - 99

  • summarizr the followung info and write them in your own words and break them into different...

    summarizr the followung info and write them in your own words and break them into different key points.   6.5 Metering Chamber: 6.5.1 The minimum size of the metering box is governed by the metering area required to obtain a representative test area for the specimen (see 7.2) and for maintenance of reasonable test accuracy. For example, for specimens incorporating air spaces or stud spaces, the metering area shall span an integral number of spaces (see 5.5). The depth of...

  • summatize the following info and break them into differeng key points. write them in yojr own...

    summatize the following info and break them into differeng key points. write them in yojr own words   apartus 6.1 Introduction—The design of a successful hot box appa- ratus is influenced by many factors. Before beginning the design of an apparatus meeting this standard, the designer shall review the discussion on the limitations and accuracy, Section 13, discussions of the energy flows in a hot box, Annex A2, the metering box wall loss flow, Annex A3, and flanking loss, Annex...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT