A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 9...
A project has 69 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity Dis 80% completed. The budgeted costs for these activities are shown in the following table. Activity B Total Budgeted Cost(5) 20 15 100 35 С D According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the total project...
A project has 61 activities. At the end of period 4, it has been reported that activity A is 93% completed, activity B is 81% completed, activity C is 36% completed, and activity Dis 23% completed. The budgeted costs for these activities are shown in the following table. Activity А B С Total Budgeted Cost($) 33211 21628 39909 44531 According to the project plan, the cumulative budgeted cost at the end of period 4 is $131534 and the total project...
A project has 101 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 98 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 114 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с Total Budgeted Cost($) 20 15 100 D 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 117 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B С D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has five activities. From the project plan, you know that the total budgeted cost for the activities are: Activity A, $73,000 activity B, $93,000 activity C, $81,000 activity D, $120,000 activity E, $72,000 The project has been going on for 8 weeks. The progress report at the end of week 8 shows the following information Activity A is 80% completed, activity B is 100% completed activity C is 70% completed activity D is 20% completed, and activity E...
The information about a project is shown below. Duration Immediate Budgeted Cost Activity (weeks) Predecessor(s) ($/week) A T 3 none 40,000 в з А 22,000 C2A 17,000 D 3 B 27,000 E5C 16,000 The above table shows that the budgeted cost of activity E is $16,000 per week. NOTE: Do not use any comma in your answer. The cumulative budgeted cost at the end of week 4 is dollars The cumulative Juugeleu cost at the NOTE: Do not use any...
Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...
2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were expecting to be only58 % through the third activity at this time. The first activity involves prepping the site for the bridge....