Question

A project has five activities. From the project plan, you know that the total budgeted cost for the activities are: Activity
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Earned value is calculated as

EV = \sum P_{i}*B_{i}

where Pi is progress for i activity and Bi is budget for i activity and i=A, B, C, D, E

Hence, EV = 80%*73,000 + 100%*93,000 + 70%*81,000 + 20%*120,000 + 0%*72,000

= 58,400 + 93,000 + 56,700 + 24,000 + 0 = $232,100

Hence, at the end of week 8, the project cumulative earned value is $232,100

Add a comment
Know the answer?
Add Answer to:
A project has five activities. From the project plan, you know that the total budgeted cost...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has 61 activities. At the end of period 4, it has been reported that...

    A project has 61 activities. At the end of period 4, it has been reported that activity A is 93% completed, activity B is 81% completed, activity C is 36% completed, and activity Dis 23% completed. The budgeted costs for these activities are shown in the following table. Activity А B С Total Budgeted Cost($) 33211 21628 39909 44531 According to the project plan, the cumulative budgeted cost at the end of period 4 is $131534 and the total project...

  • A project has 98 activities. At the end of period 4, it has been reported that...

    A project has 98 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...

  • A project has 101 activities. At the end of period 4, it has been reported that...

    A project has 101 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...

  • A project has 114 activities. At the end of period 4, it has been reported that...

    A project has 114 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с Total Budgeted Cost($) 20 15 100 D 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...

  • A project has 69 activities. At the end of period 4, it has been reported that...

    A project has 69 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity Dis 80% completed. The budgeted costs for these activities are shown in the following table. Activity B Total Budgeted Cost(5) 20 15 100 35 С D According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the total project...

  • A project has 117 activities. At the end of period 4, it has been reported that...

    A project has 117 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B С D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...

  • The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week)...

    The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week) A T 3 none 40,000 в з А 22,000 C2A 17,000 D 3 B 27,000 E5C 16,000 The above table shows that the budgeted cost of activity E is $16,000 per week. NOTE: Do not use any comma in your answer. The cumulative budgeted cost at the end of week 4 is dollars The cumulative Juugeleu cost at the NOTE: Do not use any...

  • A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 9...

    A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 95% completed, activity C is 100% completed, and activity D is 40% completed The budgeted costs for these activities are shown below Activity Total Budgeted Cost ($) 30,000 80,000 60,000 70,000 According to the project plan, the cumulative budgeted cost at the end of period 11 is $268,000 and the total project budgeted cost is $2,500,000. The cumulative actual cost at...

  • Question #2. (20 marks) The following table shows activities related to a small project and their...

    Question #2. (20 marks) The following table shows activities related to a small project and their weekly usage of labors. Smooth (level) the resource usage so that a preferred resource usage is obtained. Activity IPA Duration week) Labor/week start start start Selo F G H Question #3. (15marks) For the project information of question2 above, and referring to the field report below, perform a revised schedule, then comment on it. At the end of week 5 the following field information...

  • QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an...

    QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT