Answer
b.use the S-2 employee
Calculation:
S-1 | S-2 | S-3 | |
Time for 1 unit (in minutes)(A) | 30 | 24 | 21 |
Units in 1 hour (60/A = B) | 2 | 2.5 | 2.857142857 |
Wages per hour (C | $ 16.00 | $ 19.00 | $ 22.00 |
Wages per unit (C/B) | $ 8.00 | $ 7.60 | $ 7.70 |
Rank | III | I | II |
In case of any doubt, please comment.
WeeBee Company has three assembly labor dassifications: 5-1, S-2, and S-3. The three dassifications are paid...
Analyze Skidmore Electronics Skidmore Electronics manufactures consumer electronic products. The company has three assembly labor classifications, S-1, S-2, and S-3. The three classifications are paid $15, $18, and $22 per hour, respectively. The assembly activity for a new smartphone is as follows: Analyze Skidmore Electronics Skidmore Electronics manufactures consumer electronic products. The company has three assembly labor classifications, S-1, S-2, and S-3. The three classifications are paid $15, $18, and $22 per hour, respectively. The assembly activity for a new...
An assembly line has three operations in sequence. The work-centers take 5, 3, and 2 minutes per job. (So job 1 enters the first work-center, where it takes 5 minutes; then it is moved to the second work center where it takes 3 minutes while job 2 enters the first work-center, etc.) In the above line, if the second work-center operation time is reduced by ten percent, what is the throughput of this line (as number of jobs completed per hour...
2 how implementing them will lead to improvements in the product assembly process. Present four rules that could be used to design a product for assembly and explain [8 marks] Table Q2 itemises the precedence and timing information that is required to complete the assembly of a product. For an assembly rate of 60 per hour, determine the minimum number of stations required and through the application of the Largest Candidate heuristic, devise an assembly task grouping. Comment on the...
Question 2 Explain four rules that could be used to design a product for assembly and discuss how they will provide benefit, use sketches to illustrate your answer.. [8 marks] Table Q2 itemises the precedence and timing information that is required to complete the assembly of a product. Through the application of a Largest Candidate Rule procedure, devise an assembly task grouping to achieve an assembly rate of 30 per hour. What is the utilisation for each assembly station [8...
COVID 19 Co has an activity-based costing system with three activity cost pools--Machining, Assembly, and Other. In the first stage allocations, costs in the two overhead accounts, equipment depreciation and facotry expense, are allocated to three activity cost pools based on resource consumption. Data used in the first stage allocations follow: Overhead costs: $79,600 Equipment depreciation $5,000 Factory expense Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Machining Assembly Other 0.20 0.20 Equipment depreciation 0.50 0.30 Factory...
COVID 19 Co has an activity-based costing system with three activity cost pools--Machining, Assembly, and Other. In the first stage allocations, costs in the two overhead accounts, equipment depreciation and facotry expense, are allocated to three activity cost pools based on resource consumption. Data used in the first stage allocations follow: Overhead costs: $79,600 Equipment depreciation $5,000 Factory expense Distribution of Resource Consumption Across Activity Cost Pools: Activity Cost Pools Machining Assembly Other 0.20 0.20 Equipment depreciation 0.50 0.30 Factory...
1.Abbe Company uses activity-based costing. The company has two products: A and B. The annual production and sales of Product A is 1,600 units and of Product B is 950 units. There are three activity cost pools, with estimated costs and expected activity as follows: Activity Cost Pools Estimated Overhead Cost Expected Activity Product A Product B Total Activity 1 $ 38,241 1,100 1,000 2,100 Activity 2 $ 58,551 2,100 800 2,900 Activity 3 $ 72,702 640 620 1,260 The...
1.An assembly line with 28 activities is to be balanced. The total amount of time required for all 28 activities is 39 minutes. The longest activity is 2.2 minutes and the shortest is 0.8 minutes. The line will operate for 450 minutes per day. What is the assembly line efficiency with 11 stations and a product produced every 5 minutes? 2.An assembly line consists of 3 tasks with individual times 5, 3, and 2 minutes and the cycle time of...
Case Studies Jackson Manufacturing Company Kathleen McFadden, vice president of operations at Jackson Manufacturing Company, has just received a request for quote (RFQ) from DeKalb Electric Supply for 400 units per week of a motor armature. The components are standard and either easy to work into the existing production schedule or readily available from established suppliers on a JIT basis. But there is some difference in assembly. Ms. McFadden has identified eight tasks that Jackson must perform to assemble the...
1) 2) 3) 4) 5) The debits to Work in Process-Assembly Department for April, together with data concerning production, are as follows: April 1, work in process: $8,900 5,500 27,500 32,000 Materials cost, 3,000 units Conversion costs, 3,000 units, 80% completed Materials added during April, 10,000 units Conversion costs during April Goods finished during April, 11,500 units April 30 work in process, 1,500 units, 60% completed 0 All direct materials are placed in process at the beginning of the process...