BCWP=$110
BCWS=$320
Schedule perfromance index= BCSP/BCWS
Schedule perfromance index= 110/320=0.34
Schedule perfromance index=0.34
A project has 69 activities. At the end of period 4, it has been reported that...
A project has 101 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 61 activities. At the end of period 4, it has been reported that activity A is 93% completed, activity B is 81% completed, activity C is 36% completed, and activity Dis 23% completed. The budgeted costs for these activities are shown in the following table. Activity А B С Total Budgeted Cost($) 33211 21628 39909 44531 According to the project plan, the cumulative budgeted cost at the end of period 4 is $131534 and the total project...
A project has 98 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B с D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 114 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity A B с Total Budgeted Cost($) 20 15 100 D 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 117 activities. At the end of period 4, it has been reported that activity A is 100% completed, activity B is 100% completed, activity C is 50% completed, and activity D is 80% completed. The budgeted costs for these activities are shown in the following table. Activity А B С D Total Budgeted Cost($) 20 15 100 35 According to the project plan, the cumulative budgeted cost at the end of period 4 is $110 and the...
A project has 80 activities. At the end of penod 11, activity A is 70% completed. activity B is 95% completed, activity C is 100% completed, and activity D is 40% completed The budgeted costs for these activities are shown below Activity Total Budgeted Cost ($) 30,000 80,000 60,000 70,000 According to the project plan, the cumulative budgeted cost at the end of period 11 is $268,000 and the total project budgeted cost is $2,500,000. The cumulative actual cost at...
A project has five activities. From the project plan, you know that the total budgeted cost for the activities are: Activity A, $73,000 activity B, $93,000 activity C, $81,000 activity D, $120,000 activity E, $72,000 The project has been going on for 8 weeks. The progress report at the end of week 8 shows the following information Activity A is 80% completed, activity B is 100% completed activity C is 70% completed activity D is 20% completed, and activity E...
3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...
Problem 5-6 A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 57% through the third activity at this time. The first activity involves prepping the site for the bridge. It was...
2 Problem 5-6 (Algo) A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 65% complete. The planners were expecting to be only58 % through the third activity at this time. The first activity involves prepping the site for the bridge....