Question


C & A Furniture uses a four-step process to make its famous wood table: Process - Processing Time (minutes) Milling-table top

C & A Furniture uses a four-step process to make its famous wood table: 

Process - Processing Time (minutes) 

Milling-table top-10 minutes 

Milling-table stand - 5 minutes 

Assembly - 15 minutes 

Finishing - 20 minutes 


The milling machine requires a setup time of 30 minutes to make table tops and a changeover time of 30 minutes to make table stands.C\&A works an 8 -hour day: What is the capacity of the milling machine (in tables per day) if the batch size is 10?

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Option D is the capacity of the Milling machine.

D. 6.40

6.40 Tables can be produced with the milling machine in a day of 8 hours shift.

Add a comment
Know the answer?
Add Answer to:
What is the capacity of the milling machine (in tables per day) if the batch size is 10?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT