A community council must decide which recreation facilities to construct in its community. Four new recreation facilities have been proposed a swimming pool, a tennis center, an athletic field, and a gymnasium. The council wants to construct facilities that will maximize the expected daily usage by the residents of the community subject to land and cost limitations. The expected daily usage and cost and land requirements for each facility follow.
Recreation Facility |
Expected Usage (people per day) |
Cost ($) |
Land Requirement (Acres) |
Swimming pool |
300 |
35,000 |
4 |
Tennis center |
90 |
10,000 |
2 |
Athletic field |
400 |
25,000 |
7 |
Gymnasium |
150 |
90,000 |
3 |
The community has a $120,000 construction budget and 12 acres of land. Because the swimming pool and tennis center must be built on the same part of the land parcel, only one of these two facilities can be constructed. The council wants to know which of the recreation facilities to construct to maximize the expected daily usage.
Let S, T, A and G be binary decision variables which can take the value of either 1 or 0 for swimming pool, tennis center, athletic field, gymnasium. If the value is 1, that means the facility is constructed and if it is 0, then the facility is not constructed.
We need to maximize the daily usage which is the objective function. Hence the objective function Z is as below
Z = 300S+90T+400A+150G
Now we will model for constraints
As the total budget is 120000, we have the below constraint
35000S+10000T+25000A+90000G 120000
Also as total area is 12 acres, we have the below constraint
4S+2T+7A+3G 12
Also because the swimming pool and tennis center must be built on the same part of the land parcel and only one of these two facilities can be constructed we have the below constraints
S+T 1
This the complete Integer programming model is as below
Maximize Z = 300S+90T+400A+150G
subject to constraints
35000S+10000T+25000A+90000G 120000
4S+2T+7A+3G 12
S+T 1
The problem is formulated in excel as below. The below 2 images show the formulation as well as the formulas used
Post these the solver parameters need to be entered as per the below image.
Once this is done, click on solve. The solver will solve the problem and show the message stating the same. Click on ok. The excel will now have the final solution as per below image.
Thus we can see that S=1 and A=1. Hence the solution is to construct Swimming Pool and Athletic Field.
A community council must decide which recreation facilities to construct in its community. Four new recreation...
The council wants to construct facilities that will maximize the expected daily usage by the residents of the community. Formulate this problem Resource constraints: $120,000 budget; 12 acres of land. Selection constraint: either swimming pool or tennis center can be constructed (not both). Expected Usage (people/day) Land Requirement (acres) Cost ($) 4 Recreation Facility Swimming pool Tennis Center Athletic field Gymnasium 300 90 400 150 35,000 10,000 25,000 90,000 2 7 3
A small town wants to build several new recreational facilities. The proposed facilities include an outdoor swimming pool, a fitness center, two basketball courts, a baseball field, a beach volleyball court, and a soccer field. The town council wants to provide the facilities which will be used by the most people, but faces budget and flat land limitations. The town has $470,000 and 10 acres of land. Requirements: The pool requires locker room facilities which would be in the recreation...
please answer question #4 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven...
please answer #2 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven popular....
please answer #5 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven popular....
SYNOPSIS The product manager for coffee development at Kraft Canada must decide whether to introduce the company's new line of single-serve coffee pods or to await results from the product's launch in the United States. Key strategic decisions include choosing the target market to focus on and determining the value proposition to emphasize. Important questions are also raised in regard to how the new product should be branded, the flavors to offer, whether Kraft should use traditional distribution channels or...